What metrics to calculate if writing specification is worth its time? - metrics

What metrics to use and how to make calculations if writing specification for a new programming project is worth doing it and spending time (and money)?

I think you'll find yourself backed into an uncomfortable corner if you try to use any metric to definitively predict or control the outcome of your project. Ultimately, your project sponsor/owner will ask the questions "how long/how much" ? The best you can do is a forecast that is based on your current knowledge of the project at this point in time - and this just comes from experience and literally guess-timating.
And here's the catch: Your estimates will likely be off by several orders of magnitude. They only become more accurate as your team understands the problem domain and they estimate no more than 2-4 weeks ahead, max. Barry Boehm (and Steve McConnell) illustrated this effect with the "cone of uncertainty" principle:
The further you are from implementation of a system or feature (left side), the greater the innacuracy of your estimates (-0.25x - 4x). As you get closer, and understand the problem domain more, estimates begin to take on greater accuracy (0.8x - 1.0x). This is why, in software projects where there is a lot of "noise", or "complexity" (ie. almost every project) we want to leave concrete estimation until the last responsible moment - no more than 2-4 weeks out.
You can also expect one thing with absolute certainty: The specifications WILL change over time. How you plan to adapt and manage that change will measure your success.
So, the best judgement that can be made to scope your work would be to assemble the team who will work on the project and the "customer" to collaboratively work out the big brush strokes - the major features of the project. Write these as user stories that the team estimates using relative weight points (see Mike Cohn's book on Agile Estimating and Planning) and devise a release plan that will give the customer a "draft" forecast on what to expect - they can then decide if the investment will generate the return they are looking for.
Of course, I'm assuming that you'll be releasing early/often so that your customer is always in possession of some functional increment of the final product - vital for their continued valuation of the project.

In general small, straightforward, non-critical project: no specs. Large, complex, critical project: definitely specs.
There perhaps cannot be any cut-and-dried metrics here. You'll have to rely on your software engineering judgment.

In general, you should always write out specifications. You should need to be convinced not to.
If you have more than one person on a project, you'll definitely need specifications.
If a single person project will take more than a week, you'll probably need specifications.
If there has ever been confusion or communication difficulties between you and your client, then signed specifications are a must.

Focus on essence and what's most important to your customer. The overall business goals and visions. I like the "elevator test" - to be able to explain what your product does in under two minutes:
for (target customer)
who (statement of need or opportunity)
the (product name) is a (product category)
that (key benefit, compelling reason to buy)
unlike (primary competitive alternative)
our product (statement of primary differentiation)
(from Geoffrey Moore's book Crossing the Chasm)
Perhaps this doesn't answer your question, but writing such a small "specification" could be done for any project.

Related

Estimating a project with many unknowns

I'm working on a project with many unknowns like moving the app from one platform to another.
My original estimations are way off and there is no way I can really know for sure when this will end.
How can i deal with the inability to estimate such a project. It's not that I'm adding a button to a screen or designing a web site, or creating and app or even fixing bugs. These are not methods with bugs, these are assumptions made in the overall code, which are not correct anymore and are found step by step and each analyzed and mitigated with many more unknowns.
I happened to write a master thesis about software-estimation and there are lessons I've learned:
-1st Count, 2nd compute, 3rd judge - this means: first try to identify items in your work which are countable e.g files, classes, LOCs, UIs, etc. Then calculate using this data the effort (in person/days). Use judgement as the last ressort.
-Document your estimation! Show numbers. This minimizes your risk, thus you will present results not as your opinion, but as more or less objective figures. (In general, the more paper the cleaner the backside)
-Estimation is not a commitment. Commitment is one number, estimation is always a range - so give your estimation as a range ( use cone of uncertainty to select the range properly http://www.construx.com/Page.aspx?hid=1648 )
-Devide: Use WBS, devide your work in small pieces and estimate them separately. The granulity depents on the entire length, but at most a working-package soultn't be bigger than 10% of entire effort.
-Estimate effort first, then schedule, then costs.
-Consider estimation as support for planing, reestimate on each project phase (s. cone of uncertainty).
I would suggest the book http://www.stevemcconnell.com/est.htm which deals all these points, in particular how to deal with bosses, who try to pull a commitment from you.
Regards,
Valentin Heinitz
There's no really right answer for coming up with an accurate estimation, because there's no way to know it.
as for estimating the work itself, think about how each step can be divided into separate sub-steps, and break those down even smaller, until you can get a fair picture of as much of the work as you can, with chunks small and discreet enough to give sound estimates for. If you can, come up with both an expected time and a worst-case time, to get a range of where you could land.
Another way to approach this is to ignore the old system. It sounds like a headache. Make an estimate of scraping the old system and implementing a new one from scratch, or integrating a 3rd party, off the shelf solution. If there's a case to be made for this, it is worth at least investigating it.
Sounds like a post for postsecret not SO. :)
I would tell him that it will be done when its done, and if thats not good enough, he can learn to program and help you. Then again, I think that you might get fired, but hey that sounds like it might be better.
Tell him more or less what you told us. The project is too volatile too give an accurate estimate and the best you can do is give an estimate for a given task. As long as the number of tasks is unknown so will be the estimate. If he is at all worth his salary he would rather hear this than some made up number. This is not uncommon when dealing with a large legacy code base.
It's not that I'm adding a button to a screen or designing a web site,
or creating and app or even fixing bugs.
That is a real problem. You can not estimate what you don't have experience in. The only thing you can do is pad your estimate until you think it is a reasonable amount of time. The more unknowns you think there are the more you pad. The less you know about it the more you pad.
I read the below book and it spoke at length about accuracy vs precision. Basically you can be accurate but have a very large range. For instance you can be certain the task will be between 1 day and 1 year to complete. That is not very precise but it is really accurate.
Software Estimation Demystifying...
Some tips for estimating

