Weighted, load-balancing resource scheduling algorithm - algorithm

A software application that I'm working on needs to be able to assign tasks to a group of users based on how many tasks they presently have, where the users with the fewest tasks are the most likely to get the next task. However, the current task load should be treated as a weighting, rather than an absolute order definition. IOW, I need to implement a weighted, load-balancing algorithm.
Let's say there are five users, with the following number of tasks:
A: 4
B: 5
C: 0
D: 7
E: 9
I want to prioritize the users for the next task in the order CABDE, where C is most likely to get the assignment and E, the least likely. There are two important things to note here:
The number of users can vary from 2 to dozens.
The number of tasks assigned to each user can vary from 1 to hundreds.
For now, we can treat all tasks as equal, though I wouldn't mind including task difficult as a variable that I can use in the future - but this is purely icing on the cake.
The ideas I've come up with so far aren't very good in some situations. They might weight users too closely together if there are a large number of users, or they might fall flat if a user has no current tasks, or....
I've tried poking around the web, but haven't had much luck. Can anyone give me a quick summary of an algorithm that would work well? I don't need an actual implementation--I'll do that part--just a good description. Alternative, is there a good web site that's freely accessible?
Also, while I certainly appreciate quality, this need not be statistically perfect. So if you can think of a good but not great technique, I'm interested!

As you point out, this is a load-balancing problem. It's not really a scheduling problem, since you're not trying to minimise anything (total time, number of concurrent workers, etc.). There are no special constraints (job duration, time clashes, skill sets to match etc.) So really your problem boils down to selecting an appropriate weighting function.
You say there are some situations you want to avoid, like user weightings that are too close together. Can you provide more details? For example, what's wrong with making the chance of assignment just proportional to the current workload, normalised by the workload of the other workers? You can visualise this as a sequence of blocks of different lengths (the tasks), being packed into a set of bins (the workers), where you're trying to keep the total height of the bins as even as possible.
With more information, we could make specific recommendations of functions that could work for you.
Edit: example load-balancing functions
Based on your comments, here are some example of simple functions that can give you different balancing behaviour. A basic question is whether you want deterministic or probabilistic behaviour. I'll give a couple of examples of each.
To use the example in the question - there are 4 + 5 + 0 + 7 + 9 = 25 jobs currently assigned. You want to pick who gets job 26.
1) Simple task farm. For each job, always pick the worker with the least jobs currently pending. Fast workers get more to do, but everyone finishes at about the same time.
2) Guarantee fair workload. If workers work at different speeds, and you don't want some doing more than others, then track the number of completed + pending jobs for each worker. Assign the next job to keep this number evenly spread (fast workers get free breaks).
3) Basic linear normalisation. Pick a maximum number of jobs each worker can have. Each worker's workload is normalised to that number. For example, if the maximum number of jobs/worker is 15, then 50 more jobs can be added before you reach capacity. So for each worker the probability of being assigned the next job is
P(A) = (15 - 4)/50 = 0.22
P(B) = (15 - 5)/50 = 0.2
P(C) = (15 - 0)/50 = 0.3
P(D) = (15 - 7)/50 = 0.16
P(E) = (15 - 9)/50 = 0.12
If you don't want to use a specific maximum threshold, you could use the worker with the highest current number of pending jobs as the limit. In this case, that's worker E, so the probabilities would be
P(A) = (9 - 4)/20 = 0.25
P(B) = (9 - 5)/20 = 0.2
P(C) = (9 - 0)/20 = 0.45
P(D) = (9 - 7)/20 = 0.1
P(E) = (9 - 9)/20 = 0
Note that in this case, the normalisation ensures worker E can't be assigned any jobs - he's already at the limit. Also, just because C doesn't have anything to do doesn't mean he is guaranteed to be given a new job (it's just more likely).
You can easily implement the choice function by generating a random number r between 0 and 1 and comparing it to these boundaries. So if r is < 0.25, A gets the job, 0.25< r < 0.45, B gets the job, etc.
4) Non-linear normalisation. Using a log function (instead of the linear subtraction) to weight your numbers is an easy way to get a non-linear normalisation. You can use this to skew the probabilities, e.g. to make it much more likely that workers without many jobs are given more.
The point is, the number of ways of doing this are practically unlimited. What weighting function you use depends on the specific behaviour you're trying to enable. Hopefully that's given you some ideas which you can use as a starting point.

