Managing user stories for a large project [closed] - project-management

Closed. This question is off-topic. It is not currently accepting answers.
Want to improve this question? Update the question so it's on-topic for Stack Overflow.
Closed 9 years ago.
Improve this question
We are just starting on a pretty big project with lots of sub projects. we don't currently use any kind of named process but I am hoping to get some kind of agile/scrumlike process in by the back door.
The area I will be focusing on most is having a good backlog for the whole project and, at least in my head, the idea of an iteration where some things are taken from the backlog, looked at in more detail and developed to a reasonable deadline.
I wonder what techniques people use to break projects down into things to go in the backlog, and once the backlog is created how it is maintained and ordered. also how relationships between elements are maintained (ie this must be done before it is possible to do that, or this was one story now it is five)
I am not sure what I expect the answer for this question to look like. I think what may be most helpful is if there is an open source project that keeps its backlog online in some way so I can see how others do it.
Something else that would get +1 from me is examples of real user stories from real projects (the "a user can log on" story does not help me picture things in my project.
Thanks.

I would counsel you to think carefully before adopting a tool, especially since it sounds like your process is likely to be fluid at first as you find your feet. My feeling is that a tool may be more likely to constrain you than enable you at this stage, and you will find it no substitute for a good card-wall in physical space. I would suggest you instead concentrate your efforts on the task at hand, and grab a tool when you feel like you really need one. By that stage you'll more likely have a clear idea of your requirements.
I have run several agile projects now and we have never needed a more complex tool than a spreadsheet, and that on a project with a budget of over a million pounds. Mostly we find that a whiteboard and index cards (one per user story) is more than sufficient.
When identifying your stories, make sure you always express them in terms that make sense to your users - some (perhaps only small) piece of surfaced functionality. Never allow yourself to slip into writing stories about technical details that you could not demonstrate to a user.
The skill when scheduling the stories is to try to prioritise the things you know least about first (plan for what you want to learn, rather than what you want to do) whilst also starting with the stories that will allow you to develop the core features of your application, using subsequent stories to wrap functionality (and technical complexity) around them.
If you're confident that you can leave some piece of the puzzle till later, don't sweat on getting into the details of that - just write a single story card that represents the big conversation you'll need to have later, and get on with the more important stuff. If you need to have a feel for the size of what's to come, look at a wideband delphi estimation technique called planning poker.
The Mike Cohn books, particularly Agile Estimating and Planning will help you a lot at this stage, and give you some useful techniques to work with.
Good luck!

Like DanielHonig we also use RallyDev (on a small scale) and it sounds like it could be a useful system for you to at least investigate.
Also, a great book on the user story method of development is User Stories Applied by Mike Cohn. I'd certainly recommend reading it if you haven't already. It should answer a lot of your questions.

I'm not sure if this is what you're looking for, but it may still be helpful. Max Pool from codesqueeze has a video explaining his "agile wall". It's cool to see his process, even if it may not necessarily relate to your question:
My Agile Wall (Plus A Few Tricks)

So here are a few tips:
We use RallyDev.
We created a view of packages that our requirements live in.
Large stories are labeled as epics and placed into the release backlog of the release they are intended for. Child stories are added to the epics. We have found it best to keep the stories very granular. Coarse grained stories make it difficult to realistically estimate and execute the story.
So in general:
Organize by the release
Keep
iterations between 2-4 weeks
Product owners and project
managers add stories to the release
backlog
The dev team estimates
the stories based on TShirt sizes,
points, etc...
In Spring planning
meeetings the dev team selects the
work for the iteration from the
release backlog.
This is what we've been doing for the past 4 months and have found it to work well. Very important to keep the size of the stories small and granular.
Remember the Invest and Smart acronyms for evaluating user stories, a good story should be:
I - Independent
N - Negotiable
V - Valuable
E - Estimable
S - Small
T - Testable
Smart:
S - Specific
M - Measurable
A - Achievable
R - Relevant
T - Time-boxed

I'd start off by saying Keep it Simple.. use a shared spreadsheet with tracking (and backup). If you see scaling or synchronization problems such that maintaining the backlog in a consistent state is getting more and more time-consuming, trade up. This will automatically validate and justify the expenditure/retraining costs.
I've read some good things about Mingle from Thoughtworks.

here is my response to a similar question that may give you some ideas
Help a BA! Managing User Stories ...