using software metrics for measuring productivity of pair programming

what are the software metrics that can be used to measuring the performance of pair programming ?
to be clear
is there any metrics used to measure pair programming specifically and does not use to measure the individual programmer ? what are the parameters used for measuring ?
for example:if we want to measure the cost for both individual and pair programming
let's assume that for the individual programming Cost = x so for the pair will be Cost = 2* x
right
and the same for the time for individual Time = t while for pair Time = 2* t
so if I would like to use Lines of code for measuring the product size , is there any different between individual and pair by using this metric?
any idea
Sorry to spoil your party, but lines of code is one of the worst metrics possible, especially if people know their assessment or bonus is in any way tied to the metric. It actively encourages cut and paste programming and other attrocities. It's more effort, but why don't you categorise the workload in terms of expected effort for one person, based on your historical data? Or, get some programmers to agree to do a few projects redundantly, rotating between pair-programming and individual, so you can see how the same programmers go at each. As one good programmer can be more productive than two average programmers (I vaguely remember an old IBM study concluding someone in the top percentile was 27x more productive than median), it's useful to see the same programmers doing it both ways. If objectively discovering the right process through such an experiment is too costly in terms of lost short-term productivity, then you're better off not bothering with the LOC metrics anyway... good programmers knowing their work arrangements are being based on such will probably be highly unimpressed.
Remember that there are also intangibles involved... pair programming - IMHO - forces people to keep focused, and to make design decisions that are more rounded and professional. Just the social contact can help relieve boredom, though it may stress some people too. My suspicion is that - whether or not it's faster to begin with - it makes for better, more maintainable results. It also ensures skill and knowledge transfer. You should factor in such intangible aspects as best you can - maybe doing interviews or anonymous surveys with the trial participants.
I guess what you try to ask, is how to measure efficiency of the team that uses pair programming. If yes, then answer is the measurement of efficiency doesn't depend on method or proccess of work team is using. You should try to evaluate the quality of their product releases, with metrics like number of issues identified post release. Probably the velocity.
and, please, don't use lines of code for efficiency measurement. It doesn't make sense. Lines of code is a measure of product size and not developer efficiency. It's like using height or weight to judge how smart you are. There is no correlation between amount of code and individual efficiency.
if you are interested in more software metrics, take a look at http://www.sdlcmetrics.org