Related

Algorithm to find the correct combination in a fast manner

Assume I have 4 lists: jobs, workers, mechanisms and mechanism equipment.
Currently I am firstly looping through jobs, lets call this the
jobLoop.
Inside jobLoop I'm looping through workerLoop, checking if
worker is available and has required competences to do the job.
If worker is OK, I'm looping through mechanismLoop, checking if worker can use the mechanism and if the mechanism is available. If no mechanisms are available, I fall back to workerLoop, looking for another correct worker.
If mechanism is OK, I loop through mechEquipmentLoop, checking checking if worker can use the equipment and if the equipment is available. If no equipment is available, I fall back to mechanismLoop, looking for another correct mechanism.
If mechanism equipment is finally okay, the algorithm is done. If not, the algorithm says items cannot be matched.
This is a simplified version, on each step there are many checks like if worker is allowed on the object where the job is done and so on.
I'm trying to think of a more efficient way to do this. Currently the time complexity for this algorithm should be roughly O(n^4), right? I'm not looking for code, just guidance on how to perform this.
IMHO - this algorithm is O(jwm*e) instead of O(n^4). j = number of jobs, w = number of workers, m= number of mechanisms, e = number of mech equipment.
If these lists don't change & if the answer is needed only once this is the best algorithm to execute. You need to visit all the inputs once at least.
Suppose these lists change and the same algo needs to execute for a given job multiple times you can do this.
Store the list of workers in BST (or a self-balanced tree-like AVL) with job competency as key. Suppose if there are multiple competencies for a worker then his data will be in all the competencies. The creation of the tree is O(wlogw) here w is the number of unique competency & worker combinations, not workers number alone. Deletion, Addition & Search will be O(logw). Here are we are assuming that competency - worker distribution is decent. Suppose if all workers have only one competency this will become O(w) once again.
The same applies to mechanism and equipment. This will make the search at every level to O(logm) and O(loge).
So for every job best case scenario of allocation is O(logw * logm * loge), with a overhead of O(wlogw + mlogm + eloge). For all jobs it will be (j * logw * logm * loge).

Sampling from discrete distribution without replacement where the probabilities change each draw

I have a sequence S = (s1,s2,...sk) with probability weights for each sequence site P = (p1,p2,...pk) where the sum of P = 1 maximum length of S may be around 10^9
By Simulation a site k is picked and modified after each draw , as reason the pk also changes each run through. Expected number of site exchanges is about 50k - 100k per simulation
Question 1: How would you suggest to draw site?
Actually I implemented this logic which seems to be ok itself as going along literature see e.g. here:
counter = 0
random_number = draw_random() #<= float in range 0,1
while P_sum < random_number
P_sum += P[counter]
counter++
return counter
By testing the simulation I observed a strong bias which seems to rebuilt random generators distribution ( see_here ) Three different generators generate 3 different results... which is fairly ok but none of them is correct at all states
Walkers and Knuth's methods with lookup table seem to be too time expensive for me as the lookup tables have to be recalculated each time.
Question 2 How can I reduce bias from randomness? Actual built in 3 different generators (only one used per simulation) which are uniform distributed in kindness to their chances. Knowing this is a heavy question when not knowing a line of simulation code
Question 3 Library for the thing ?
As it's not to much code I don't have problem to write on my own, but is there a another library for it which may not BOOST? Asking as this question may be outdated... Not Boost as I don't want to built in a fourth random generator and use that large thing
Question 4 Faster alternative?
I know that this topic was answered may thousands of time before - but none of the answers satisfies me enough nor gave me a wise alternative e.g. here seems to have the same problem but I don't understand which heap is where built and why in addition it seems very complicated for such a "easy" thing
Thank you for your support!