A lot of these responses have been with suggestions about tools to use. However, the reality is that your process will be the much more important than the tools you use to implement the process. Stay away from tools that attempt to cram a methodology down your throat. But also, be wary of simply implementing an old non-agile process using a new tool. Here are some strong facts to consider when determining tools for processes:
A bad process instrumented with a software tool will result in a bad
software tool implemention.
Processes will change based on the group you are managing. The
important thing is the people, not the process. Implement something
they can work successfully in, and your project will be successful.
All that said, here are a few guidelines to help you:
Start with a pure implementation of a documented process,
Make your iterations small,
After each iteration talk with your teams and ask what they they
would change, implement the changes that make sense.
For larger organizations, if you are using SCRUM, use a cascading stand-up mechanism. Scrum masters meet with thier teams. Then the Scrum Masters meet in stand-ups of 6 - 9, with a Super-Scrum-MAster responsible for reporting the items from the Scum-Master's scrum to the next level... and so forth..
You may find that have weekly super-scrum meetings will suffice at the highest level of your hierarchy.

Related

Is Scrum useful for single programmer developments? [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
I lead a team of six programmers, and we are presently implementing a number of agile development practices. I'm very interested in Scrum, however it seems to assume that your project will have multiple developers. Most of my projects are smaller, and involve a single developer. We run 3 or 4 such projects in parrallel at any time.
From reading Schwaber, a lot of the benefit of Scrum seems to derive from teams self-organising to achieve a complex task. If you have a single developer doing all the work, will Scrum deliver much value?
Scrum might be more than you need as a single developer, but if you have a stake holder and a QA person then Scrum can still be helpful. Remember they are apart of your team, and should be at your standups to trade information with the team.
If you are truly alone there are other agile practices that might make more sense to you. For example, Kanban might be a better fit. You don't have iteration overhead, retros, sprint planning, etc. You just have a backlog that you pull tasks from. This works well as a way to organize your work, allows stake holders to adjust priorities, and works well for a single developer or small team where you can break up work without a lot of need to synchronize between developers. Maybe you have a product built that only has small features that doesn't need a lot of architecture being built to support new features. Or lots of small projects that are independent say for advertising firms, etc.
The single most important benefit of Scrum that is there even if there is just one developer is not the daily sync (meeting), but rather the limitation on context switches. While working in sprints this single developer can concentrate on given stories within his (presumably short) sprint knowing he won't be interrupted or pushed to do something else before finishing this.
Less context switching == less waste == more productivity.
BTW - Kanban offers less overhead than Scrum, but it is easier to circumvent and force developer to context switch. This can be a benefit but can easily become a problem too.
I think that the value you may get can come from scrum or other agile concepts.
For example, instead of a weird standup meeting, have the one developer tell you why he has taken x desicion for the y task. You may or may not be able to suggest things (depends on your background as a developer I guess), but the fact that the developer is hearing his own explanation might be useful for finding bugs or dead-end reasonings.
As a professor of mine once commented on asking yourself a question aloud: "If you ask the universe for an answer, it will give you one"
While, as others have pointed out, the daily standup may be weird, there's still value for an individual developer in adopting a scrum-'like' process.
Timeboxed, potentially releasable, iterations and a stack-ranked backlog can only help an individual developer keep focused on actually getting something done instead of endlessly ratholing.