How to manage agile development when the team is not stable? [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
I have been using agile approaches (XP and Scrum) for my projects for several years with great results. But in all cases, all members of the dev team were committed 100% to the project.
Now I am faced with doing this when the team is not stable. For instance, one iteration there may be four people working, the next maybe only two or three.
I realize this makes it hard (or impossible) to estimate using the normal velocity approach since it will fluctuate to much and not be stable. What follows is that one cannot really expect to be able to release at the end of each iteration.
Maybe another approach is needed here. Just grab stuff from the backlog and just muddle through and release whenever it is possible. I really don't like that though...
Any thoughts?
From the question I assume you have some developers (probably, 2) 100% commited to the project and some (another 2-3) only participate at a times.
One thing you can do is set different process for core developers who are 100% commited and everyone else. Use you normal agile process for core people and release their work at normal iteration cycle. For non-core people, do little planning and assume their (and your) estimates would be way of at a times. Ideally their changes should be isolated and merged into stable branch of code by core members, but not every project's architecture and team roles allow this.
The point is to separate and isolate source of chaos and leave the heart of a project and team unaffected.
Maybe instead of agile approaches, you can slow things down with other iterative and incremental approaches. Instead of having iterations measured in weeks, having longer iterations (perhaps measured in months) would be better if you keep adding and dropping people from the team.
This doesn't mean that you still can't use some Agile techniques. I would still maintain your Backlogs and burn down charts, with the realization that instead of having a release every 2 weeks, you'll release every 6 weeks (~2 months). If you have new developers joining more experienced developers, use pair programming, assign the new developers to bug fixes, or assign the new developers to maintaining unit tests to help them learn the code base.
Velocity is only an estimation.
Naively, if you have a given velocity v with a team of 4 developers, then schedule your iteration with a velocity of (v/4)*number_of_developers
You can fudge this value if the members you are losing are particularly stronger or weaker than the average.
This is basically what PivotalTracker does with its team strength metric.
So, you have a project with a continually changing team size and your boss wants you to give him an accurate estimate of how long it will take? You can do this, as long as you keep in mind the difference between accurate and precise. Your precision will depend largely on the number of items and how granular (decomposed) each item is; the more items you have the more the Law of Large Numbers works for you, averaging out over- and underestimates.
Your accuracy is a function of confidence. Note that estimates aren't single-point values, they're a range with numbers with a percentage of confidence. For instance, a proper estimate wouldn't be "2 weeks" it would be "50% confidence of 2 weeks, 80% confidence of 4 weeks."
If I were the person assigned with the unenviable task of providing an estimate to completion for a project being managed as arbitrarily as in the original post, I'd try to figure out a range based upon the minimum number of folks assigned (e.g., "48 to 66 weeks given 2 developers [50% to 80% confident]"), and a range associated with the average number of folks assigned (e.g., "25 to 45 weeks with 5 developers [50% to 80% confident]"), and use the low figure from the average number along with the high figure from the minimum number (e.g., "25 to 66 weeks given anywhere from 2 to 5 developers [50% to 80% confident]"), and even then I'd put a disclaimer on it ("plus 10% for the lost time due to context switching").
Better yet, I'd explain exactly why this arrangement was, to be polite, sub-optimal, and why multi-tasking is a primary signpost on the road to project Hell.
As someone else suggested, changing the workflow from iteration-based to flow-based (Kanban) might well be a good strategy. With Kanban you handle changing project priorities by changing the priority of items in the backlog; once an item has been grabbed by the team it is generally finished (flows all of the way through the workflow, stakeholders aren't allowed to disrupt the team by screwing around with work-in-progress). I've used Kanban for sustained engineering projects and it worked very well. Re how it would help with estimates, the key to continuous flow is to try to have each work item be roughly the same size (1x, 2x, 3x, not 10x, 20x, 100x). You should track movement of items through the workflow by tracking dates of process state changes, e.g., Queue 1/15, Design 1/22, Dev 1/24, Test 2/4, Integrate 2/7, etc., and then generating a cumulative flow diagram regularly to evaluate the time-in-state durations over time. Working out how long the project should take given that you know the size of each item and the time through the workflow for items is a trivial computational exercise left to the reader. (The more interesting question is how to spot constraints... and then how to remove them. Hint: look for long times in states, because work piles up in front of constraints.)
Let the individual developer that will be working on the story estimate the effort required to complete the story. You can take into account historical variances in that developer's estimations, but the idea is that you can take their estimates and then figure out how many stories you'll be able to finish in that sprint.
Don't forget that average velocity is largely used for lookahead release planning; the team is responsible for selecting in each iteration how many backlog items to take on (although knowing historical velocity can assist them).
If your team size (and hence velocity) is fluctuating from iteration to iteration, you can still do useful release planning by using average velocities over the past N sprints, assuming the team fluctuations will continue and hence their long-term average velocity will actually be stable.
Your main problem here is that the team will find it hard to give predictable estimates and deliveries since the team is changing from sprint to sprint. This can also hurt the team commitment and continuous improvement.
This case might actually be well suited for a Kanban approach. Check out Henrik Knibergs introduction to Kanban for a quick overview.
Good luck!

