I am designing a project management app for a factory. The app is expected to produce draft project plans. To schedule a task, the app should check three conditions:
task dependency - do not start before,
machine availability, and
shift work hours
I keep track of machine engagement in machine_allocations table:
machine_allocations
+------------+--------------+-----------------+---------------+
| machine_id | operation_id | start_timestamp | end_timestamp |
+------------+--------------+-----------------+---------------+
Shift hours follow a pattern.
Now, to find the earliest possible date-time for an operation I am thinking of a function:
function earliest_slot($machine_id, $for_duration, $no_sooner_than) {
// pseudo code
1. get records for the machine in question for after $no_sooner_than
2. put start and end timestamps into $unavailable array
3. add non-working times as new elements to the array
4. in a loop find timeslots which are not in the array
5. if a timeslot is found which is equal to or bigger than $for_duration, return that
}
My question is, is this a good approach? Are there simpler ways to do this?

Finding the earliest date-time for one operation at a time may not give you the best result. Consider the example where operation A uses machine 1 for a long time, operation B uses machine 1 for a short time and operation C uses machine 2 for a short time, but operation C must be done after B.
In this case, it is better to schedule B before A on machine 1, but your approach would not achieve this. Of course, writing and using software to manage this would be more difficult than what you have suggested, so you need to decide whether the benefit is worth the extra effort.
Have a look at Scheduling, Job Shop Scheduling and Scheduling algorithm.
First you need to think about what sort of information you can collect about tasks (such as dependencies, priorities, deadlines) and then decide how best to put it together.
You may find that an approach like you propose is good enough in your case. My addition to your proposed algorithm would be to sort the list of existing machine operations to make searching through them faster, that is you can stop as soon as you find a time where your operation fits because it's guaranteed to be the earliest time.
A relatively simple extension would be a priority system that allows you to bump lower-priority tasks forward (which may require the adjustment of their dependencies as well), but more complicated algorithms would consider multiple tasks at once and try to optimise the outcome. In the end it comes down to what's appropriate for your specific problem.

That depends when You want to plan work. If before starting work of machines then mayby a Branch&Bound algorithm, or something like it (mayby dynamic programming). If work have to planned when machines are working and You can not tell what jobs would be performed then for optimal solution You can not count (well I can't think about it). Mayby put next jobs on machine with smalles max time? Mayby a dynamic version of Ford-Bellmas alg (if you have couple layers of production). Hard to say.
I would do couple of approches and determine witch are best. The You can write an article about this :)

Related

Need an advice about algorithm to solve quite specific Job Shop Scheduling Problem

Job Shop Scheduling Problem (JSSP): I have jobs that consist of tasks and I have machines that can perform these tasks.
I should be able to add new jobs dynamically. E.g. I have a schedule for the first 5 jobs, and when the 6th arrive - I need to be able to fit it into the schedule in the best way. It is possible to adjust existing schedule within the given flexibility constrains.
Look at the picture below.
Jobs have tasks, each task is the same type of action. Think about painting of some objects with paint spray. All the machines are the same (paint sprays), and all of the tasks are the same.
Constraint 1. Jobs have a preferred deadline for completion, but the deadline is flexible to some extent.
Edit after #tucuxi answer: Flexible deadline mean that the time of completion can be extended by some delta if necessary.
Constraint 2. Between the jobs there is resting phase. Think about drying the paint. Resting phase has minimal required duration. Resting phase can be longer or shorter if necessary.
Edit after #tucuxi answer: So there is planned time of rest Tp which is desired, but flexible value that can be increased or decreased if this allows for better scheduling. And there is minimal time of rest Tm. So Tp-Tadjustmenet>=Tm.
The machine is occupied by the job from the start to the completion.
Here goes parts that make this problem very distinct from what I have read about.
Jobs arrive in batches of several jobs. For example a batch can contain 10 jobs of the type Job_1 and 5 of Job_2. Different batches can contain different types of jobs. All the jobs from the batches should be finished as close to each other as possible. Not necessary at the same time, but we need to minimize the delay between the completion of first and last jobs from the batch.
Constraint 3. Machines are grouped. In each group only M machines can work simultaneously. Think about paint sprays that are connected to the common pressurizer that has limited performance.
The goal.
Having given description of the problem, it should be possible to solve JSSP. It should be also possible to add new jobs to the existing schedule.
Edit after #tucuxi answer: This is not a task that should be solved immediately: it is not a time-critical system. But it shouldn't be too long to irritate a human who put new tasks into the algorithm.