How to measure software development performance? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 6 years ago.
Improve this question
I am looking after some ways to measure the performance of a software development team. Is it a good idea to use the build tool? We use Hudson as an automatic build tool. I wonder if I can take the information from Hudson reports and obtain from it the progress of each of the programmers.
The main problem with performance metrics like this, is that humans are VERY good at gaming any system that measures their own performance to maximize that exact performance metric - usually at the expense of something else that is valuable.
Lets say we do use the hudson build to gather stats on programmer output. What could you look for, and what would be the unintended side effects of measuring that once programmers are clued onto it?
Lines of code (developers just churn out mountains of boilerplate code, and other needless overengineering, or simply just inline every damn method)
Unit test failures (don't write any unit tests, then they won't fail)
Unit test coverage (write weak tests that exercise the code, but don't really test it properly)
Number of bugs found in their code (don't do any coding, then you won't get bugs)
Number of bugs fixed (choose the easy/trivial bugs to work on)
Actual time to finish a task based against their own estimate (estimate higher to give more room)
And it goes on.
The point is, no matter what you measure, humans (not just programmers) get very good at optimizing to meet exactly that thing.
So how should you look at the performance of your developers? Well, that's hard. And it involves human managers, who are good at understanding people (and the BS they pull), and can look at each person subjectively in the context of who/where/what they are to figure out if they are doing a good job or not.
What you do once you've figured out who is/isn't performing is a whole different question though.
(I can't take credit for this line of thinking. It's originally from Joel Spolsky. Here and here)
Do NOT measure the performance of each individual programmer simply using the build tool. You can measure the team as a whole, sure, or you can certainly measure the progress of each programmer, but you cannot measure their performance with such a tool. Some modules are more complicated than others, some programmers are tasked with other projects, etc. It's not a recommended way of doing this, and it will encourage programmers to write sloppy code so that it looks like they did the most work.
No.
Metrics like that are doomed to failure. Different people work on different parts of the code, on different classes of problem, and absolute measurements are misleading at best.
The way to measure developer performance is to have excellent managers that do their job well, have good specs that accurately reflect requirements, and track everyone's progress carefully against those specs.
It's hard to do right. A software solution won't work.
I think this needs a very careful approach when deciding the ways to measure developers performance as most the traditional methods such as line of codes, number of check ins, number of bugs fixed etc. are proven to be subjective with todays software engineering concepts. We need to value team performance approach rather measuring individual KPIs in a project. However working in commercial development environment its important to keep a track and a close look at following factors of individual developers;
Code review comments – Each project, we can decide the number of code reviews need to be conducted for a given period. Based on the code reviews individuals get remarks about their coding standard improvements. Recurring issues of code reviews of same individual’s code needs to be brought in to attention. You can use automated code reviews tools or manual code reviews.
Test coverage and completeness of tests. – The % covered needs to be decided upfront and if certain developer fails to attempt it often, it needs to be taken care of.
Willingness to sign in to complex tasks and deliver them without much struggle
Achieving what’s defined as “Done” in a user story
Mastery level of each technical area.
With agile approach in some of the projects, the measurements of the development team and the expected performance are decided based on the releases. At each release planning there are different ‘contracts’ negotiated with the team members for the expected performance. I find this approach is more successful as there is no reason of adhering to UI related measurements in a release where there is a complex algorithm to be released.
I would NOT recommend using build tool information as a way to measure the performance / progress of software developers. Some of the confounding problems: possibly one task is considerably harder than another; possibly one task is much more involved in "design space" than "implementation space"; possibly (probably) the more efficient solution is the better solution, but that better solution contributes less lines of code than a terribly inefficient one which provides many many more lines of code; etc.
Speaking of KPI in software developers. www.smartKPIs.com may be a good resource for you. It contains a user friendly library of well-documented performance measures. At the moment it lists over 3300 KPI examples, grouped in 73 functional areas, as well as 83 industries and sub-categories.
KPI examples for the software developers are available on this page www.smartKPIs.com - application development They include but not limited to:
Defects removal efficiency
Data redundancy
In addition to examples of performance measures, www.smartKPIs.com also contains a catalogue of performance reports that illustrate the use of KPIs in practice.
Examples of such reports for information technology are available on: www.smartKPIs.com - KPIs in practice - information technology
The website is updated daily with new content, so check it from time to time for additional content.
Please note that while examples of performance measures are useful to inform decisions, each performance measure needs to be selected and customized based on the objectives and priorities of each organisation.
You would probably do better measuring how well your team tracks to schedules. If a team member (or entire team) is consistantly late, you will need to work with them to improve performance.
Don't short-cut or look for quick and easy ways to measure performance/progress of developers. There are many many factors that affect the output of a developer. I've seen alot of people try various metrics ...
Lines of code produced - encourages developers to churn out inefficient garbage
Complexity measures - encourages over analysis and refactoring
Number of bugs produced - encourages people to seek out really simple tasks and to hate your testers
... the list goes on.