load balancing algorithms - special example

Let´s pretend i have two buildings where i can build different units in.
A building can only build one unit at the same time but has a fifo-queue of max 5 units, which will be built in sequence.
Every unit has a build-time.
I need to know, what´s the fastest solution to get my units as fast as possible, considering the units already in the build-queues of my buildings.
"Famous" algorithms like RoundRobin doesn´t work here, i think.
Are there any algorithms, which can solve this problem?
This reminds me a bit of starcraft :D
I would just add an integer to the building queue which represents the time it is busy.
Of course you have to update this variable once per timeunit. (Timeunits are "s" here, for seconds)
So let's say we have a building and we are submitting 3 units, each take 5s to complete. Which will sum up to 15s total. We are in time = 0.
Then we have another building where we are submitting 2 units that need 6 timeunits to complete each.
So we can have a table like this:
Time 0
Building 1, 3 units, 15s to complete.
Building 2, 2 units, 12s to complete.
Time 1
Building 1, 3 units, 14s to complete.
Building 2, 2 units, 12s to complete.
And we want to add another unit that takes 2s, we can simply loop through the selected buildings and pick the one with the lowest time to complete.
In this case this would be building 2. This would lead to Time2...
Time 2
Building 1, 3 units, 13s to complete
Building 2, 3 units, 11s+2s=13s to complete
...
Time 5
Building 1, 2 units, 10s to complete (5s are over, the first unit pops out)
Building 2, 3 units, 10s to complete
And so on.
Of course you have to take care of the upper boundaries in your production facilities. Like if a building has 5 elements, don't assign something and pick the next building that has the lowest time to complete.
I don't know if you can implement this easily with your engine, or if it even support some kind of timeunits.
This will just result in updating all production facilities once per timeunit, O(n) where n is the number of buildings that can produce something. If you are submitting a unit this will take O(1) assuming that you keep the selected buildings in a sorted order, lowest first - so just a first element lookup. In this case you have to resort the list after manipulating the units like cancelling or adding.
Otherwise amit's answer seem to be possible, too.
This is NPC problem (proof at the end of the answer) so your best hope to find ideal solution is trying all possibilities (this will be 2^n possibilities, where n is the number of tasks).
possible heuristic was suggested in comment (and improved in comments by AShelly): sort the tasks from biggest to smallest, and put them in one queue, every task can now take element from the queue when done.
this is of course not always optimal, but I think will get good results for most cases.
proof that the problem is NPC:
let S={u|u is a unit need to be produced}. (S is the set containing all 'tasks')
claim: if there is a possible prefect split (both queues finish at the same time) it is optimal. let this time be HalfTime
this is true because if there was different optimal, at least one of the queues had to finish at t>HalfTime, and thus it is not optimal.
proof:
assume we had an algorithm A to produce the best solution at polynomial time, then we could solve the partition problem at polynomial time by the following algorithm:
1. run A on input
2. if the 2 queues finish exactly at HalfTIme - return True.
3. else: return False
this solution solves the partition problem because of the claim: if the partition exist, it will be returned by A, since it is optimal. all steps 1,2,3 run at polynomial time (1 for the assumption, 2 and 3 are trivial). so the algorithm we suggested solves partition problem at polynomial time. thus, our problem is NPC
Q.E.D.
Here's a simple scheme:
Let U be the list of units you want to build, and F be the set of factories that can build them. For each factory, track total time-til-complete; i.e. How long until the queue is completely empty.
Sort U by decreasing time-to-build. Maintain sort order when inserting new items
At the start, or at the end of any time tick after a factory completes a unit runs out of work:
Make a ready list of all the factories with space in the queue
Sort the ready list by increasing time-til-complete
Get the factory that will be done soonest
take the first item from U, add it to thact factory
Repeat until U is empty or all queues are full.
Googling "minimum makespan" may give you some leads into other solutions. This CMU lecture has a nice overview.
It turns out that if you know the set of work ahead of time, this problem is exactly Multiprocessor_scheduling, which is NP-Complete. Apparently the algorithm I suggested is called "Longest Processing Time", and it will always give a result no longer than 4/3 of the optimal time.
If you don't know the jobs ahead of time, it is a case of online Job-Shop Scheduling
The paper "The Power of Reordering for Online Minimum Makespan Scheduling" says
for many problems, including minimum
makespan scheduling, it is reasonable
to not only provide a lookahead to a
certain number of future jobs, but
additionally to allow the algorithm to
choose one of these jobs for
processing next and, therefore, to
reorder the input sequence.
Because you have a FIFO on each of your factories, you essentially do have the ability to buffer the incoming jobs, because you can hold them until a factory is completely idle, instead of trying to keeping all the FIFOs full at all times.
If I understand the paper correctly, the upshot of the scheme is to
Keep a fixed size buffer of incoming
jobs. In general, the bigger the
buffer, the closer to ideal
scheduling you get.
Assign a weight w to each factory according to
a given formula, which depends on
buffer size. In the case where
buffer size = number factories +1, use weights of (2/3,1/3) for 2 factories; (5/11,4/11,2/11) for 3.
Once the buffer is full, whenever a new job arrives, you remove the job with the least time to build and assign it to a factory with a time-to-complete < w*T where T is total time-to-complete of all factories.
If there are no more incoming jobs, schedule the remainder of jobs in U using the first algorithm I gave.
The main problem in applying this to your situation is that you don't know when (if ever) that there will be no more incoming jobs. But perhaps just replacing that condition with "if any factory is completely idle", and then restarting will give decent results.

