I was reluctant to post this question at first as it seems like functionality that could be pretty fundamental to the way in which TFS manages work items, but I cannot find anything documented that covers it; how do I categorise TFS work items (more specifically, new tasks)?
I've created a bunch of tasks. Some may fall under 'solution setup', others fall under 'core development' for example. How do I represent this categorisation in TFS? Is it something I need to consider when I'm creating the new tasks? Or are the work items brought back in this way during the query?
There are a handful of ways that people typically categorize/organize their Tasks:
Group tasks by User Story. This is done by linking the WI's, and this information will show up in WI Queries, and on the Task Board (task board only available in tfs 2012 and up).
Use the Area field and Area hierarchy to categorize your Tasks. The Area hierarchy is typically used to represent a functional breakdown of your application, then applied to WI's to categorize them based on which functional area they affect.
Activity Field. There is a field on Task work items called Activity that by default that has the values: Deployment, Design, Development, Documentation, Testing, Requirements. This list can be customized by editing the Work Item Type Definition.
Surprisingly difficult to find anything on this. I was already using 'linked item' as I should, the problem was the query. I created a new query and set the type to 'Tree...' so that the hierarchical structure was pulled back in away that mimicked a tasks and sub-tasks structure.
We're using Redmine to log and track all of our tasks, bugs, and features. We have a one month release cycle and it's important to ensure that the order of the items in Redmine corresponds to the relative priority of each item, so that people are not working on less important stuff.
Currently to achieve this we created a custom field in Redmine called 'rank' and assigned each items a integer from 1-1000. This works initially but re-ranking items and reordering is just painful because the same item ends up being edited many times to get it in the correct place on the priority list. Is there any way to be able to drag and drop items to reorder them? I doubt we have a unique requirement, there must be some way other people are doing this??
Thanks for the help in advance,
Max
Have you looked at the Stuff To Do plugin from Eric Davis? It may be close to what you're looking for -
http://www.redmine.org/projects/redmine/wiki/PluginStuffToDo
https://github.com/edavis10/redmine-stuff-to-do-plugin
It doesn't look like there is an existing plugin to do this. It has been raised on the Redmine forums, but nothing seems to have come of it:
http://www.redmine.org/issues/9183
Thats right, There is no existing plugin to do that. Stuff_to_do is user-level organization of tasks assigned to him and drag-and-drop to recoorganize the tasks from/to 'current working list', 'recommended list of tasks' and 'available list of tasks'.
I kinda feel there should be an alternative to your requirement. Why should we rank the tasks? We should probably conduct scrum/stand-ups and assign list of tasks to each person and reorganize the order in the stuff_to_do plugin so that the developer checks off the tasks in his list.
Also you can group the related tasks together using 'Related Tasks' option in each issue. Add an issue to be a 'follower'/'predecessor' to an other issue.
Use better reporting using 'custom queries'
Use Redmine_whining plugin to remind developers.
These are just my view based on the exposure I got in the area of Agile Product Management and Redmine plugins
We use Vs2008/2010 with TFS 2010 for our source control, because it also lets us create custom work item types that we can use for project management, such as product backlog items and sprint backlog items.
One item thats not tracked (by machine) is build regression test tasks for release candidates. Our regression testing is part automated, part manual, and the manual part can take several days. Currently we use an excel spreadsheet with a list of all the test cases, and then the testers just fill in results and notes.
I've been proposing creating a build regression test template that contains each test case, default owner, and then when we want to do regression testing on a build, we can automatically create work items for every test in the template.
My argument is that if the regression test work is mandatory for the project, and the results should be tracked, then writing additional TFS work items make sense, especially since the work items can hold estimates, giving managers an idea of how much re-test time remains.
The argument against this is that we already have high level work items to capture the overall project test requirements, and the regression testing is basically a "re-test", so new work items would be duplicate.
My question: Is anyone else doing anything like this? Is it reasonable to use TFS to track outstanding re-test tasks?
Note: we don't own Visual Studio Test Professional
I think it's reasonable to go with your suggested solution. You should have another work item type for the "test tasks", that can be linked as children to the test requirement work items. Doing that, like you said, would allow you to track results, progress, reporting, etc. You can also add other fields like build number, tested by, tested date, etc. to the work item type for history, something that cannot be done with just one test requirement work item type.
Essentially, what you proposed is done in the ITestResult object in the Microsoft.TeamFoundation.TestManagement.Client.dll.
I was thinking that I’d rather only use the Task Work Item and ignore the Bug Work Item. This is my thinking as I set things up for my team. I’m on a quest to see why I shouldn’t do this. From my perspective a Task is either a new item or a bug item. There is no need to use two distinct Work Item Types. To make this happen in TFS I’ll start with the Bug Work Item and create a custom field (“Item Type”) to distinguish the two task types: new/bug. Both new tasks and bugs will share the same fields. Anyone see any major drawbacks to this approach?
The main reason Tasks/Issue/Bugs/etc are different work items are because the individual fields of each work type can be configured differently.
For example, by default, Bugs have a Triage property, Issues have Due date, Tasks have a Discipline. The States of a Bug (Active/Closed/Resolve) are different from an issue (Active/Closed).
By merging them into a single work item type you would loose the ability to configure each one uniquely.
Also, the rules followed when a Bug and Task are closed, for example, are generally different. Segregating them into work items allows a simpler rules set.
Work item type is also a standard column in all queries.
