These are previous homework problems, but I am using them as exam review. I am changing numbers around from what is actually in the problem. I just want to make sure I have a grasp on the concepts. I already have the answers, just need clarification that I understand them. This is not homework but review work.
Anyway, this focuses on aspects of CPI
The fist problem:
An application running on a 1GHz processor has 30% load-store instructions, 30% arithmetic, and 40% branch instructions. The individual CPIs are 3 for load-store, 4 for arithmetic, 5 for branch instructions. Determine the overall CPI of this program on the given processor.
My answer: The overall CPI is the sum of the sub-CPIs, multiplied by the percentages in which they occur i.e. 3*0.3 + 4*0.3 + 5*0.4 = 0.9 + 1.2 + 2 = 4.1
Now, the processor is enhanced to run at 1.6GHz. The CPIs of the branch instructions remain the same but load-store and arithmetic instruction CPIs both increase to 6 cycles. A new compiler is in use which eliminates 30% of branch instructions and 10% of load-stores. Determine the new overall CPI and the factor by which the application will be faster or slower.
My answer: Once again, the new CPI is just the sum of its parts. However, the parts have changed and this must be accounted for. Branch instructions will drop by 30% (0.4*0.7=0.28) and load-stores will drop by 10% (0.3*0.9=0.27); arithmetic instructions will now account for the rest of the instructions (1-0.28-0.27=0.45), or 45%. These will be multiplied by the new sub-CPIs to get: 6*0.45+6*0.27+5*0.28=5.72.
Now, the processor enhancement is 60% faster, and the CPI is greater by (5.72-4.1)/4.1 = 39.5%. Thus, the application will run roughly 0.6*0.395 = 23.7% faster.
Now, the second problem:
A new processor with a load/store architecture has an ideal CPI of 1.25. Typical applications on this processor are a mix of 50% arithmetic and logic, 25% conditional branching and 25% load/store. Memory is accessed via a separate data and instruction cache, with a 5% instruction cache miss rate and 10% data miss rate. The penalty of any cache miss is 100 cycles and hits don't produce any penalties.
What is the effective CPI?
My answer: The effective CPI is the ideal CPI, plus the stalled cycles per instruction due to cache access. The ideal CPI is, as given, 1.25. The stalled cycles per instruction is (0.1*100*0.25) + (0.05*100*1) = 7.5. 0.1*100*0.25 is the data miss rate multiplied by the stalled cycle penalty which is also multiplied by the load/store percentage (which is where the data accesses take place); 0.05*100*1 is the instruction miss rate, which is the instruction cache miss rate times the stalled cycle penalty, instruction access take place in 100% of the program, so this is multiplied by 1. Following from this, the effective CPI is 1.25 + 7.5 = 8.75.
What is the misses per 1000 instruction for typical applications and what is the average memory access time (in clock cycles) for typical applications?
My answers: The misses per 1000 instructions is equal to the stalled cycles per instruction due to cache access (as given above: 7.5), divided by 1000, which equals 7.5/1000 = 0.0075
When discussing the average memory access time (AMAT), we first must talk about the total number of accesses here, which is the percentage of data accesses (25%) plus the percentage of instruction accesses (100%), or 125%=1.25. The data accesses are .25/1.25 and the instruction accesses are 1/1.25.
The AMAT equals the percentage of data accesses (.25/1.25) multiplied by the sum of the hit time (1) and the data miss rate multiplied by the miss penalty (0.1*100), or (.25/1.25)(1+0.1*100) and this is added to the percentage of instruction accesses (1/1.25) multiplied by the sum of the hit time (1) and the instruction miss rate multiplied by the miss penalty (0.05*100), or (1/1.25)(1+0.05*100). Put together, the AMAT is (.25/1.25)(1+0.1*100)+(1/1.25)(1+0.05*100)=7.
Once again, sorry for the wall of text. If I am wrong, please try to help me understand how I am wrong. I tried to show all my work to make it as easy as possible to understand. Thanks in advance.

There's an error in the lat part of your question. When they ask:
What is the misses per 1000 instruction for typical applications and what is the average memory
access time (in clock cycles) for typical applications?
what's needed here is the number of misses you will get for every 1000 instructions, which in this case would be 1000*1*0.05 for instruction cache misses and 1000*0.25*0.1 for data cache misses. This equals 75 misses per 1000 instructions.
To calculate the AMAT, you use the formula AMAT = hit time + (miss rate*miss penalty)
In this case, your miss rate is 75/1000 and your miss penalty is 100 cycles. The hit time is given as 1.25 cycles (your ideal CPI!).
Hope this helps and all the best for your exam!