Question
What kind of many JSSP algorithms can help me solve this? I can implement an algorithm by myself, if there is one. The closest I found is This - Resource Constrained Project Scheduling Problem. But I was not able to comprehend how can I glue it to the JSSP solving algorithm.
Edit after #tucuxianswer: No, I haven't tried it yet.
Is there any libraries that can be used to solve this problem? Python or C# are the preferred languages, but in the end it doesn't really matter.
I appreciate any help: keyword to search for, link, reference to a book, reference to a library.
Thank you.
I doubt that there is a pre-made algorithm that solves your exact problem.
If I had to solve it, I would first:
compile datasets of inputs that I can feed into candidate solvers.
think of a metric to rank outputs, so that I can compare the candidates to see which is better.
A baseline solver could be a brute-force search: test and rate all possible job schedulings for small sample problems. This is of course infeasible for large inputs, but for small inputs it allows you to compare the outputs of more efficient solvers to a known-best answer.
Your link is to localsolver.com, which appears to provide a library for specifying problem constraints to then solve them. It is not freely available, requiring a license to use; but it would seem that your problem can be readily modeled in it. Have you tried to do so? They appear to support both C++ and Python. Other free options exist, including optaplanner (2.8k stars in github) or python-constraint (I have not looked into other languages).
Note that a good metric is crucial to choosing a good algorithm: unless you have a clear cost function to minimize, choosing "a good algorithm" is impossible. In your description of the problem, I see several places where cost is unclear (marked in italics):
job deadlines are flexible
minimal required rest times... which may be shortened
jobs from a batch should be finished as close together as possible
(not from specification): how long can you wait for an optimal vs a less-optimal-but-faster solution?

Scheduling with variable Resources

(First of all, sorry for my english, it's not my first language)
I have a list of tasks/jobs, each task must start after a specific start time, needs to run for a certain time and has to be finished after a certain end time.
I can dynamically add and remove workers, so it is possible to execute 2 or more tasks at the same time if I have to. My Goal is to find a scheduling plan that executes each job successfully and uses the minimal amount of workers possible.
I'm currently using an EDF (http://en.wikipedia.org/wiki/Earliest_deadline_first_scheduling) Algorithm and recursively call the function with a higher Worker Limit if it can't schedule all jobs correctly, but I think this doesn't work right because I don't have a real way to measure when I can lower the ressource limit again.
Are there any Algorithms that work for my problem, or any other clever ideas?
Thanks for your help.
A scheduling problem can often be solved very effectively by formulating it either as mixed-integer program (MIP)
http://en.wikipedia.org/wiki/Mixed_integer_programming#Integer_unknowns
or expressing it using constraint programming (CP)
http://en.wikipedia.org/wiki/Constraint_programming
For either MIP or CP, you will find both free and commercial solvers that can address your problem.
In both of these approaches, you put your effort into stating the properties that the solution must have, and the hard work of applying an appropriate algorithm is left to a specialized solver.

Algorithm for creating a school timetable

I've been wondering if there are known solutions for algorithm of creating a school timetable. Basically, it's about optimizing "hour-dispersion" (both in teachers and classes case) for given class-subject-teacher associations. We can assume that we have sets of classes, lesson subjects and teachers associated with each other at the input and that timetable should fit between 8AM and 4PM.
I guess that there is probably no accurate algorithm for that, but maybe someone knows a good approximation or hints for developing it.
This problem is NP-Complete!
In a nutshell one needs to explore all possible combinations to find the list of acceptable solutions. Because of the variations in the circumstances in which the problem appears at various schools (for example: Are there constraints with regards to classrooms?, Are some of the classes split in sub-groups some of the time?, Is this a weekly schedule? etc.) there isn't a well known problem class which corresponds to all the scheduling problems. Maybe, the Knapsack problem has many elements of similarity with these problems at large.
A confirmation that this is both a hard problem and one for which people perennially seek a solution, is to check this (long) list of (mostly commercial) software scheduling tools
Because of the big number of variables involved, the biggest source of which are, typically, the faculty member's desires ;-)..., it is typically impractical to consider enumerating all possible combinations. Instead we need to choose an approach which visits a subset of the problem/solution spaces.
- Genetic Algorithms, cited in another answer is (or, IMHO, seems) well equipped to perform this kind of semi-guided search (The problem being to find a good evaluation function for the candidates to be kept for the next generation)
- Graph Rewriting approaches are also of use with this type of combinatorial optimization problems.
Rather than focusing on particular implementations of an automatic schedule generator program, I'd like to suggest a few strategies which can be applied, at the level of the definition of the problem.
