How effective is scrum for short-timespan projects? [closed] - project-management

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
For projects that should take between two and six weeks, is Scrum the right way? Having read up on Scrum a bit, I was left with the impression Scrum is an excellent choice for mid to large sized projects.

I've run short projects of around 5-6 weeks using 1 week sprints - I found it useful to have each sprint run from Wednesday->Tuesday - the team was fresher for the final two days of the sprint, and carried through the rest of the week by new stories!
One thing we struggled with in 1 week sprints was getting stories tested - we would sometimes start a new iteration with some stories not formally tested. Here we had to "tweak" the process a little to perform tests over 2 week cycles.
In short, it's doable, and you can still reap the benefits of iterative development. You just might find yourself making a few compromises in the process.

We do Scrum for short projects all the time, I find it it is much more productive for short term stuff than the waterfall approach or similar phasing.
Just one word of warning: start bugfixing from day 2, keep testing intensely. Our first Scrum tries led into truckloads of bugs to fix (for free) after the delivery of the product.
Nowadays we maintain a stringent "not done until free of bugs" policy, per story, which works wonders, without hurting productivity! If it's broken it's not in the release.
Have fun at Scrumming!

I think the point of scrum is that it delivers business value throughout rather than just at the end, I guess you have to decide whether your project can do that and whether it needs to do that.
Also read this, very simple explanation of how scrum works, you will be able to think about how it will affect your project while reading. http://www.softhouse.se/Uploades/Scrum_eng_webb.pdf

Depends on your velocity. Usually a sprint is around 2 weeks. Using a formal process for just 3 sprints seems a bit overkill to me. I would still recommend using it, but not be so rigid about sticking to the process too much.

Related

Is Scrum useful for single programmer developments? [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
I lead a team of six programmers, and we are presently implementing a number of agile development practices. I'm very interested in Scrum, however it seems to assume that your project will have multiple developers. Most of my projects are smaller, and involve a single developer. We run 3 or 4 such projects in parrallel at any time.
From reading Schwaber, a lot of the benefit of Scrum seems to derive from teams self-organising to achieve a complex task. If you have a single developer doing all the work, will Scrum deliver much value?
Scrum might be more than you need as a single developer, but if you have a stake holder and a QA person then Scrum can still be helpful. Remember they are apart of your team, and should be at your standups to trade information with the team.
If you are truly alone there are other agile practices that might make more sense to you. For example, Kanban might be a better fit. You don't have iteration overhead, retros, sprint planning, etc. You just have a backlog that you pull tasks from. This works well as a way to organize your work, allows stake holders to adjust priorities, and works well for a single developer or small team where you can break up work without a lot of need to synchronize between developers. Maybe you have a product built that only has small features that doesn't need a lot of architecture being built to support new features. Or lots of small projects that are independent say for advertising firms, etc.
The single most important benefit of Scrum that is there even if there is just one developer is not the daily sync (meeting), but rather the limitation on context switches. While working in sprints this single developer can concentrate on given stories within his (presumably short) sprint knowing he won't be interrupted or pushed to do something else before finishing this.
Less context switching == less waste == more productivity.
BTW - Kanban offers less overhead than Scrum, but it is easier to circumvent and force developer to context switch. This can be a benefit but can easily become a problem too.
I think that the value you may get can come from scrum or other agile concepts.
For example, instead of a weird standup meeting, have the one developer tell you why he has taken x desicion for the y task. You may or may not be able to suggest things (depends on your background as a developer I guess), but the fact that the developer is hearing his own explanation might be useful for finding bugs or dead-end reasonings.
As a professor of mine once commented on asking yourself a question aloud: "If you ask the universe for an answer, it will give you one"
While, as others have pointed out, the daily standup may be weird, there's still value for an individual developer in adopting a scrum-'like' process.
Timeboxed, potentially releasable, iterations and a stack-ranked backlog can only help an individual developer keep focused on actually getting something done instead of endlessly ratholing.