When reviewing a developer you really need to look at how good their work is and define "good" in the context of what the comany needs and what situations/positions the company has put that indivual in. Progress should be evaluated with equal consideration and thought.
There are many different ways of doing this. Entire books written on the subject. You could use reports from Hudson but I think that would lead to misinformation and provide crude results. Really you need to have task tracking methodology.
Check how many lines of the codes each has written.
Then fire the bottom 70%.. NO 90%!... EVERY DAY!
(for the folks that aren't sure, YES, I am joking. Serious answer here)
We get 360 feedback from everyone on the team. If all your team members think you are crap, then you probably are.
There is a common mistake that many businesses make when setting up their release management tool. The Salesforce release management toolkit is one of the best ones available in the market today, but if you do not follow the vital steps of setting it up, you will definitely have some very bad results. You will get to use it but not to its full capacity. Establishing release management processes in isolation from the business processes is one of the worst mistakes to make. Release management tools go hand in hand with the enterprise strategy, objectives, governance, change management plus some other aspects. The processes of release management need to be formed in such a way that everyone in the business is on the same page.
Goals of release management
The main goal of release management is to have a consistent set of reliable and repeatable processes that are resource independent. This enables the achievement of the most favorable business value while at the same time optimizing the utilization of resources available. Considering that most organizations focus on running short, high-yield business projects, it is essential for optimization of the delivery value chain of the application to make certain that there are no holdups in the delivery of the business value.
Take for instance the force.com migration toolkit, as this tool has proven to be great in governance. A release management tool should allow for optimal visibility and accountability in governance.
Processes and release cycles
The release management processes must be consistent for the whole business. It is necessary to have streamlined and standardized processes across the various tool users. This is because they will be using the same platform and resources that enable efficient completion of their tasks. Having different processes for different divisions of your business can lead to grievous failures in tool management. The different sets of users will need to have visibility into what the others are doing. As aforementioned, visibility is of great importance in any business process.
When it comes to the release cycles, it is also imperative to have one centralized system that will track all the requirements of the different sets of users. It is also necessary to have this system centralized so that software development teams get insight into the features and changes requested by the business. Requests have to become priorities to make sure that the business gets to enjoy maximum benefit. Having a steering team is important because it is involved in the reviewing of business requirements plus also prioritizing the most appropriate changes that the business needs to make.
The changes that should happen to the Salesforce system can be very tricky and therefore having a regular meet up between the business and IT is good. This will help to determine the best changes to make to the system that will benefit the business. By considering the cost and value of implementing a feature, the steering committee has the task of deciding on the most important feature changes to make.
Here also good research http://intersog.com/blog/tech-tips/how-to-manage-millennials-on-software-development-teams
This is an old question but still, something you can do is borrow Velocity from Agile Software Development, where you assign a weight to each task and then you calculate how much "weight" you solve in each sprint (or iteration or whatever DLC you use). Of course this comes in hand with the fact that, like a commenter mentioned before, you need to actively keep track yourself of whether your developers are working or chatting online.
If you know your developers are working responsively, then you can rely on that velocity to give you an estimate of how much work the team can do. If at any iteration this number drops (considerably), then either it was poorly estimated or the team worked less.
Ultimately, the use of KPIs together with velocity can give you per-developer (or per-team) insights on performance.
Typically, directly using metrics for performance measurement is considered a Bad Idea, and one of the easy ways to run a team into the ground.
Now, you can use metrics like % of projects completed on-time, % of churn as code goes toward completion, etc...it's a wide field.
Here's an example:
60% of mission-critical bugs were written by Joe. That's a simple, straightforward metric. Fire Joe, right?
But wait, there's more!
Joe is the Senior Developer. He's the only guy trusted to write ultra-reliable code, every time. He's written about 80% of the mission-critical software, because he's the best.
Metrics are a bad measurement of developers.
I would share my experience and how I learnt a very valuable process on measuring the team performance. I must admit, I have fallen on tracking KPI simply because most of the departments would do the same but not really for the insight until I had the responsibility to evaluate developers performance where after a number of reading I evolved with the following solution.
One every project, I would entertain the team in a discussion on the project requirements and involve them so everyone knows what is to be done. In the same discussion through collaboration we would break the projects in to tasks and weight those tasks. Now previously we would estimate the project completion as 100% where each task has a percentage contribution. Well this did work for a while but was not the best solution. Now we would based the task on weight or points to be exact and use relative measurements to compare the task and differentiate the weights for example. There is a requirement to develop a web form to gather user data.
Task would go about like
1. User Interface - 2 Points
2. Database CRUD - 5 Points
3. Validation - 4 Points
4. Design (css) - 3 Points
With this strategy We can pin point a weekly approximate on how much we have completed and what is pending on the task force. We can also be able to pin point who has performed best.
I must admit that I still face some challenges on this strategy such as not every developer is comfortable on every technology. Somehow some are excited to learn technologies simply because they find 2015 high % of points fall in that section some would do what they can.
Remember, do not track a KPI for their own sake, track it for it's insight.