The general rationale is that in most real world scheduling problems, some compromises will be required, not all constraints, expressed and implied: will be satisfied fully. Therefore we help ourselves by:
Defining and ranking all known constraints
Reducing the problem space, by manually, providing a set of additional constraints.This may seem counter-intuitive but for example by providing an initial, partially filled schedule (say roughly 30% of the time-slots), in a way that fully satisfies all constraints, and by considering this partial schedule immutable, we significantly reduce the time/space needed to produce candidate solutions. Another way additional constraints help is for example "artificially" adding a constraint which prevent teaching some subjects on some days of the week (if this is a weekly schedule...); this type of constraints results in reducing the problem/solution spaces, without, typically, excluding a significant number of good candidates.
Ensuring that some of the constraints of the problem can be quickly computed. This is often associated with the choice of data model used to represent the problem; the idea is to be able to quickly opt-for (or prune-out) some of the options.
Redefining the problem and allowing some of the constraints to be broken, a few times, (typically towards the end nodes of the graph). The idea here is to either remove some of constraints for filling-in the last few slots in the schedule, or to have the automatic schedule generator program stop shy of completing the whole schedule, instead providing us with a list of a dozen or so plausible candidates. A human is often in a better position to complete the puzzle, as indicated, possibly breaking a few of the contraints, using information which is not typically shared with the automated logic (eg "No mathematics in the afternoon" rule can be broken on occasion for the "advanced math and physics" class; or "It is better to break one of Mr Jones requirements than one of Ms Smith ... ;-) )
In proof-reading this answer , I realize it is quite shy of providing a definite response, but it none the less full of practical suggestions. I hope this help, with what is, after all, a "hard problem".
It's a mess. a royal mess. To add to the answers, already very complete, I want to point out my family experience. My mother was a teacher and used to be involved in the process.
Turns out that having a computer to do so is not only difficult to code per-se, it is also difficult because there are conditions that are difficult to specify to a pre-baked computer program. Examples:
a teacher teaches both at your school and at another institute. Clearly, if he ends the lesson there at 10.30, he cannot start at your premises at 10.30, because he needs some time to commute between the institutes.
two teachers are married. In general, it's considered good practice not to have two married teachers on the same class. These two teachers must therefore have two different classes
two teachers are married, and their child attends the same school. Again, you have to prevent the two teachers to teach in the specific class where their child is.
the school has separate facilities, like one day the class is in one institute, and another day the class is in another.
the school has shared laboratories, but these laboratories are available only on certain weekdays (for security reasons, for example, where additional personnel is required).
some teachers have preferences for the free day: some prefer on Monday, some on Friday, some on Wednesday. Some prefer to come early in the morning, some prefer to come later.
you should not have situations where you have a lesson of say, history at the first hour, then three hours of math, then another hour of history. It does not make sense for the students, nor for the teacher.
you should spread the arguments evenly. It does not make sense to have the first days in the week only math, and then the rest of the week only literature.
you should give some teachers two consecutive hours to do evaluation tests.
As you can see, the problem is not NP-complete, it's NP-insane.
So what they do is that they have a large table with small plastic insets, and they move the insets around until a satisfying result is obtained. They never start from scratch: they normally start from the previous year timetable and make adjustments.
The International Timetabling Competition 2007 had a lesson scheduling track and exam scheduling track. Many researchers participated in that competition. Lots of heuristics and metaheuristics were tried, but in the end the local search metaheuristics (such as Tabu Search and Simulated Annealing) clearly beat other algorithms (such as genetic algorithms).
Take a look at the 2 open source frameworks used by some of the finalists:
JBoss OptaPlanner (Java, open source)
Unitime (Java, open source) - more for universities
One of my half-term assignments was an genetic-algorithm school table generation.
Whole table is one "organism". There were some changes and caveats to the generic genetic algorithms approach:
Rules were made for "illegal tables": two classes in the same classroom, one teacher teaching two groups at the same time etc. These mutations were deemed lethal immediately and a new "organism" was sprouted in place of the "deceased" immediately. The initial one was generated by a series of random tries to get a legal (if senseless) one. Lethal mutation wasn't counted towards count of mutations in iteration.
"Exchange" mutations were much more common than "Modify" mutations. Changes were only between parts of the gene that made sense - no substituting a teacher with a classroom.
Small bonuses were assigned for bundling certain 2 hours together, for assigning same generic classroom in sequence for the same group, for keeping teacher's work hours and class' load continuous. Moderate bonuses were assigned for giving correct classrooms for given subject, keeping class hours within bonds (morning or afternoon), and such. Big bonuses were for assigning correct number of given subject, given workload for a teacher etc.