Scrum in a fixed cost project [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
I have read the agile manifesto and spend a nice day surfing the web in search for this elusive answer. But sadly I did not get an answer that would cover all the bases.
When watching all the blog posts and newscasts of Agile preachers, you just hear about open scope or open "time" projects. How do you apply this to a fix cost project?
From what I found out the biggest problem is scope management. How do you determine if something is not inside the projected scope and how do you formulate arguments for your decision? Because of the agile way you are implementing your software there is no detailed design to argue upon. In most cases you only have a vague wish-list that the customer hands to you. And is so general that you can interpret any feature into it.
And with the rising percentage of fixed-cost projects this seams to me to be a real issue.
So the questions would be:
How do you manage scope in a fix cost project?
How do you determine if the features wished for, are outside the original scope?
To me, the short answer about Agile and fixed price is that you can't do it, at least not with a fixed scope.
I know some people will say "that's not true, we are doing it" but, with all due respect, I don't think they are really doing Agile and I'll explain why. Actually the explanation is quite simple: fixed price implies fixed scope and is based on predictability where Agile is all about variable scope, scope management and adaptivity. So fixed price with fixed scope is basically the opposite of Agile.
With an Agile approach, fixed price gives you a number of iterations for a given team size. During these iterations, the customer will be able to have the team build the most valuable features first and thus to maximize the generated business value. The whole idea is then to stop iterating when the cost of an iteration is greater than the generated value. This is how Agile works.
So when people says they do fixed price with fixed scope in an agile way, they actually introduce some constraints that are not really compatible with the Agile theory - like doing an up-front estimation of a given set of features and freezing these features and estimations - and they loose important advantages of Agile (unless they have a perfect knowledge of the technologies and of the business domain and master them enough to predict everything but I know few projects that are like this).
Here is anyway a good compilation of various Agile contracts: 10 Contracts for your next Agile Software Project that might be helpful. But I think they all require some education of customers, especially the one that are used to fixed price with fixed scope (and late deliveries).
Scrum does not replace having proper requirements, or even having occasional major releases or milestones. Rather, it gives you a means to keep your team productive and focused, and avoids the time-wasting side-effects of a waterfall process.
In fact, one of the biggest advantages of an agile process like Scrum is that it causes you to "fail quickly and loudly" on problematic areas of your project. If, after a couple of sprints, your team still can't effectively estimate the time and resources needed to implement a particular feature, it may be worth pushing back on the requirements in that area -- they may need to be clarified, simplified, or scrapped altogether. In a traditional waterfall process, however, those "problem features" can often be pushed back to the last possible minute, resulting in the usual deathmarch and under-delivery into which most projects devolve.
However, the role of the Product Owner is even more critical in teams using Scrum who have a large set of requirements. Left to their own devices, most development teams will focus on the most interesting/fun/geeky features (service APIs, caching, search) first, and leave the "messy" stuff like payment process, UX design, and i18n until the last minute. A strong user voice is essential to making sure those features critical to the end user receive their fair share of attention.
Okay, this will not be the ideal answer you are looking for, but may help non-the-less.
For your first point:
With agile, and Scrum in particular, the style is suited toward changing specifications and unfixed deadlines using iteration patterns. To be able to manage this in a fixed scope project will be a nightmare. What one would normally do is set a budget for the specified scope, and any addendum to this would produce billable hours above and beyond the scoped budget. To do this in Scrum would be pointless, as the product backlog will be continually filled by the stakeholders. If there is no "punishment" for scope changes in a fixed budget, there will be nothing holding people back from just loading on to you.
The alternative here is to have fixed scope sprint successions, so for instance:
5x Sprints = x Cost with minimal scope change.
For your second point:
The use of Analysis and Design is an invaluable tool. By using use cases, event tables, sequence diagrams, state machines and the like; you will be saving yourselves oceans of tears in the long run. Basically, once the planning has been done, any addendum to this that requires additional (please note additional, not things that have been overlooked) use cases and large code changes will be out of scope. In fact, anything that was not overlooked in the planning and is not in your specification, is out of scope.