Related

How to determine which processor has the highest performance

The following conditions exist.
Consider three diff erent processors P1, P2, and P3 executing the same
instruction set. P1 has a 3 GHz clock rate and a CPI of 1.5. P2 has
a
2.5 GHz clock rate and a CPI of 1.0. P3 has a 4.0 GHz clock rate and has a CPI of 2.2.
And the question is
Which processor has the highest performance when executing the same program?
I have learned to compare cpu execution when comparing computer performance.
However, since cpu execution time = CPI * instruction set * 1/clock rate, the size of the instruction set cannot be known only with the conditions in the above problem, I thought that the performance between processors could not be compared.
I looked for other issues similar to this one, and the issue is Which processor has the highest performance expressed in instructions per second? We compared the performance between processors under the condition of instructions per second as shown.
So what I want to know is whether it is possible to compare performance between processors without any special conditions. (Isn't the given problem wrong?) If possible, I wonder how they can be compared.
However, since cpu execution time = CPI * instruction set * 1/clock rate, the size of the instruction set cannot be known only with the conditions in the above problem, I thought that the performance between processors could not be compared.
For that formula; I'd assume that instruction set reflects how many instructions are needed to do the same work. E.g. if one instruction set can do a multiply in one instruction it might have instruction set = 1, and if another instruction set needs 20 instructions to do one multiply then it might have instruction set = 20 because you need 20 times as many instructions to get the same work done.
For your homework (3 processors that all execute the same instruction set), instruction set is irrelevant - they all take the same number of instructions to get any amount of work done. With this in mind you can just do performance = clock rate / CPI. More specifically:
P1 = 3 GHz / 1.5 = 2,000,000,000
P2 = 2.5 GHz / 1.0 = 2,500,000,000
P3 = 4 GHz / 2.2 = 1,818,181,818
Of course the homework is extremely over-simplified - stalls (time CPU spends doing nothing while waiting for things like cache misses and instruction fetch after a branch misprediction, etc) tend to have a larger impact on performance than clock speed or "theoretical maximum CPI"; and "measured CPI in practice" depends which specific instructions are used (and can never be a single number like "1.5 CPI" for all programs). In other words, in practice, it's easy to have a situation where a CPU is fastest for one program but slowest for another program.