Teachers could create their workload schedules of "want to work then", "okay to work then", "doesn't like to work then", "can't work then", with proper weights assigned. Whole 24h were legal work hours except night time was very undesired.
The weight function... oh yeah. The weight function was huge, monstrous product (as in multiplication) of weights assigned to selected features and properties. It was extremely steep, one property easily able to change it by an order of magnitude up or down - and there were hundreds or thousands of properties in one organism. This resulted in absolutely HUGE numbers as the weights, and as a direct result, need to use a bignum library (gmp) to perform the calculations. For a small testcase of some 10 groups, 10 teachers and 10 classrooms, the initial set started with note of 10^-200something and finished with 10^+300something. It was totally inefficient when it was more flat. Also, the values grew a lot wider distance with bigger "schools".
Computation time wise, there was little difference between a small population (100) over a long time and a big population (10k+) over less generations. The computation over the same time produced about the same quality.
The calculation (on some 1GHz CPU) would take some 1h to stabilize near 10^+300, generating schedules that looked quite nice, for said 10x10x10 test case.
The problem is easily paralellizable by providing networking facility that would exchange best specimens between computers running the computation.
The resulting program never saw daylight outside getting me a good grade for the semester. It showed some promise but I never got enough motivation to add any GUI and make it usable to general public.
This problem is tougher than it seems.
As others have alluded to, this is a NP-complete problem, but let's analyse what that means.
Basically, it means you have to look at all possible combinations.
But "look at" doesn't tell you much what you need to do.
Generating all possible combinations is easy. It might produce a huge amount of data, but you shouldn't have much problems understanding the concepts of this part of the problem.
The second problem is the one of judging whether a given possible combination is good, bad, or better than the previous "good" solution.
For this you need more than just "is it a possible solution".
For instance, is the same teacher working 5 days a week for X weeks straight? Even if that is a working solution, it might not be a better solution than alternating between two people so that each teacher does one week each. Oh, you didn't think about that? Remember, this is people you're dealing with, not just a resource allocation problem.
Even if one teacher could work full-time for 16 weeks straight, that might be a sub-optimal solution compared to a solution where you try to alternate between teachers, and this kind of balancing is very hard to build into software.
To summarize, producing a good solution to this problem will be worth a lot, to many many people. Hence, it's not an easy problem to break down and solve. Be prepared to stake out some goals that aren't 100% and calling them "good enough".
My timetabling algorithm, implemented in FET (Free Timetabling Software, http://lalescu.ro/liviu/fet/ , a successful application):
The algorithm is heuristic. I named it "recursive swapping".
Input: a set of activities A_1...A_n and the constraints.
Output: a set of times TA_1...TA_n (the time slot of each activity. Rooms are excluded here, for simplicity). The algorithm must put each activity at a time slot, respecting constraints. Each TA_i is between 0 (T_1) and max_time_slots-1 (T_m).
Constraints:
C1) Basic: a list of pairs of activities which cannot be simultaneous (for instance, A_1 and A_2, because they have the same teacher or the same students);
C2) Lots of other constraints (excluded here, for simplicity).
The timetabling algorithm (which I named "recursive swapping"):
Sort activities, most difficult first. Not critical step, but speeds up the algorithm maybe 10 times or more.
Try to place each activity (A_i) in an allowed time slot, following the above order, one at a time. Search for an available slot (T_j) for A_i, in which this activity can be placed respecting the constraints. If more slots are available, choose a random one. If none is available, do recursive swapping:
a. For each time slot T_j, consider what happens if you put A_i into T_j. There will be a list of other activities which don't agree with this move (for instance, activity A_k is on the same slot T_j and has the same teacher or same students as A_i). Keep a list of conflicting activities for each time slot T_j.
b. Choose a slot (T_j) with lowest number of conflicting activities. Say the list of activities in this slot contains 3 activities: A_p, A_q, A_r.
c. Place A_i at T_j and make A_p, A_q, A_r unallocated.
d. Recursively try to place A_p, A_q, A_r (if the level of recursion is not too large, say 14, and if the total number of recursive calls counted since step 2) on A_i began is not too large, say 2*n), as in step 2).
e. If successfully placed A_p, A_q, A_r, return with success, otherwise try other time slots (go to step 2 b) and choose the next best time slot).
f. If all (or a reasonable number of) time slots were tried unsuccessfully, return without success.
g. If we are at level 0, and we had no success in placing A_i, place it like in steps 2 b) and 2 c), but without recursion. We have now 3 - 1 = 2 more activities to place. Go to step 2) (some methods to avoid cycling are used here).