In closing, you will need to have very well planned documentation as well as very solid agreements with your clients to be able to pull this off 100%.
I hope this helps.
I worked in a environment where we had fixed cost and fixed time projects. We has switched to a Scrum-esque methology from a Waterfall/VModel methology. Scrum can work very well in fixed cost/time projects as the concept is that the customer is put in control, however for this to work you have to be able to somewhat accuratly determine what work is required and what it will cost (time, money, resource). And this is a situtation where Scrum in an ideal candidate.
You break down the wishy-washy wish list/requirements/screenshots into tagiable deliverables. E.g. a customer may say "I want ecommerce, with Paypal", you need to break this down into actual deliverables e.g. "1. Customer Registration and Login, 2. Product Catalogue, 3. Shopping Bag, 4. Payment, 5. Order Acknowlegment". At this stage, it's still impossible to determine how long it will take, and ofc we need to deliver all of the above in order to complete the project (i.e. you can't have Ecommerce without Payment). So break them down again, and again, until you have granular deliverables, genreally delverable within hours, maybe days, but certainly not weeks e.g.
1 Catalogue
1a View all Items
1ai View all items on 1 page with an image and item name underneath in a grid, 4 items per row
1aii View 10 items per page with paging
1aiii View a user slected number of items per page, with paging
1aiiii View all items on 1 page with an image and item name, descriptioon and price on the same line, 1 item per row
1b View by Category
...
1c Search
...
1d Attribute Filter
...
And so on, it can be done very quickly, and you can now probably guesstimate how long it would take todo x (ofc, I might break the above down even further, add more descriptive text to describe the work required, such as what persistant data stuctures Ill might need, the data in those structures, how data will be added, going further you might even desribe the required the begin and exit states).
Once you've go this, you'll notice that some features and depenant on others, e..g you can't have paging feature on a catalogue unless you have a catalogue to start witj, and the catagloge will require the CMS screesn to add and edit items etc etc. Highlight these 'can't live without feature' in whatever tool you using and this forms the core project, and within a day or two you have a bunch of features that can be developed somewhat standalone, with costs, which when added up make the cost of the project. And now the customer is in charge, they decide thay want to added a feature and increase the cost, cool, its up to them afterall.
All the above is obviously only a small portion of what scrum or any agile process is.
I don't think a fixed price contract with scope creep and a Scrum process are incompatible. You just need to agree up front with your customer how it will work. If you create your initial backlog with your customer, estimating as you go, you can use that as your basis for the fixed price cost and schedule. You can even agree to a rate of "X" story points equals "Y" cost and "Z" schedule at the beginning.
You then do the normal scrum thing, having the customer allocate stories to the current iteration, etc.
As the customer engages in scope creep, you work with them to add the "creep" as user stories to the backlog. Each time you add a new story, point out that for each X points added to the backlog, they will have to increase cost by Y and schedule by Z, or, they will have to give up story points of equal value. Since they are picking what you work each iteration, the points they give up (if that's the choice) will be the least valuable features. When your schedule runs out, you will be left with a backlog of the least important features that they can choose to drop or give you a new contract to finish.
The trick, of course, is to be good at estimating cost and schedule for each story/task ;-)
The project could be broken down into smaller parts and fixed rates could be attached to those. The other phases of the project could then be adjusted.
You have to be able to sell the agile process against your competitors. If a client has a history of fixed bid projects that were delivered on time, spec and cost, why would they waste their time taking bids from other developers?
Fixed Cost does not mean single sprint. Scope gets transfered to the Product Backlog, and as Sprints progress, scope is adjusted, negotiated and delivered. Scrum allows for rapid value delivery, and provides quick validation, and the opportunity to identify potential gold plating.
Scope change may result in the addition of backlog items, and the deletion of others. Its a balance of ROI vs the fixed budget provided.
If the scope does increase (and add value), and the cost is fixed, then the triple constraint (cost, time and scope) must be managed accordingly.
Remember that fixed cost does not mean fixed length.