Calculating Cycles Per Instruction

From what I understand, to calculate CPI, it's the percentage of the type of instruction multiplied by the number of cycles right? Does the type of machine have any part of this calculation whatsoever?
I have a problem that asks me if a change should be recommended.
Machine 1: 40% R - 5 Cycles, 30% lw - 6 Cycles, 15% sw - 6 Cycles, 15% beq 3 - Cycles, on a 2.5 GHz machine
Machine 2: 40% R - 5 Cycles, 30% lw - 6 Cycles, 15% sw - 6 Cycles, 15% beq 4 - Cycles, on a 2.7 GHz machine
By my calculations, machine 1 has 5.15 CPI while machine 2 has 5.3 CPI. Is it okay to ignore the GHz of the machine and say that the change would not be a good idea or do I have to factor the machine in?
I think the point is to evaluate a design change that makes an instruction take more clocks, but allows you to raise the clock frequency. (i.e. leaning towards a speed-demon design like Pentium 4, instead of brainiac like Apple's A7/A8 ARM cores. http://www.lighterra.com/papers/modernmicroprocessors/)
So you need to calculate instructions per second to see which one will get more work done in the same amount of real time. i.e. (clock/sec) / (clocks/insn) = insn/sec, cancelling out the clocks from the units.
Your CPI calculation looks ok; I didn't check it, but yes a weighted average of the cycles according to the instruction mix.
These numbers are obviously super simplified; any CPU worth building at 2.5GHz would have some kind of branch prediction so the cost of a branch isn't just a 3 or 4 instruction bubble. And taking ~5 cycles per instruction on average is pathetic. (Most pipelined designs aim for at least 1 instruction per clock.)
Caches and superscalar CPUs also lead to complex interactions between instructions depending on whether they depend on earlier results or not.
But this is sort of like what you might do if considering increasing the L1d cache load-use latency by 1 cycle (for example), if that took it off the critical path and let you raise the clock frequency. Or vice versa, tightening up the latency or reducing the number of pipeline stages on something at the cost of reducing frequency.
Cycles per instruction a count of cycles. ghz doesnt matter as far as that average goes. But saying that we can see from your numbers that one instruction is more clocks but the processors are a different speed.
So while it takes more cycles to do the same job on the faster processor the speed of the processor DOES compensate for that so it seems clear this is a question about does the processor speed account for the extra clock?
5.15 cycles/instruction / 2.5 (giga) cycles/second, cycles cancels out you get
2.06 seconds/(giga) instruction or (nano) seconds/ instruction
5.30 / 2.7 = 1.96296 (nano) seconds / instruction
The faster one takes a slightly less amount of time so it will run the program faster.
Another way to see this to check the math.
For 100 clock cycles on the slower machine 15% of those are beq. So 15 of the 100 clocks, which is 5 beq instructions. The same 5 beq instructions take 20 clocks on the faster machine so 105 clocks total for the same instructions on the faster machine.
100 cycles at 2.5ghz vs 105 at 2.7ghz
we want the amount of time
hz is cycles / second we want seconds on the top
so we want
cycles / (cycles/second) to have cycles cancel out and have seconds on the top
1/2.5 = 0.400 (400 picoseconds)
1/2.7 = 0.370
0.400 * 100 = 40.00 units of time
0.370 * 105 = 38.85 units of time
So despite taking 5 more cycles the processor speed differences is fast enough to compensate.
2.7/2.5 = 1.08
105/100 = 1.05
so 2.5 * 1.05 = 2.625 so a processor 2.625ghz or faster would run that program faster.
Now what were the rules for changing computers, is less time defined as a reason to change computers? What is the definition of better? How much more power does the faster one consume it might take less time but the power consumption might not be linear so it may take more watts despite taking less time. I assume the question is not that detailed, meaning it is vague meaning it is a poorly written question on its own, so it goes to what the textbook or lecture defined as the threshold for change to the other processor.
Disclaimer, dont blame me if you miss this question on your homework/test.
Outside an academic exercise like this, the real world is full of pipelined processors (not all but most of the folks writing programs are writing programs for) and basically you cant put a number on clock cycles per instruction type in a way that you can do this calculation because of a laundry list of factors. Make sore you understand that, nice exercise, but that specific exercise is difficult and dangerous to attempt on real world processors. Dangerous in that as hard as you work you may be incorrectly measuring something and jumping to the wrong conclusions and as a result making bad recommendations. At the same time there is very much the reality that faster ghz does improve some percentage of the execution, but another percentage suffers, and is there a net gain or loss. Or a new processor design faster or slower may have features that perform better than an older processor, but not all feature will be better, there is a tradeoff and then we get into what "better" means.

How can I force an L2 cache miss?

I want to study the effects of L2 cache misses on CPU power consumption. To measure this, I have to create a benchmarks that gradually increase the working set size such that core activity (micro-operations executed per cycle) and L2 activity (L2 request per cycle) remain constant, but the ratio of L2 misses to L2 requests increases.
Can anyone show me an example of C program which forces "N" numbers of L2 cache misses?
You can generally force cache misses at some cache level by randomly accessing a working set larger than that cache level1.
You would expect the probability of any given load to be a miss to be something like: p(hit) = min(100, C / W), and p(miss) = 1 - p(hit) where p(hit) and p(miss) are the probabilities of a hit and miss, C is the relevant cache size, and W is the working set size. So for a miss rate of 50%, use a working set of twice the cache size.
A quick look at the formula above shows that p(miss) will never be 100%, since C/W only goes to 0 as W goes to infinity (and you probably can't afford an infinite amount of RAM). So your options are:
Getting "close enough" by using a very large working set (e.g., 4 GB gives you a 99%+ miss chance for a 256 KB), and pretending you have a miss rate of 100%.
Applying the formula to determine the actual expected number of misses. E.g., if you are using a working size of 2560 KB against an L2 cache of 256 KB, you have a miss rate of 90%. So if you want to examine the effect of 1,000 misses, you should make 1000 / 0.9 = ~1111 memory access to get about 1,000 misses.
Use any approximate approach but then actually count the number of misses you incur using the performance counter units on your CPU. For example, on Linux you could use PAPI or on Linux and Windows you could use Intel's PCM (if you are using Intel hardware).
Use an "almost random" approach to force the number of misses you want. The formula above is valid for random accesses, but if you choose you access pattern so that it is random with the caveat that it doesn't repeat "recent" accesses, you can get a 100% miss ratio. Here "recent" means accesses to cache lines that are likely to still be in the cache. Calculating what that means exactly is tricky, and depends in detail on the associativity and replacement algorithm of the cache, but if you don't repeat any access that has occurred in the last cache_size * 10 accesses, you should be pretty safe.
As for the C code, you should at least show us what you've tried. A basic outline is to create a vector of bytes or ints or whatever with the required size, then to randomly access that vector. If you make each access dependent on the previous access (e.g., use the integer read to calculate the index of the next read) you will also get a rough measurement of the latency of that level of cache. If the accesses are independent, you'll probably have several outstanding misses to the cache at once, and get more misses per unit time. Which one you are interested in depend on what you are studying.
For an open source project that does this kind of memory testing across different stride and working set sizes, take a look at TinyMemBench.
1 This gets a bit trickier for levels of caches that are shared among cores (usually L3 for recent Intel chips, for example) - but it should work well if your machine is pretty quiet while testing.