How small is too small for a project plan? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 3 years ago.
Improve this question
I have friends who have asked me to make websites and most are very small, usually I don't bother with a technical plan but one friend in particular clearly had goals larger than my own and the project is dragging on forever. If I had made a spec before the project I feel like this wouldn't have happened and our relationship would be as solid as before.
So my question is, how can you tell how small is too small? How do you tell when the project you're embarking on is going to end up in a guilt-ridden scope creep nightmare?
If you are going to be charging money (or don't want to be stuck doing the project forever), a project plan is always a good idea. Even if it's just a one-pager outlining what the web site will have (how many pages, any special features) and who is responsible for what. You should factor in that you'll spend 20% of your time (or whatever percentage past experience has taught you) on documentation or non-coding type work, you can give a better estimate of the effort needed. If it's a friend, you might want to tell them that you'll do the first X hours for free, but after that your rate is $Y per hour. Also, keep an accurate log of the time you've spent so that you can show them the amount of effort that is involved. Also, keeping an accurate log helps you estimate future projects.
As you may have already figured out, no project is too small to have at least an informal, written plan. Even if it's just a features list.
A project that does not need a plan is a project that does not need to be even started. In my opinion everything needs a plan, what changes is the extent of that plan. A plan could be just a list of deliverables and some deadline attached to each one. A more robust plan should include time charts, cost, phases, communications howto, dependencies, etc. So I think everything needs a plan, the contents of the plan is what changes depending on the project complexity.
Dwight Eisenhower on planning:
In preparing for battle I have always
found that plans are useless, but
planning is indispensable.
It seems the same in many software projects: you'll find that your plans need to be continually updated and that your first plan was quite different from what you finally completed. But that's okay, it's much better to put some planning in up front than to try something by the seat of your pants.
Agilists try to accommodate such changes in plans by breaking longer term plans into small "sprints" of 2-4 weeks. They'll have more details on the near term sprints, and fewer details on the longer term goals.
You'll especially want to be more detailed and precise if the project is bigger, if you are doing this for an external customer, or if you're attempting something new for you. It's less important (though not unimportant) for smaller projects and types of work you've done before and are very familiar with.

Has Crashing or Fast-Tracking a project schedule ever worked? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
I posted this question on Reddit Programming and did not get a single response. So I am hoping that Stack Overflow community will have an opinion.
Have any of you ever been on a software project that had fallen behind, where 'Crashing' or 'Fast-Tracking' the project schedule actually brought the project schedule back on track? I have never seen either of these project management techniques actually work. And all the articles on software development that I have read all state that these 2 techniques do not work and actually pushing the project further behind (for example literature on the Mythical Man Month). So who has seen it work?
Thanks Bill.
I have only ever seen it work once. It was a three or four month long project that was projected to run an extra two months over the original delivery date. The project got fast-tracked and things ended up getting back on track for the release.
...keep in mind though, that was only once. I've been on many more projects where the PM tried to use one of those two methods and they failed miserably and dragged the project out for months beyond already extended date.
It can work. But there's a price to be paid: lower quality (more bugs, less testing) and turnover of burned-out programmers.
And in many cases, a fast-tracked project will both fail to deliver on time and will still pay the full negative price, for the reasons stated in Mythical man-month.
I've seen it work but it's not the norm.
Things I'd want to see before I thought it might be feasible:
1) Staff available with suitable skills and approach. By that I don't mean ".NET programmer", I mean detailed technical skills, business domain skills (so they understand the problem), personality fit and understand the tools and the approach (source control, methodology and so on). This can happen in large companies where there are common tools, standards and knowledge but you need to be sure that they're ticking pretty much all the boxes.
2) Tasks must be nicely divisible. The best situation is where there are whole modules, applications or tasks unstarted and you can put new people on that. It minimises upskilling, additional communication and so on. If you can't separate out what the new people will do you're likely to majorly disrupt the existing team.
3) The whole team must have bought into the approach. If the existing team don't agree that bringing people on board will be right they'll likely fight it and you're doomed.
4) You need to be sure you've addressed why it was running late in the first place. If it was just bad estimates then are you confident the new estimates are good? If it was scope creep have you got the scope and change control in hand now? If it was because the deadline moved, are you sure it won't move again?
If you can't tick all four of those off, it isn't going to work.
Crashing and Fast-Tracking are two very different things...
Fast Tracking is where you take something (tasks or work packages) out of sequence and do it early. This may because of hardware delivery lead times, availability of resources, risk or whatever. So you might do things in parallel where originally you had planned to do it sequentially. I've fast tracked a lot of projects.. and yes it works.
Crashing a project is different in that you typically throw more resources at a problem to get it done quicker... this can be tricky. If it's done as a crisis response it can be painful adding extra people as you are already under the pump. In some situations you just add more problems.
Another alternative to crashing is to reduce scope. This is not always possible, but it should be considered.
With fast tracking or crashing... the sooner you know when you need to make a schedule change the easier to manage. This is why early deadlines are so important, they indicate how the rest of the project will go.
Both of these project management techniques work well to maintain a schedule, but they should be used intelligently by judiciously analyzing the network diagram:
study the variance,
study lead and lags;
decide what suits to your project: ‘Crashing’ or ‘Fast-Tracking’.
There is a software management principle that says adding manpower to a late project makes it later.
That said, as long as the measures taken are sensible it should be ok. Don't expect too much of your staff and provide reasonable incentives and don't take short cuts. It won't make miracles happen but if you're practical and want to push things just that little bit faster it can definitely be done.
When people have a stake in the potential success of something it's amazing how much more effort they're willing to put in.
It depends on what you mean by "work". I don't think I've ever seen it make a way late project deliver on time, if that's what you are asking.
However, I have seen it make way late projects deliver only a bit late. From the fuzzy perspective of management, that might be called "working". I've also seen it significantly lower the customer-based pressure on the company. Some might also call that "working".
Of course the price is rather high. Employees burn out, develop health problems or big problems in their neglected personal lives, etc. All of that has large financial repurcussions to the company. So I doubt the company comes out ahead in the long run. Is that "working"?