Story estimates in Scrum [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
We started a project that will be managed with Scrum/XP. We wrote the whole product backlog upfront for evaluation purposes. We're making sure all stories are customer-centric and we're evaluating them by
story business value: MoSCoW technique - Must, should, could, would/won't have this implemented
story effort/complexity (= story points): 1, 2, 3, 5, 8, 13, 21, 100 - related to story complexity/effort rather than ideal days duration
100 story points may have some stories with Would/Won't have because they actually are bigger complex stories that will be broken down later if needed.
Calculated story importance is based on value&effort by not overlapping MoSCoW stories.
But without 100 point stories our stories so far (also broken down) has complexity between 2 and 8 which we think is an appropriate story size to avoid micromanagement. But some stories became related or dependant on each other. We have stories that may take more if done first, and less if some other story would be done before them.
Questions
Is it possible to adjust story points later on during development, as we can do with story tasks where we can re-evaluate them, add new, remove existing or is this not the case with stories? Because changing their complexity, will also change end date estimates based on planned velocity. What's the best practice in this case?
You absolutely can estimate your stories again and you should. The points are only locked when the team commits to them at the Sprint Planning Session immediately prior to the start of a Sprint.
One practice I've used is when doing the individual Sprint Planning you should evaluate each story again. The team learns over time and will become more accurate with estimates and identifying dependencies. Remember what goes into a Sprint is up to the team, the product owner defines the overall backlog. If the project is time bound don't try to make the estimates fit the End Date, if you do you are setting yourself up for failure.
Remember that with Velocity you start with a guess at what you can accomplish. It usually isn't until the 3rd or 4th Sprint that you hit identify a realistic Velocity that the team can manage. Yes this does mean that you may have assumed the team could deliver 20 points per Sprint and actually can only do 15 points. Yes that means delivery time goes out or stories fall below the cut line.
As for dependent stories you should work with your product owner. If the team talks to them you can usually rearrange stories. Most people are receptive to someone that tells them "If we do A now it will take the full Sprint, but if we do A later it will take 15% of a Sprint" that makes it pretty convincing.
A useful practice to try is scheduling the stories within the Sprint. During the planning session once all stories are validated and discussed the team pulls up a calendar and discuss when they want to have things done. By putting target dates on a calendar it helps to identify overlaps and dependencies between the stories. This can identify things that are serial in nature and may cause a Sprint to fail.
Hope this information is helpful.
From your explanation you're doing a great job already. Of course there will always be stories with a dependency. Some may not even have directly visible customer value; i.e. the initial effort to set up an architecture and some frameworks). But if you leave them out you'll create a lot of technical debt. If you can, I'd suggest that you try to make the equation complete and somehow show the relation between the tasks.
For instance:
- task 3 is 8 points if done after task 2, but 12 points if done independently.
This way the product owner will feel the pain of ignoring dependencies, but can still make a choice to do the most valuable stories first. If the product owner is sure that all of the stories make it in the next sprints, then you can steer to have them implemented in the most efficient order. For instance, by blocking items for which dependencies have not been fulfilled (i.e. you can only have the 'change my logo on website' feature after the story 'webenabled version' is completed.)
Good luck!
I can only describe my expirience.
When we were planning first sprint we decided that we could accomplish 18 points. So we took several stories and total estimation were 15 points. As I mentioned above we were making our first steps in scrum and that's why we decided that 3 unused points and form-factor 0.6 guaranteed our success.
But our estimations of each story were only approximate. We had also some dependent stories. And we didn't make plan of implementation of each story because we thought that it's unnessecary with agile methodology.
As a result we failed our first sprint with only 8 complete points.
Before our second sprint I decided that we should take something from old good simple cascade and iterative methodoligies (and I was a scrum-master). So, on our next spring planning to make correct estimations we planned each story (about 20 minutes per story), with simple diagrams, all dependencies, details of implementation and so on. The planning was difficult and it took 2 meetings.
But the second sprint was much better and we've done almost all (actually we've done all but with some bugs). I think that we'll take less form-factor in 3rd sprint and it'll be successful.
There are some patterns that would help you in splitting User Stories in a way that they would remain INVEST, which means you would try to save dependencies, size, testability and value in particular. You can read more about that here: http://www.richardlawrence.info/2009/10/28/patterns-for-splitting-user-stories/ Richard is actively applying and improving them, and he is not alone ;-)
Just be aware that splitting and keeping dependencies (which is like creating a critical path in a Gantt chart) is going to trump the capability of the team to be creative, and to negotiate on those stories, and might also hide a "non-valuable-proposition".
HTH
ANdreaT