How to prioritize future features (enterprise web development) [closed]

Closed. This question is off-topic. It is not currently accepting answers.
Want to improve this question? Update the question so it's on-topic for Stack Overflow.
Closed 10 years ago.
Improve this question
Suppose you're the product manager for an internal enterprise web application that has 2000 users and 7 developers. You have a list of 350 future features, each ranging from 5 to 150 developer days of work.
How do you choose what features to work on, and how do you run the release process?
Here's what I'm thinking: (skip if boring)
Release Process. Work on several features at once, release each individually when it's ready. The other option (what we've been doing up to this point) is to pick out a certain set of features, designate them as "a release", and release them all at once (announcing via mass email).
The advantage of a shorter release process is that we can release features as soon as we finish development. The advantage of a bigger process is that it's easier to organize.
Feature Prioritization. Put all the future features in a spreadsheet with columns for feature, description, comments, estimate, benefit, (your) estimate, (your) benefit. Give copies to 2 senior engineers, the other senior project manager and yourself.
The engineers estimate all the features (how precisely? consulting each other?). To determine benefit, everyone allocates points (total = 10 * [number of future features]) among the future features (without consulting each other?), compare scores and average (?).
Another potential strategy here is to just rank each feature on an absolute (say) 1-100 scale. Having an absolute ranking is nice because it makes prioritizing as our feature list changes easier (we don't want to have to redistribute points every time someone proposes a new feature).
What's your strategy? Do any books / websites attack the problem at this level of detail?
There's a great book that helps cover this topic called Agile Estimating and Planning by Mike Cohn. It has some great ways to estimate and plan releases. Including a planning game called planning poker where the engineering team gets together with cards to estaimate user stories. Each engineer plays a card 1,2,3,5,8,13 face down. The high and low card explains and you do it again. After 1 or 2 repeats there is generally convergence on the same estimate.
There's also Beyond Software Architecture: Creating and Sustaining Winning Solutions by Luke Hohmann which might help with some of the product management related pieces and the reasoning to use to prioritization. I have not yet read the book but I went to a talk by Luke Hohmann where he covered the subjects of his book and I can't wait to read it.
Also I would recommend reading books on various Agile Development processes such as Scrum, Crystal Clear, and XP. There's Agile Project Management with Scrum by Ken Schwaber and Crystal Clear: A Human-Powered Methodology for Small Teams by Alistair Cockburn. Also Extreme Programming Explained: Embrace Change (2nd Edition) by Kent Beck and Cynthia Andres.
As for feature prioritization, that is generally done by the stakeholders. You need to work on the features that address the needs of your stakeholders, which, as Luke Hohmann points out, includes the system architecture.
However, one of the most important things is to make sure that you have agreement on the software development process from the team. If you force a process and the team doesn't believe in, then it will not work.
Surely you don't have 350 independent features, some must depend on others.
Put them all into some task management software which allows you to define which tasks depend on which other ones, and you might soon find that you've got a much easier decision process...
As for the release process, you could introduce the features when they are ready and inform the users via a company blog that is updated whenever a new feature is done. Such a blog entry should then give a short overview about the feature, where to find it, how to use it, etc.
Not only does this keep your users curious and coming back, it also offers a great way of potential customers to check out the progress of your offering.
As for prioritizing future implementation: how about involving the customers there as well? Look at uservoice (it is used to track requests/bugs for this site). It offers a nice way of letting the users vote on most desired things as well as showing what is being worked on and what is planned.
"rank each feature on an absolute (say) 1-100 scale"
Build them in order.
Release them when you've got (a) significant value or (b) critical mass of small things.
Always work in priority order. Build the most important stuff first. Deliver as much value as quickly as possible.
a few people here have already said it - involve the end users in the decision process of what goes in and what waits. after all, its not about whats useful to you, but whats useful to your end user.
that said, i wouldnt leave it open to 'all users to decide'; there should be a representative from the user group who you work with (i.e. senior user role).
even then, you arent saying "what features do you want?" to the user, you ask them what functionality they would like to see arrive next. the reason why you put it to them that way rather then letting them pick off a massive spreadsheet of individual features is two-fold: 1) they dont know about dependancies, 2) you want to gather together a pack of features for a logical release.
so the user representative may say "we need to have the photo gallery working next". they might not be aware that the photo galery is practically the same as the file upload module (it just accepts different file types).
so, in the next release version, you pack together the photo gallery and the file upload - why wouldnt you, considering that the file upload is like 75% done because of the work that went into the photo gallery module?
i dont believe you necessarily have to work on the hardest features first, its what the users need sooner + what other features you gather together to make a 'logical pack'.
to a certain extent, you want to clear the feature log too. so for example, you could have the following features and estimaed times:
Registration Form - 3 hrs
Photo Gallery - 8 hrs (<- client has said they want this next)
File Upload - 2 hrs
Voting/Poll module - 7 hrs
Stock Ticker - 5 hrs
out of these contrived features, i would take no. 2 (because the client is asking for it), then i would take no. 1 and 3. no. 3 because its practically done when the gallery code has been done, and no. 1 purely because its the smallest estimate out of the remaining features. nothing will give you or your coding crew the feeling of progress on your project like seriously beating down the feature list (it will probably refill though).
as far as letting people know about a new release and whats in it, i would do it via email (rather then by blog or within the program itself). and i would make it as brief as possible, bullet points, something like this:
===
Version 1.1 of Blue Widgets has just been launched and is available for your use now.
The following has been added:
Photo Gallery
File Upload
Registration Form
The user manual within the system contains more information on how these features work.
===
bang - done, make it as easy for people as possible.
LM