UPDATE: from comments ... should have heuristics too!
I'd go with Prolog ... then use Ruby or Perl or something to cleanup your solution into a prettier form.
teaches(Jill,math).
teaches(Joe,history).
involves(MA101,math).
involves(SS104,history).
myHeuristic(D,A,B) :- [test_case]->D='<';D='>'.
createSchedule :- findall(Class,involves(Class,Subject),Classes),
predsort(myHeuristic,Classes,ClassesNew),
createSchedule(ClassesNew,[]).
createSchedule(Classes,Scheduled) :- [the actual recursive algorithm].
I am (still) in the process of doing something similar to this problem but using the same path as I just mentioned. Prolog (as a functional language) really makes solving NP-Hard problems easier.
Genetic algorithms are often used for such scheduling.
Found this example (Making Class Schedule Using Genetic Algorithm) which matches your requirement pretty well.
Here are a few links I found:
School timetable - Lists some problems involved
A Hybrid Genetic Algorithm for School Timetabling
Scheduling Utilities and Tools
This paper describes the school timetable problem and their approach to the algorithm pretty well: "The Development of SYLLABUS—An Interactive, Constraint-Based Scheduler for Schools and Colleges."[PDF]
The author informs me the SYLLABUS software is still being used/developed here: http://www.scientia.com/uk/
I work on a widely-used scheduling engine which does exactly this. Yes, it is NP-Complete; the best approaches seek to approximate an optimal solution. And, of course there are a lot of different ways to say which one is the "best" solution - is it more important that your teachers are happy with their schedules, or that students get into all their classes, for instance?
The absolute most important question you need to resolve early on is what makes one way of scheduling this system better than another? That is, if I have a schedule with Mrs Jones teaching Math at 8 and Mr Smith teaching Math at 9, is that better or worse than one with both of them teaching Math at 10? Is it better or worse than one with Mrs Jones teaching at 8 and Mr Jones teaching at 2? Why?
The main advice I'd give here is to divide the problem up as much as possible - maybe course by course, maybe teacher by teacher, maybe room by room - and work on solving the sub-problem first. There you should end up with multiple solutions to choose from, and need to pick one as the most likely optimal. Then, work on making the "earlier" sub-problems take into account the needs of later sub-problems in scoring their potential solutions. Then, maybe work on how to get yourself out of painted-into-the-corner situations (assuming you can't anticipate those situations in earlier sub-problems) when you get to a "no valid solutions" state.
A local-search optimization pass is often used to "polish" the end answer for better results.
Note that typically we are dealing with highly resource-constrained systems in school scheduling. Schools don't go through the year with a lot of empty rooms or teachers sitting in the lounge 75% of the day. Approaches which work best in solution-rich environments aren't necessarily applicable in school scheduling.
Generally, constraint programming is a good approach to this type of scheduling problem. A search on "constraint programming" and scheduling or "constraint based scheduling" both within stack overflow and on Google will generate some good references. It's not impossible - it's just a little hard to think about when using traditional optimization methods like linear or integer optimization. One output would be - does a schedule exist that satisfies all the requirements? That, in itself, is obviously helpful.
Good luck !
I have designed commercial algorithms for both class timetabling and examination timetabling. For the first I used integer programming; for the second a heuristic based on maximizing an objective function by choosing slot swaps, very similar to the original manual process that had been evolved. They main things in getting such solutions accepted are the ability to represent all the real-world constraints; and for human timetablers to not be able to see ways to improve the solution. In the end the algorithmic part was quite straightforward and easy to implement compared with the preparation of the databases, the user interface, ability to report on statistics like room utilization, user education and so on.
You can takle it with genetic algorithms, yes. But you shouldn't :). It can be too slow and parameter tuning can be too timeconsuming etc.
There are successful other approaches. All implemented in open source projects:
Constraint based approach
Implemented in UniTime (not really for schools)
You could also go further and use Integer programming. Successfully done at Udine university and also at University Bayreuth (I was involved there) using the commercial software (ILOG CPLEX)
Rule based approach with heuristisc - See Drools planner
Different heuristics - FET and my own
See here for a timetabling software list
I think you should use genetic algorithm because:
It is best suited for large problem instances.
It yields reduced time complexity on the price of inaccurate answer(Not the ultimate best)
You can specify constraints & preferences easily by adjusting fitness punishments for not met ones.