How to convince a client that all next projects/enhancements should be done via TDD (with some agile practices)? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
We are a small team (3 developers) and one of our main clients is about to submit a bunch of new feature requests and a follow on project to us to get estimates on cost and delivery times. Our last project with them was a 'success' in that they are coming back to us but I know we could have done a much better job (we used waterfall... testing was an after thought and as a result unit-testing code coverage is significantly lower than we feel comfortable with, not to mention the never-ending 'we are ALMOST done' problem).
I have just finished reading 'Art of Unit Testing' and 'Working Effectively with Legacy Code' and I have used TDD on a pet project of mine outside of work and now I can never go back to waterfall and testing after the fact.
What I want to know is are there are good 'easy to digest' videos for non-developers that clearly show the benefits of TDD along with Agile practices in a business sense? I'd be super happy if there are any sub 10 minutes videos but I'm also OK with longer videos (and I will reference them to a time index in it). If there are no good videos then a written source is next best thing.
I want nothing more than for them to be on board and really excited with the transition.
For me it is not an option to 'just do it' as there will definitely be a learning curve for the other two developers and without doubt the first number of iterations may be stressful and bumpy and that needs to be communicated to our client.
[I have answered my own question below with a number of videos I found since asking the question... they are not perfect for my use but definately my plan B if no-one else knows of a better one]
Technical debt kills velocity. Thus, I like to include "No increased technical debt" in the Definition of Done. Without this, you can't achieve sustainable pace. This is illustrated by the picture below (borrowed from the Technical Debt - How not to ignore it presentation from Henrik Kniberg):
alt text http://img27.imageshack.us/img27/329/screenshotkq.png
To me, all these things are obvious and you can even prove it with numbers (by measuring the velocity over time). Explain these concepts to your client, explain him that TDD is one of the techniques allowing to control technical debt. Then, let him choose (or choose for him).
How you run your project internally is your business. Don't involve them in this decision. They are not experts in software development processes. Ask them about business requirements and things they know about.
Sound like you are doing this to improve project quality. Do you think it will cost more to do TDD? Why work to convince them of something and then ask their approval? Did you ask if you could do waterfall on the last project?
Why would your client even notice the transition to TDD? Stressful, bumpy; how so?
Tell the client why you are upgrading to TDD. I'm sure the reasons are as compelling to them as they are to you. To me, TDD first of all means a much greater sense of reliability on what you produce.
Surely your client remembers all the regressions and manual testing from your last project?
I don't know of any specific illustrations for you (the web is full of articles and blogs, but I'm not aware of any videos), but you pretty much answered your own question...
we used waterfall... testing was an after thought and as a result unit-testing code coverage is significantly lower than we feel comfortable with, not to mention the never-ending 'we are ALMOST done' problem
You just need to be honest with your client. Explain to them what the project methodology you used on your last project cost them in terms of flexibility, maintainability, and your ability to confidently provide them with quality code. Explain to them how TDD addresses that, and explain that you anticipate a slower start due to using a new methodology.
Illustrate for them, as concretely as possible, what they will gain, and it should be an easy sell. I would, however, approach it more from the "this is what we're planning on doing" angle, rather than the "can we please do this?" angle. Give them the impression (without being dishonest) that you are already planning on going this way and any change to that plan will be an inconvenience to you and your team, and will likely cost them productivity.
I'm not aware of any videos, but explain to them that it took you N man-hours to redesign a certain feature on the last project due to original design not being correct taht was not caught until you started testing; and with TDD it would take M (<<N) man-hours since you would not spend the extra hours working based on a bad design/bug as happened last time.
Also, explain that the confidence level of having less buggy software will be raised by Y percent due to thought-out tests.
Then explain you estimate X hours for learning curve on the FIRST peoject, and ask them if the given benefits on ALL future projects will be worth it, when the initial time investment is depreciated across those.
Firstly, unit testing isn't unique to Agile methodologies; I've been around a while and have seen it used on waterfall projects. In fact, I heard of unit testing long before I heard of Agile!
Afraid I can't point you to any videos that will help convince a client to switch development methodologies. Google may help though; if not with videos, then maybe with studies, blogs, etc.
Anyway, one suggestion for improving the chances that the client will accept your reduced productivity during your learning curve is to reduce his costs somehow. E.g. if you're billing by the hour either charge less by the hour for time spent learning, or just don't bill for those learning hours.
I spent the time since asking this question looking for the best videos I could and I've come across a number that are very close to what I need. I will post them here so that others will find them if they are in a similar position to me.
I realise that I asked more about TDD - but these videos capture a good portion of the message I'm trying to drive home... especially 'Why does Agile Software Development Pay' and 'Scrum in under 10 minutes'... it is the process of being responsive to change, producing higher quality code, having fewer defects and faster development cycles.
Agile vs waterfall: A Tale of Two Teams (8:20)
Why does Agile Software Development Pay? (5:03)
Scrum Basics (5:50)
Scrum in under 10 minutes (7:59)