What are the major benefits of scrum as a methodology? [closed]

Closed. This question needs to be more focused. It is not currently accepting answers.
Want to improve this question? Update the question so it focuses on one problem only by editing this post.
Closed 5 years ago.
Improve this question
I work in the technical department of a design agency. We use XP to manage our department's software development. I have been asked to give a short presentation describing Scrum and whether it would be suitable, in a broader context, for managing client project work.
Scrum would be applied to cross functional teams containing graphic designers, information architects, content editors, user experience engineers, web designers and software developers.
What benefits could scrum bring to this sort of team?
Based on my experience, I would say the key features of Scrum are:
High visibility of progress.
Regular feedback from customer.
Predictable rhythm.
Measurable productivity (via burndown, velocity, etc.).
Cross-functional, self-organising teams.
Inspect and adapt.
Low bureaucratic overhead (meetings, documentation, etc.).
Emphasis on face-to-face communication.
And these features lead to the following benefits:
Project can respond easily to change.
Problems are identified early.
Customer gets most beneficial work first.
Work done will better meet the customers needs.
Improved productivity.
Ability to maintain a predictable schedule for delivery.
If we're talking about the benefits only they are pretty much obvious.
Using a proper methodology you work better, i.e. you have higher rate of successful projects. If your projects are already 100% successful you probably do not need to change anything.
For us using Agile helps to:
Increase the quality of the deliverables (because of the strict iteration rules, when you expect everything to be working by the end of the iteration instead of 'coding being complete' it works wonders)
Cope better with the changes (and expect the changes. It's mostly psychological issue but it really helps when your developers expect that a requirement will change at some point)
Provide better estimates and spend less time doing them
Be more in control of the project schedule and state (short iterations, clear, unambiguous ways of calculating the velocity etc.)
As a result we achieve higher customers satisfaction rate in general
In my experience, the main benefit is that your manager gets to say you are doing Scrum, and you get to waste more time going to daily meetings instead of getting work done.
... it's possible they weren't doing it right ;-).
For the team you describe I see these main benefits:
Visibility into what's happening and accountability. During the SHORT daily meeting you get a better idea of what's happening, what was finished and what was not. After some time you start to see trends: who's good estimating, who is not, who is telling you they are working when they really are not. You have a better picture of when you are going to be done.
Self organization. The team members are the ones that pick what to do and when for the given iteration. This takes time when people are not used to it, but ends up making team members happier because nobody is dictating who gets to do what. They decide.
Improved ability to rapidly react to requirements changes. The concepts of time boxing , daily status checks and user involvement will make it easier to both capture feedback and change your priorities.
I don't see much differences between XP and Scrum. If you already have XP, you likely don't need to switch. Maybe adopt some Scrum specific practices for better scalability like Scrum-of-Scrums. Almost all the other practices exist in XP like daily meetings, iterations, roles separation, retrospectives, etc.
In fact I am not sure that such separation have benefits. It is bette to decide what you are doing bad during retrospective meetings and apply practices from any process (or create own solutions) to your specific problems. XP and Scrum give you a framework that will help to be adaptive and creative. While traditional processes gives you a set of rules that impedance any creative behavior.