Faster cpu wastes more time as compared to slower cpu

Suppose I have a program that has an instruction to add two numbers and that operation takes 10 nanoseconds(constant, as enforced by the gate manufactures).
Now I have 3 different processors A, B and C(where A< B < C in terms of clock cycles). A's one clock cycle has 15 nanosec, B has 10 nanosec and C has 7 nanosec.
Firstly am I correct on my following assumptions-
1. Add operation takes 1 complete cycle of processor A(slow processor) and wastes rest of 5 ns of the cycle.
2. Add operation takes 1 complete cycle of processor B wasting no time.
3. Add operation takes 2 complete cycles(20 ns) of processor C(fast processor) wasting rest of the 20-14=7 ns.
If the above assumptions are correct then isn't this a contradiction to the regular assumption that processors with high clock cycles are faster. Here processor C which is the fastest actually takes 2 cycles and wastes 7ns whereas, the slower processor A takes just 1 cycle.
Processor C is fastest, no matter what. It takes 7 ns per cycle and therefore performs more cycles than A and B. It's not C's fault that the circuit is not fast enough. If you would implement the addition circuit in a way that it gives result in 1 ns, all processors will give the answer in 1 clock cycle (i.e. C will give you the answer in 7ns, B in 10ns and A in 15ns).
Firstly am I correct on my following assumptions-
1. Add operation takes 1 complete cycle of processor A(slow processor) and wastes rest of 5 ns of the cycle.
2. Add operation takes 1 complete cycle of processor B wasting no time.
3. Add operation takes 2 complete cycles(20 ns) of processor C(fast processor) wasting rest of the 20-7=13 ns.
No. It is because you are using incomplete data to express the time for an operation. Measure the time taken to finish an operation on a particular processor in clock cycles instead of nanoseconds as you are doing here. When you say ADD op takes 10 ns and you do not mention the processor on which you measured the time for the ADD op, the time measurement in ns is meaningless.
So when you say that ADD op takes 2 clock cycles on all three processors, then you have standardized the measurement. A standardized measurement can then be translated as:
Time taken by A for addition = 2 clock cycles * 15 ns per cycle = 30 ns
Time taken by B for addition = 2 clock cycles * 10 ns per cycle = 20 ns
Time taken by C for addition = 2 clock cycles * 07 ns per cycle = 14 ns
In case you haven't noticed, when you say:
A's one clock cycle has 15 nanosec, B has 10 nanosec and C has 7 nanosec.
which of the three processors is fastest?
Answer: C is fastest. It's one cycle is finished in 7ns. It implies that it finishes 109/7 (~= 1.4 * 108) cycles in one second, compared to B which finishes 109/10 (= 108) cycles in one second, compared to A which finishes only 109/15 (~= 0.6 * 108) cycles in one second.
What does a ADD instruction mean, does it purely mean only and only ADD(with operands available at the registers) or does it mean getting
the operands, decoding the instruction and then actually adding the
numbers.
Getting the operands is done by MOV op. If you are trying to compare how fast ADD op is being done, it should be compared by time to perform ADD op only. If you, on the other hand want to find out how fast addition of two numbers is being done, then it will involve more operations than simple ADD. However, if it's helpful, the list of all Original 8086/8088 instructions is available on Wikipedia too.
Based on the above context to what add actually means, how many cycles does add take, one or more than one.
It will depend on the processor because each processor may have the adder differently implemented. There are many ways to generate addition of two numbers. Quoting Wikipedia again - A full adder can be implemented in many different ways such as with a custom transistor-level circuit or composed of other gates.
Also, there may be pipelining in the instructions which can result in parallelizing of the addition of the numbers resulting in huge time savings.
Why is clock cycle a standard since it can vary with processor to processor. Shouldn't nanosec be the standard. Atleast its fixed.
Clock cycle along with the processor speed can be the standard if you want to tell the time taken by a processor to execute an instruction. Pick any two from:
Time to execute an instruction,
Processor Speed, and
Clock cycles needed for an instruction.
The third can be derived from it.
When you say the clock cycles taken by ADD is x and you know the processor speed is y MHz, you can calculate that the time to ADD is x / y. Also, you can mention the time to perform ADD as z ns and you know the processor speed is same y MHz as earlier, you can calculate the cycles needed to execute ADD as y * z.
I'm no expert BUT I'd say ...
the regular assumption that processors with high clock cycles are faster FOR THE VAST MAJORITY OF OPERATIONS
For example, a more intelligent processor might perform an "overhead task" that takes X ns. The "overhead task" might make it faster for repetitive operations but might actually cause it to take longer for a one-off operation such as adding 2 numbers.
Now, if the same processor performed that same operation 1 million times, it should be massively faster than the slower less intelligent processor.
Hope my thinking helps. Your feedback on my thoughts welcome.
Why would a faster processor take more cycles to do the same operation than a slower one?
Even more important: modern processors use Instruction pipelining, thus executing multiple operations in one clock cycle.
Also, I don't understand what you mean by 'wasting 5ns', the frequency determines the clock speed, thus the time it takes to execute 1 clock. Of course, cpu's can have to wait on I/O for example, but that holds for all cpu's.