You can specify time limit for program execution.
The quality of solution depends on how much time you intend to spend solving the program..
Genetic Algorithms Definition
Genetic Algorithms Tutorial
Class scheduling project with GA
Also take a look at :a similar question and another one
This problem is MASSIVE where I work - imagine 1800 subjects/modules, and 350 000 students, each doing 5 to 10 modules, and you want to build an exam in 10 weeks, where papers are 1 hour to 3 days long... one plus point - all exams are online, but bad again, cannot exceed the system's load of max 5k concurrent. So yes we are doing this now in cloud on scaling servers.
The "solution" we used was simply to order modules on how many other modules they "clash" with descending (where a student does both), and to "backpack" them, allowing for these long papers to actually overlap, else it simply cannot be done.
So when things get too large, I found this "heuristic" to be practical... at least.
I don't know any one will agree with this code but i developed this code with the help of my own algorithm and is working for me in ruby.Hope it will help them who are searching for it
in the following code the periodflag ,dayflag subjectflag and the teacherflag are the hash with the corresponding id and the flag value which is Boolean.
Any issue contact me.......(-_-)
periodflag.each do |k2,v2|
if(TimetableDefinition.find(k2).period.to_i != 0)
subjectflag.each do |k3,v3|
if (v3 == 0)
if(getflag_period(periodflag,k2))
#teachers=EmployeesSubject.where(subject_name: #subjects.find(k3).name, division_id: division.id).pluck(:employee_id)
#teacherlists=Employee.find(#teachers)
teacherflag=Hash[teacher_flag(#teacherlists,teacherflag,flag).to_a.shuffle]
teacherflag.each do |k4,v4|
if(v4 == 0)
if(getflag_subject(subjectflag,k3))
subjectperiod=TimetableAssign.where("timetable_definition_id = ? AND subject_id = ?",k2,k3)
if subjectperiod.blank?
issubjectpresent=TimetableAssign.where("section_id = ? AND subject_id = ?",section.id,k3)
if issubjectpresent.blank?
isteacherpresent=TimetableAssign.where("section_id = ? AND employee_id = ?",section.id,k4)
if isteacherpresent.blank?
#finaltt=TimetableAssign.new
#finaltt.timetable_struct_id=#timetable_struct.id
#finaltt.employee_id=k4
#finaltt.section_id=section.id
#finaltt.standard_id=standard.id
#finaltt.division_id=division.id
#finaltt.subject_id=k3
#finaltt.timetable_definition_id=k2
#finaltt.timetable_day_id=k1
set_school_id(#finaltt,current_user)
if(#finaltt.save)
setflag_sub(subjectflag,k3,1)
setflag_period(periodflag,k2,1)
setflag_teacher(teacherflag,k4,1)
end
end
else
#subjectdetail=TimetableAssign.find_by_section_id_and_subject_id(#section.id,k3)
#finaltt=TimetableAssign.new
#finaltt.timetable_struct_id=#subjectdetail.timetable_struct_id
#finaltt.employee_id=#subjectdetail.employee_id
#finaltt.section_id=section.id
#finaltt.standard_id=standard.id
#finaltt.division_id=division.id
#finaltt.subject_id=#subjectdetail.subject_id
#finaltt.timetable_definition_id=k2
#finaltt.timetable_day_id=k1
set_school_id(#finaltt,current_user)
if(#finaltt.save)
setflag_sub(subjectflag,k3,1)
setflag_period(periodflag,k2,1)
setflag_teacher(teacherflag,k4,1)
end
end
end
end
end
end
end
end
end
end
end

Constrained graph transformation in scheduling applications

I'm working on an interactive job scheduling application. Given a set of resources with corresponding capacity/availabilty profiles, a set of jobs to be executed on these resources and a set of constraints that determine job sequence and earliest/latest start/end times for jobs I want to enable the user to manually move jobs around. Essentially I want the user to be able to "grab" a node of the job network and drag that forwards/backwards in time without violating any of the constraints.
The image shows a simple example configuration. The triangular job at the end denotes the latest finish time for all jobs, the connecting lines between jobs impose an order on the jobs and the gray/green bars denote resource availabilty and load.
You can drag any of the jobs to compress the schedule. Note that jobs will change in length due to different capacity profiles.
I have implemented an ad-hock algorithm that kinda works. However there are still cases where it'll fail and violate some constraints. However, since job-shop-scheduling is a well researched field with lots of algorithms and heuristics for finding an optimal (or rather good) solution to the general NP-hard problem - I'm thinking solutions ought to exist for my easier subset. I have looked into constraint programming topics and even physics based solutions (rigid bodies connected via static joints) but so far couldn't find anything suitable. Any pointers/hints/tips/search key words for me?