slot machine payout calculation

There's this question but it has nothing close to help me out here.
Tried to find information about it on the internet yet this subject is so swarmed with articles on "how to win" or other non-related stuff that I could barely find anything. None worth posting here.
My question is how would I assure a payout of 95% over a year?
Theoretically, of course.
So far I can think of three obvious variables to consider within the calculation: Machine payout term (year in my case), total paid and total received in that term.
Now I could simply shoot a random number between the paid/received gap and fix slots results to be shown to the player but I'm not sure this is how it's done.
This method however sounds reasonable, although it involves building the slots results backwards..
I could also make a huge list of all possibilities, save them in a database randomized by order and simply poll one of them each time.
This got many flaws - the biggest one is the huge list I'm going to get (millions/billions/etc' records).
I certainly hope this question will be marked with an "Answer" (:
You have to make reel strips instead of huge database. Here is brief example for very basic 3-reel game containing 3 symbols:
Paytable:
3xA = 5
3xB = 10
3xC = 20
Reels-strip is a sequence of symbols on each reel. For the calculations you only need the quantity of each symbol per each reel:
A = 3, 1, 1 (3 symbols on 1st reel, 1 symbol on 2nd, 1 symbol on 3rd reel)
B = 1, 1, 2
C = 1, 1, 1
Full cycle (total number of all possible combinations) is 5 * 3 * 4 = 60
Now you can calculate probability of each combination:
3xA = 3 * 1 * 1 / full cycle = 0.05
3xB = 1 * 1 * 2 / full cycle = 0.0333
3xC = 1 * 1 * 1 / full cycle = 0.0166
Then you can calculate the return for each combination:
3xA = 5 * 0.05 = 0.25 (25% from AAA)
3xB = 10 * 0.0333 = 0.333 (33.3% from BBB)
3xC = 20 * 0.0166 = 0.333 (33.3% from CCC)
Total return = 91.66%
Finally, you can shuffle the symbols on each reel to get the reels-strips, e.g. "ABACA" for the 1st reel. Then pick a random number between 1 and the length of the strip, e.g. 1 to 5 for the 1st reel. This number is the middle symbol. The upper and lower ones are from the strip. If you picked from the edge of the strip, use the first or last one to loop the strip (it's a virtual reel). Then score the result.
In real life you might want to have Wild-symbols, free spins and bonuses. They all are pretty complicated to describe in this answer.
In this sample the Hit Frequency is 10% (total combinations = 60 and prize combinations = 6). Most of people use excel to calculate this stuff, however, you may find some good tools for making slot math.
Proper keywords for Google: PAR-sheet, "slot math can be fun" book.
For sweepstakes or Class-2 machines you can't use this stuff. You have to display a combination by the given prize instead. This is a pretty different task, so you may try to prepare a database storing the combinations sorted by the prize amount.
Well, the first problem is with the keyword assure, if you are dealing with random, you cannot assure, unless you change the logic of the slot machine.
Consider the following algorithm though. I think this style of thinking is more reliable then plotting graphs of averages to achive 95%;
if( customer_able_to_win() )
{
calculate_how_to_win();
}
else
no_win();
customer_able_to_win() is your data log that says how much intake you have gotten vs how much you have paid out, if you are under 95%, payout, then customer_able_to_win() returns true; in that case, calculate_how_to_win() calculates how much the customer would be able to win based on your %, so, lets choose a sampling period of 24 hours. If over the last 24 hours i've paid out 90% of the money I've taken in, then I can pay out up to 5%.... lets give that 5% a number such as 100$. So calculate_how_to_win says I can pay out up to 100$, so I would find a set of reels that would pay out 100$ or less, and that user could win. You could add a little random to it, but to ensure your 95% you'll have to have some other rules such as a forced max payout if you get below say 80%, and so on.
If you change the algorithm a little by adding random to the mix you will have to have more of these caveats..... So to make it APPEAR random to the user, you could do...
if( customer_able_to_win() && payout_percent() < 90% )
{
calculate_how_to_win(); // up to 5% payout
}
else
no_win();
With something like that, it will go on a losing streak after you hit 95% until you reach 90%, then it will go on a winning streak of random increments until you reach 95%.
This isn't a full algorithm answer, but more of a direction on how to think about how the slot machine works.
I've always envisioned this is the way slot machines work especially with video poker. Because the no_win() function would calculate how to lose, but make it appear to be 1 card off to tease you to think you were going to win, instead of dealing with a 'fair' game and the random just happens to be like that....
Think of the entire process of.... first thinking if you are going to win, how are you going to win, if you're not going to win, how are you going to lose, instead of random number generators determining if you will win or not.
I worked many years ago for an internet casino in Australia, this one being the only one in the world that was regulated completely by a government body. The algorithms you speak of that produce "structured randomness" are obviously extremely complex especially when you are talking multiple lines in all directions, double up, pick the suit, multiple progressive jackpots and the like.
Our poker machine laws for our state demand a payout of 97% of what goes in. For rudely to be satisfied that our machine did this, they made us run 10 million mock turns of the machine and then wanted to see that our game paid off at what the law states with the tiniest range of error (we had many many machines running a script to auto playing using a script to simulate the click for about a week before we hit the 10 mil).
Anyhow the algorithms you speak of are EXPENSIVE! They range from maybe $500k to several million per machine so as you can understand, no one is going to hand them over for free, that's for sure. If you wanted a single line machine it would be easy enough to do. Just work out you symbols/cards and what pay structure you want for each. Then you could just distribute those payouts amongst non-payouts till you got you respective figure. Obviously the more options there are means the longer it will take to pay out at that respective rate, it may even payout more early in the piece. Hit frequency and prize size are also factors you may want to consider
A simple way to do it, if you assume that people win a constant number of times a time period:
Create a collection of all possible tumbler combinations with how much each one pays out.
The first time someone plays, in that time period, you can offer all combinations at equal probability.
If they win, take that amount off the total left for the time period, and remove from the available options any combination that would payout more than you have left.
Repeat with the reduced combinations until all the money is gone for that time period.
Reset and start again for the next time period.