Another important aspect of modern cpu's are the L1, L2 and L3 caches and the architecture of those caches in multicore systems. For example: if a register access takes 1 time unit, a L1 cache access will take around 2 while a normal memory access will take between 50 and 100 (and a harddisk access would take thousands..).
This is actually almost correct, except that on processor B taking 2 cycles means 14ns, so with 10ns being enough the next cycle starts 4ns after the result was already "stable" (though it is likely that you need some extra time if you chop it up, to latch the partial result). It's not that much of a contradiction, setting your frequency "too high" can require trade-offs like that. An other thing you might do it use more a different circuit or domino logic to get the actual latency of addition down to one cycle again. More likely, you wouldn't set addition at 2 cycles to begin with. It doesn't work out so well in this case, at least not for addition. You could do it, and yes, basically you will have to "round up" the time a circuit takes to an integer number of cycles. You can also see this in bitwise operations, which take less time than addition but nevertheless take a whole cycle. On machine C you could probably still fit bitwise operations in a single cycle, for some workloads it might even be worth splitting addition like that.
FWIW, Netburst (Pentium 4) had staggered adders, which computed the lower half in one "half-cycle" and the upper half in the next (and the flags in the third half cycle, in some sense giving the whole addition a latency of 1.5). It's not completely out of this world, though Netburst was over all, fairly mad - it had to do a lot of weird things to get the frequency up that high. But those half-cycles aren't very half (it wasn't, AFAIK, logic that advanced on every flank, it just used a clock multiplier), you could also see them as the real cycles that are just very fast, with most of the rest of the logic (except that crazy ALU) running at half speed.
Your broad point that 'a CPU will occasionally waste clock cycles' is valid. But overall in the real world, part of what makes a good CPU a good CPU is how it alleviates this problem.
Modern CPUs consist of a number of different components, none of whose operations will end up taking a constant time in practice. For example, an ADD instruction might 'burst' at 1 instruction per clock cycle if the data is immediately available to it... which in turn means something like 'if the CPU subcomponents required to fetch that data were immediately available prior to the instruction'. So depending on if e.g. another subcomponent had to wait for a cache fetch, the ADD may in practice take 2 or 3 cycles, say. A good CPU will attempt to re-order the incoming stream of instructions to maximise the availability of subcomponents at the right time.
So you could well have the situation where a particular series of instructions is 'suboptimal' on one processor compared to another. And the overall performance of a processor is certainly not just about raw clock speed: it is as much about the clever logic that goes around taking a stream of incoming instructions and working out which parts of which instructions to fire off to which subcomponents of the chip when.
But... I would posit that any modern chip contains such logic. Both a 2GHz and a 3GHz processor will regularly "waste" clock cycles because (to put it simply) a "fast" instruction executed on one subcomponent of the CPU has to wait for the result of the output from another "slower" subcomponent. But overall, you will still expect the 3GHz processor to "execute real code faster".
First, if the 10ns time to perform the addition does not include the pipeline overhead (clock skew and latch delay), then Processor B cannot complete an addition (with these overheads) in one 10ns clock cycle, but Processor A can and Processor C can still probably do it in two cycles.
Second, if the addition itself is pipelined (or other functional units are available), then a subsequent non-dependent operation can begin executing in the next cycle. (If the addition was width-pipelined/staggered (as mentioned in harold's answer) then even dependent additions, logical operations and left shifts could be started after only one cycle. However, if the exercise is constraining addition timing, it presumably also prohibits other optimizations to simplify the exercise.) If dependent operations are not especially common, then the faster clock of Processor C will result in higher performance. (E.g., if a dependence stall occurred every fourth cycle, then, ignoring other effects, Processor C can complete four instructions every five 7ns cycles (35 ns; the first three instruction overlap in execution) compared to 40ns for Processor B (assuming the add timing included pipelining overhead).) (Note: Your assumption 3 is incorrect, two cycles for Processor C would be 14ns.)
Third, the extra time in a clock cycle can be used to support more complex operations (e.g., preshifting one operand by a small immediate value and even adding three numbers — a carry-save adder has relatively little delay), to steal work from other pipeline stages (potentially reducing the number of pipeline stages, which generally reduces branch misprediction penalties), or to reduce area or power by using simpler logic. In addition, the extra time might be used to support a larger (or more associative) cache with fixed latency in cycles, reducing miss rates. Such factors can compensate for the "waste" of 5ns in Processor A.
Even for scalar (single issue per cycle) pipelines clock speed is not the single determinant of performance. Design choices become even more complex when power, manufacturing cost (related to yield, adjusted according to sellable bins, and area), time-to-market (and its variability/predictability), workload diversity, and more advanced architectural and microarchitectural techniques are considered.
The incorrect assumption that clock frequency determines performance even has a name: the Megahertz myth.