I highly recommend you take a look at Mozart Oz, if your problem
deals only with integers. Oz has excellent support for finite domain
constraint specification, inference, and optimization. In your case
typically you would do the following:
Specify your constraints in a declarative manner. In this, you would
specify all the variables and their domains (say V1: 1#100, means
V1 variable can take values in the range of 1--100). Some variables
might have values directly, say V1: 99. In addition you would specify
all the constraints on the variables.
Ask the system for a solution: either any solution which satisfies
the constraints or an optimal solution. Then you would display this
solution on the UI.
Lets say the user changes the value of a variable, may be the start
time of a task. Now you can go to step 1 to post the problem to the
Oz solver. This time, solving the problem most probably will not take
as much time as earlier, as all the variables are already instantiated.
It may be the case that the user chose a inconsistent value. In that
case, the solver returns null. Then, you can take the UI to the earlier
solution.
If Oz suits your need and you like the language, then you may want to
write a constraint solver as a server which listens on a socket. This way,
you can keep the constraint solver separate from the rest of your code,
including the UI.
Hope this helps.
I would vote in favor of constraint programming for several reasons:
1) CP will quickly tell you if there is no schedule that satifies your constraints
2) It would appear that you want to give you users a feasible solution to start with but
allow them to manipulate jobs in order to improve the solution. CP is good at this too.
3) An MILP approach is usually complex and hard to formulate and you have to artificially create an objective function.
4) CP is not that difficult to learn especially for experienced programmers - it really comes more from the computer science community than the operations researchers (like me).
Good luck.
You could probably alter the Waltz constraint propagation algorithm to deal with changing constraints to quickly find out if a given solution is valid. I don't have a reference to hand, but this might point you in the right direction:
http://www.sciencedirect.com/science?_ob=ArticleURL&_udi=B6TYF-41C30BN-5&_user=809099&_rdoc=1&_fmt=&_orig=search&_sort=d&_docanchor=&view=c&_searchStrId=1102030809&_rerunOrigin=google&_acct=C000043939&_version=1&_urlVersion=0&_userid=809099&md5=696143716f0d363581a1805b34ae32d9
Have you considered using an Integer Linear Programming engine (like lp_solve)? It's quite a good fit for scheduling applications.

Which algorithm for assigning shifts (discrete optimization problem)

I'm developing an application that optimally assigns shifts to nurses in a hospital. I believe this is a linear programming problem with discrete variables, and therefore probably NP-hard:
For each day, each nurse (ca. 15-20) is assigned a shift
There is a small number (ca. 6) of different shifts
There is a considerable number of constraints and optimization criteria, either concerning a day, or concerning an emplyoee, e.g.:
There must be a minimum number of people assigned to each shift every day
Some shifts overlap so that it's OK to have one less person in early shift if there's someone doing intermediate shift
Some people prefer early shift, some prefer late shift, but a minimum of shift changes is required to still get the higher shift-work pay.
It's not allowed for one person to work late shift one day and early shift the next day (due to minimum resting time regulations)
Meeting assigned working week lengths (different for different people)
...
So basically there is a large number (aout 20*30 = 600) variables that each can take a small number of discrete values.
Currently, my plan is to use a modified Min-conflicts algorithm
start with random assignments
have a fitness function for each person and each day
select the person or day with the worst fitness value
select at random one of the assignments for that day/person and set it to the value that results in the optimal fitness value
repeat until either a maximum number of iteration is reached or no improvement can be found for the selected day/person
Any better ideas? I am somewhat worried that it will get stuck in a local optimum. Should I use some form of simulated annealing? Or consider not only changes in one variable at a time, but specifically switches of shifts between two people (the main component in the current manual algorithm)? I want to avoid tailoring the algorithm to the current constraints since those might change.
Edit: it's not necessary to find a strictly optimal solution; the roster is currently done manual, and I'm pretty sure the result is considerably sub-optimal most of the time - shouldn't be hard to beat that. Short-term adjustments and manual overrides will also definitely be necessary, but I don't believe this will be a problem; Marking past and manual assignments as "fixed" should actually simplify the task by reducing the solution space.
This is a difficult problem to solve well. There has been many academic papers on this subject particularly in the Operations Research field - see for example nurse rostering papers 2007-2008 or just google "nurse rostering operations research". The complexity also depends on aspects such as: how many days to solve; what type of "requests" can the nurse's make; is the roster "cyclic"; is it a long term plan or does it need to handle short term rostering "repair" such as sickness and swaps etc etc.