How to spread processes over time getting minimum number of "collisions"

I'm developing a scheduler for an embedded system.
This scheduler will call each process every X milliseconds; this time can be configured separately for each process, of course.
Everything is coded and calls every process as it should; the problem I'm facing is this:
Imagine I set 4 processes to be called every 10, 15, 5 and 30 milliseconds respectively:
A: 10ms
B: 15ms
C: 5ms
D: 30ms
The resulting calling over time will be:
A |
A B A B |
C C C C C C C | processes being called
D |
----------------------------------
0 5 10 15 20 25 30 35... ms
The problem is that when 30ms is reached, all processes are called at the same moment (one after another) and this can delay the correct execution from here.
This can be solved by adding a delay to each process (but preserving its calling frequency), so the frequencies stops being multiples of each other. My problem is that I don't know how to calculate the delay to apply to each process so the number of collisions is minimized.
Is there any known algorithm for this, or some mathematical guidance?
Thank you.
Given a set of intervals, you can find the time at which the start times would coincide (assuming no offsets) by finding the least common multiple as mentioned by Jason in a comment to your post. You can find the LCM by doing the prime factorization of the intervals for a set of tasks.
It seems, though, that the greatest common divisor (or greatest common factor GCF) might be the most useful number to compute. That number will give you interval at which repeats will happen. In your example, the GCF is 5. With a GCF of 5, it is possible to add an initial offset of 1, 2, 3, etc. to each task to avoid overlapping start times. Thus, with a GCF of 5, you can have up to 5 tasks that have start times that would never overlap. With a GCF of 20, you could have up to 20 tasks scheduled with no overlapping start times. If two (or more) tasks are relatively prime (GCF=1), then an overlap will definitely occur no matter what offset you use for those tasks if the intervals never change.
There is no perfect solution for this, they will collide from time to time.
I would suggest to add tiny(0.01-0.1ms) random value to cycle length, so in the long term they will really rarely called at the same time.
Alternatively, if you have 5ms scheduler granularity, first thread is always called at X+1ms, second at X+2, e.t.c, so that it is always guaranteed 1ms of uninterrupted run (if you have 10 threads, then it will be X+0.5, X+1, X+1.5). But this might get quite tricky to implement.
This kind of problem relates directly the domain of real-time programming and scheduling algorithms. I took a class on this subject in college, and if I remember well, Rate-monotonic scheduling is the kind of algorithm you are looking for.
The idea is that you assign priorities to jobs that are inversely proportional to their period, ie the smaller the period, the higher the priority. But this works better if you can interrupt your jobs and resume them later.
There are other alternatives, though, like EDF (earliest deadline first), but these are dynamic scheduling algorithms (ie the priorities are assigned during the execution).
The easy solution is to change the schedule in which you call the subroutines. I.e. instead of 5, 10, 15, and 30 ms, can you live e.g. with 5, 15, 15 and 30? Then you can use the following pattern: (A=5 ms proc, B,C=15 ms proc, D=30 ms proc):
AAAAAAAAAAAAAAAAAAAA ...
B B B B B B B ...
C C C C C C C ...
D D D ...
I'm sure you can generalize this idea, but it works only if you can actually change the static intervals.
If you can't change the intervals, and also you need to obey them strictly, then I you are kind of out of luck as there are no parameters to change :)