Finding Average Penalty from AMAT

I can calculate penalty when I have a single cache. But I'm unsure what to do when I am presented with two L1 caches (one for data and one for instruction) that are accessed in parallel. I'm also unsure what to do when I'm presented with clock cycles instead of actual time such as ns.
How do I calculate the average miss penalty using these new parameters?
Do I just use the formula two times and then average the miss penalty or is there more to this?
AMAT = hit time + miss rate * miss penalty
For example I have the following values:
AMAT = 4 clock cycles
L1 data access = 2 clock cycle (also hit time)
L1 instruction access = 2 clock cycle (also hit time)
60% of instructions are loads and stores
L1 instruction miss rate = 1%
L1 data miss rate = 3%
How would these values fit into AMAT?
Short answer
The average memory access time (AMAT) is typically calculated by taking the total number of instructions and dividing it by the total number of cycles spent servicing the memory request.
Details
On page B-17 of Computer Architecture a Quantiative Approach, 5th edition AMAT is defined as:
Average memory access time = % instructions x (Hit time + instruction miss rate x miss penalty) + % data x (Hit time + Data miss rate x miss penalty)`.
As you can see in this formula each instruction counts for a single memory access and the instructions that operate on data (load/store) constitute an additional memory access.
Note that there are many simplifying instructions that are made when using AMAT, and depending on the performance analysis that you want to perform. The same textbook I quotes earlier notes that:
In summary, although the state of the art in defining and measuring
memory stalls for out-of-order processors is complex, be aware of the
issues because they significantly affect performance. The complexity
arises because out-of-order processors tolerate some latency due to
cache misses without hurting performance. Consequently, designers
normally use simulators of the out-of-order processor and memory when
evaluating trade-offs in the memory hierarchy to be sure that an
improvement that helps the average memory latency actually helps
program performance.
My point of including this quote is that in practice AMAT is used for getting an approximate comparison between various different option. And as a result there are always simplifying assumptions used. But generally the memory accesses for instructions and data are added together to get a total number of accesses when calculating AMAT, rather than being calculated separately.
The way I see it, since the L1 Instruction Cache and the L1 Data Cache are accessed in parallel, you should compute AMAT for Instructions and AMAT for data, and then take the largest value as the final AMAT.
In your example since the Data Miss Rate is higher than Instruction Miss Rate you can consider that during the time the CPU waits for data, it solves all the misses on the instruction cache.
If the measure unit is cycles you do the same as if it were nanoseconds. If you know the frequency of your processor, you can convert back the AMAT in nanoseconds.

Resources