Your team and your project IS special. Think and communicate to sharpen your development process.
First of all Scrum is a methodology for project management not for development...it can be combined with XP or RUP...
Scrum is good for you if you have a project that changes...when your requierements changes you need to keep up with these changes... Scrum has short iterations (2-4 weeks) and this provides more response to the changes... and the client can have a early release of his product and you can have all that feedback you need... maybe this is the first benefit...
Another benefit: your team will be always working syncronized specially when they depend on each other...
As I understand it, daily Scrum meetings are for the team to discuss progress and blocking issues. The Scrum master facilitates. The product owner can be invited if the team decides to do so, but the meeting is not intended to provide any progress status to a boss or a manager.
I hope I am correct.
When you say "Scrum" I don't know if you mean agile, or just the daily meeting. Assuming you just mean what is the advantage of the daily meeting I see 3
1 - You have an opportunity to expose any issues you are having to the entire team and can get help an advice from people you might not have thought to ask. It's more efficient that having to interrupt coworkers throughout the day to try to get help for some problems you're having.
2 - Group teams get a better picture of what the entire group is doing and you have an opportunity to influence development you're not immediately involved in.
3 - You generally get to spend less time writing progress reports because everyone, including your boss, hears everyday what you're working on and what progress you've made.
That's my experience with scrum
I've been "Scruming" for two years and my experience tells me that it's much easier to know "where we are" at any point because the development process is in fixed length periods (Sprints) that allows to evaluate what's been done. And in the middle of those periods having the Daily Scrum (those meetings Dmitriy was talking about) and the Burndown Chart (the graphic of the remaining work) allows the team and the manager to always know what's already done and what's the team is working on.
In your case you'll probably need to have several smaller Scrums, instead of a large one, because Scrum works best with smaller teams. This book has some insights about that:
http://www.infoq.com/minibooks/scrum-xp-from-the-trenches
You won't get deadlines getting late :)
I think scrum is more of a habit than a method or practice. There are lot of teams operating in scrum without knowing that they are doing agile and there could be lot of teams claiming that they are agile and not following the basic principles of scrum.
I have worked with kanban, waterfall, agile scrum and others while development software products and with my experience, I am more comfortable with scrum. It gives you sense of achievement and keep you awake in the light of what needs to be achieved further and how to do it.
Scrum product development methodology is based on incremental and iterative product development process where solutions grow due to collaboration between cross-functional and self-organizing teams. Here are the major benefits of scrum
Simplicity and transparency of processes
Adaptive planning
Quick adaptability to change
Evolutionary development and delivery model
Iterative approach
Quick learning cycles
Automated testing offers a stable platform
Rapid market release
Integrated and flexible teams which can change requirements anytime based on user feedback
I feel I have made enough justice to the answer.
Here is where you can learn more on my experience: http://www.cygnet-infotech.com/blog/agile-scrum-methodology-for-product-engineering
Team Spirit
High visibility of progress.
Frequent demonstration and early feedback from stakeholders
Problems are identified early
Quality of product and Improved productivity
Higher customer satisfaction