The algorithm you describe is a heuristic approach.
You may find you can tweak it to work well for one particular instance of the problem but as soon as "something" is changed it may not work so well (e.g. local optima, poor convergence).
However, such an approach may be adequate depending your particular business needs - e.g. how important is it to get the optimal solution, is the problem outline you describe expected to stay the same, what is the potential savings (money and resources), how important is the nurse's perception of the quality of their rosters, what is the budget for this work etc.
Umm, did you know that some ILP-solvers do quite a good job? Try AIMMS, Mathematica or the GNU programming kit! 600 Variables is of course a lot more than the Lenstra theorem will solve easily, but sometimes these ILP solvers have a good handle and in AIMMS, you can modify the branching strategy a little. Plus, there's a really fast 100%-approximation for ILPs.
I solved a shift assignment problem for a large manufacturing plant recently. First we tried generating purely random schedules and returning any one which passed the is_schedule_valid test - the fallback algorithm. This was, of course, slow and indeterminate.
Next we tried genetic algorithms (as you suggested), but couldn't find a good fitness function that closed on any viable solution (because the smallest change can make the entire schedule RIGHT or WRONG - no points for almost).
Finally we chose the following method (which worked great!):
Randomize the input set (i.e. jobs, shift, staff, etc.).
Create a valid tuple and add it to your tentative schedule.
If not valid tuple can be created, rollback (and increment) the last tuple added.
Pass the partial schedule to a function that tests could_schedule_be_valid, that is, could this schedule be valid if the remaining tuples were filled in a possible way
If !could_schedule_be_valid, simply rollback (and increment) the tuple added in (2).
If schedule_is_complete, return schedule
Goto (2)
You incrementally build a partial shift this way. The benefit is that some tests for valid schedule can easily be done in Step 2 (pre-tests), and others must remain in Step 5 (post-tests).
Good luck. We wasted days trying the first two algorithms, but got the recommended algorithm generating valid schedules instantly in under 5 hours of development.
Also, we supported pre-fixing and post-fixing of assignments that the algorithm would respect. You simply don't randomize those slots in Step 1. You'll find that the solutions doesn't have to be anywhere near optimal. Our solution is O(N*M) at a minimum but executes in PHP(!) in less than half a second for an entire manufacturing plant. The beauty is in ruling out bad schedules quickly using a good could_schedule_be_valid test.
The people that are used to doing it manually don't care if it takes an hour - they just know they don't have to do it manually any more.
Mike,
Don't know if you ever got a good answer to this, but I'm pretty sure that constraint programming is the ticket. While a GA might give you an answer, CP is designed to give you many answers or tell you if there is no feasible solution. A search on "constraint programming" and scheduling should bring up lots of info. It's a relatively new area and CP methods work well on many types of problems where traditional optimization methods bog down.
Dynamic programming a la Bell? Kinda sounds like there's a place for it: overlapping subproblems, optimal substructures.
One thing you can do is to try to look for symmetries in the problem. E.g. can you treat all nurses as equivalent for the purposes of the problem? If so, then you only need to consider nurses in some arbitrary order -- you can avoid considering solutions such that any nurse i is scheduled before any nurse j where i > j. (You did say that individual nurses have preferred shift times, which contradicts this example, although perhaps that's a less important goal?)
I think you should use genetic algorithm because:
It is best suited for large problem instances.
It yields reduced time complexity on the price of inaccurate answer(Not the ultimate best)
You can specify constraints & preferences easily by adjusting fitness punishments for not met ones.
You can specify time limit for program execution.
The quality of solution depends on how much time you intend to spend solving the program..
Genetic Algorithms Definition
Genetic Algorithms Tutorial
Class scheduling project with GA
Also take a look at :a similar question and another one
Using CSP programming I made programms for automatic shitfs rostering. eg:
2-shifts system - tested for 100+ nurses, 30 days time horizon, 10+
rules
3-shifts system - tested for 80+ nurses, 30 days time horizon, 10+ rules
3-shifts system, 4-teams - tested for 365 days horizon, 10+ rules,
and a couple of similiar systems. All of them were tested on my home PC (1.8GHz, dual-core). Execution times always were acceptable ie. for 3/ it took around 5 min and 300MB RAM.
Most hard part of this problem was selecting proper solver and proper solving strategy.
Metaheuristics did very well at the International Nurse Rostering Competition 2010.
For an implementation, see this video with a continuous nurse rostering (java).