Advice for Date Driven Development Model [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 3 years ago.
Improve this question
Does anybody have any advice on working in a Date Driven Development environment? Essentially, we are updating our RIA every 8 weeks. I work in a small team of less than 5 developers, so I'm concerned about how to manage long-term features that don't fit in small cycles. Additionally, I'm concerned about being in a state of perpetual crunch-time.
Rule 1. Defer features.
If it's not done, (1) defer it to the next release and then (2) figure out why.
"Pushing", "Overtime" and "working smarter not harder" don't actually do much. The point is to be realistic about your plans.
Plans are an attempt to predict the future.
You cannot predict the future.
Therefore, your plans will be wrong. Always.
Rather than rant and rave about "the plan", "the commitment" and "customer expectations", think about this.
Your goal is to deliver features at a pace that is faster than the users can make use of them.
Strive for 2-week increments. Tested, Integrated, ready-for production.
After the first four sprints, you're at 8-weeks, ready to release. You will have built things, deferred things, and wound up with a deferred list at the end.
Many cycles of new features will -- generally -- bother the users with the pace of change. You wouldn't release each 2-week sprint because the users don't like this. If you release too often, you get told to bundle the features together into a bigger release so that the pace of change seen by the users is slower.
You must still do many small cycles. Aim for 2-week sprints where you build some small subset of your bigger backlog.
You just don't release each small cycle.
8 weeks is a lot of time....compared to some shops that have 1 or 2 week releases...so you're fortunate. Some recommendations:
prioritize your maint/bug fixes with the help of your client/business owner after each release and work your way from top of list down...(sounds simple until you get a last minute must have in there)
the development for cycle 'D' should actually start in cycle 'C' in regards to planning and should end 1-2 weeks prior to delivery to ensure proper QA and fixing of found issues
there will always be 'something' to make you question pushing the delivery date - don't give into it - reduce scope/keep to the date
break the larger deliveries into smaller ones and promote in a manner that they are 'there' but no 'live' (beta) - this incremental work might add some extra effort, but should reduce end of delivery QA/bug related issues and risks
track important metrics - for planning and showing progress

Resources