Obtaining Management Buy-in on Process [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
The company I work for has historically had very little process as far as software development. Currently we don't really follow any specific method. The problem is of course it makes it difficult to plan, successfully have a decent release or even attract good software developers.
I think I may be able to convince them to do some sort of Scrum process. Key however is getting management/owner buy-in. The idea of locking into specific features for any period of time I think scares them off.
Does anyone have any suggestions on how I can make my case?
So far I plan to:
Give presentation on how Scrum works. how I see it working with the people we currently have and how it will benefit the business.
Ask for training for specific people so we aren't "making it up as we go along"
Set a date to implement, there is some planning and loose ends I probably have to tie up to start a process fresh.
If your projects are like the standard / typical IT projects, then chances are your projects have failed, or been buggy, or cost too much, or didn't do what the customer (internal or external) needed, or took too long to develop.
If you are going to advocate a process, it needs to be shown that you will not lose flexibility just to have structure.
Points to make to decision makers:
Having a Scrum-like process will improve how much information that management has at its fingertips, and allow them to make decisions more quickly. Consider the scenario that you have a 6 month project. Well, with no processes, how do you know how much work is done until it is released? With Burndown charts, you can track how much time is left in a visible way. If you couple that with TDD, where you define say 100 test cases, they can see that 50% of the test cases are left to get working, but from the burndown rate there is only enough time to do 25% (remember Managers like it simple, so this isn't a perfect state of the project, but it is an easy to understand one that was better than what they had before). .e.g. they will feel more in control because the projects have better visibility.
Having process allows you to improve quality, which long term will result in less bugs, less time spent on bugs, more knowledge transfer (what happens if your star developer is hit by a bus), and all this means that the company will get developers focused on a better product than on continuously fixing bugs. e.g. this will save them money
A small set of changes will be implemented first. This will be a proof of concept, and safe and easy to back out of if needbe. e.g. this shows that you are mitigating perceived risk . And you need to mitigate perceived risk because that is what they'll be focusing on. That said, you will want to gather some data before you even make the proposal. Why? Good question: you need a baseline for 2 reasons:
You'll want to know how much the changes have helped. So you can propose more changes.
You'll likely have a manager complain about a problem while the proof of concept is going on. You'll want evidence that shows that problems in a chaotic process free environment are the norm, and this is not a worsening of the state, and perhaps a slight improvement. You can bet on something going wrong in a process-free environment. And you can bet that the proof of concept process changes will be blamed. So be ready for it.
In my experience it's easier to sell management on a design methodology or practice after it's been piloted once. I would cherry-pick a small project, usually internally facing if possible, and ask to "pilot" your new scrum process. Generally it's a lot easier to get people to buy into a pilot because they only have to commit on a limited basis.
As your new scrumified pilot project moves along, be sure to document (post-its, notepads, Word doc, whatever) how scrum is making your project more or less successful than the previous (lack of) method. Be brutally honest here, and try to quantify things in real terms whenever possible.
After the project completes, compile your notes and present to management your findings using the completed project as evidence. Use findings such as:
"product backlog provided users with real sense of progress on featureset X"
"pigs/chickens meetings style saved X man/hours a week by keeping meetings in control"
"sprints allowed developers to work more closely together and resulted in X% less buggy code"
Generally, if you can bring leaders to a spot where they can draw dollars-and-cents conclusions, they will go for a new product or methodology. Also, and this is important as well, be prepared to walk away from your original process ideas if you find them not bearing out during the pilot.
Good luck and happy productivity!
You can sell Scrum as a "No Lose" proposition. Look at what happens when you use Scrum:
All development work is always focused on the highest priority tasks.
Progress is 100% open, and inspected daily.
Users/customers get to examine the progress at the end of every iteration.
Shifting requirements are handled automatically.
The only reasonable objection that I've ever seen to Scrum is that it isn't really possible to predict how much a project will cost, or how long it will take. This is because Scrum acknowledges that everyone will learn as the project commences, and the requirements will change. Waterfall pretends to be able to do this, but we all know how well this works.
Run the Joel Test to determine how much work you have to do. If you are having trouble estimating release dates, look into Evidence Based Scheduling.
Provide some sort of argument that shows how Scrum will address past pain points experienced by the key decision maker. Extra points if you can also provide evidence that demonstrates this.
Keep in mind that it is also possible that you don't have a process because the management doesn't know and doesn't care about it. If your managers have no interest or no understanding of a process, such a process could also be started by getting all the programmers to agree to it (or at least team leaders) and telling new employees, "this is how things are done." Of course, it is necessary that you pick a process that is compatible with your manager's requirements if you do this (e.g. if your managers ask for daily updates on milestones, don't pick a process that has no coding for the first two weeks).
This is really only appropriate if you have a discussion with a manager and their basic reaction is "It doesn't matter, as long as you keep writing code." If you present a process as being a means to redistribute order of work done rather than as one which adds new work, you're more likely to succeed in such an approach.