Overall, it depends on how extensively you are using Team Foundation. If your project is small, and the above don't matter, it's not going to hurt. Though I don't see much gain either.
I would suggest keeping Bug and dropping Task if you want to merge them. By default when you check in code and Resolve with a bug, it sets the status to Resolved and assigns it to whoever created it - usually a tester, but in your case possibly a PM. That person can then test to confirm the work is done and close it. You can set up alerts on their work items so they get an email and know that progress has happened. Alternatively if you use Task, when you Resolve at check in it is just closed. No alerts, no further testing. YMMV but on some of our projects we use Bug for things like "user would like to add a new report" and it fits our process well. (For others we keep the distinction for reporting purposes.)
It all boils down to 3 things:
Creation / prioritization
Reporting / Notifications
Completion workflow
Typically creation of a Task involves different fields than a Bug. For a bug you'll want to know things like environment found in, who notified you, severity, priority, etc.
For tasks you usually want to know the requestor, reason behind it, business unit impacted and iteration it is scheduled for. Tasks might be long term goals that result in new or enhanced functionality.
Reporting and Notifications of the two are generally different as well. PM's are going to track tasks to ensure deliverables are met, your tech support area is going to track bugs.
Next, bugs will generally result in hotfixes and service packs. Depending on severity this this might involve a high priority push through QA and release as quickly as possible. Tasks are more laid back and will go through all forms of regression and regular testing with a period of acceptance by the impacted business unit.
Finally, bugs may impact previous versions of your software. Tasks will almost always be for either the version currently under development or the one after that.
In short, they are fundamentally different things. They might share most fields in common, however by combining them you are restricting yourself in both reporting and workflows. Today this might be okay; however within the next month or next year this could seriously restrict you.
Considering that maintainence of work item types is an incredibly easy thing there is almost no benefit to merging them.
We've got a surprisingly complex workflow that needs to be monitored by a quasi-technical employees with an in-house webapp. There's about 30 steps, some of which are manual (editing), some are semi-automated stop points (like "the files have been received" or customer approval of certain templates), and some are completely automated (file conversion, search indexing, etc). The flowchart for all of these steps is large and complicated, and three people might be working on three completely different steps at any one time.
How would you present this vast amount of information as usefully as possible to your users? Just showing the whole diagram seems like the brute force solution. But it's big, and it'll likely get bigger as we do more things. Not to mention the complexity necessary to encode this entire diagram in HTML.
I assume you don't want to show these just for entertainment or mockery, but help the users along the way, automating as much as possible, document the process etc. It would probably help if you clearly define the goals or purpose of your app.
I don't see a point in showing the entire workflow, except for "debugging the business rules" or maybe the clients want to see it.
If your goal is to help users do their job, I would present the state of the "project" (or whatever term fits better) is at, and possible transitions to other states.
The State might be multiple mostly independent variables, e.g. one might describe the progress of content - e.g. "incomplete" / "complete" / "reviewed by 2nd staffer" / "signed off by 2nd staffer", others might contain a schedule that is developed in parallel, e.g. "test print date = not scheduled", "print date = not scheduled", "final delivery = tomorrow, preferredly yesterday".
A transition might be "Seint to customer for review", "mark as content-complete", "content modified", etc.
Is this what you have in mind?
I propose to divide your workflow in modules and represent the active state for each module.
A module is a subset of your main workflow. For example it could be divided by tasks, person, roles, department, etc. This will greatly simplify the representation of the workflow. Let's says someone is responsible for data entry at many critical moments. We can group all his tasks in one module (or sub-workflow) containing the same activities, inputs, outputs and conditions. Modules could be inter-dependants and related.
A state is where we are located in a module. In simple workflows there is only one active task. In real life we are multi-threaded! So maybe in one module many states could be active at the same time. The state also includes active inputs, outputs and memory bits.
An input is something required to perform an activity for evaluation a boolean condition. It could be a document, a piece of data, a signal...
An output is something resulting from a task: an information, a document, a signal...
Enough definitions?
Then simply convert your workflow into a LADDER LOGIC and you have your states!
See Ladder Logic definition on Wikipedia
You display only active states:
Active task(s) for the module
Inputs required / inputs confirmed
Output required / output realized
Conditions to continue
Seems abstract?
Here is a small example...
Janet enters data in the system. She manages the green tasks of the diagram. We focus only on her work, not other tasks. She knows how to do 16 tasks in the workflow. We are waiting the following actions from her to continue, and her Intranet dashboard says:
Priority 1: You must send a PO to order enough pencils for the next month based on the sales report.
Task: Send a purchase order
Inputs: Forecast report from the marketing department
Outputs: PO, vendor, item, quantity
Condition for completion: PO sent and order confirmation received from supplier
Priority 2: You must enter into the financial system the number of erasers rejected by production
Task: Data entry
Inputs: Reject count from production
Outputs: Number of rejects
Condition for completion: data entered and confirmed
We do a lot of troubleshooting on automated production systems having hundreds of thousands ladder steps (the workflow is too complex to be represented in a whole). When the system is blocked we look at each module and determine what inputs are missing to activation task completion.
Good luck!
This sounds like the sort of application for which BPEL is suited.
Of course you don't want to re-architect your system right now. But there are a number of BPEL implmentations out there, some of which include graphical editing tools. One of these might help you in your current situation, because they are good at handling scope and hiding detail. So I think you might derive benefit from drawing your workflow as a BPEL diagram even if you don't do anything else with the language.
The Wikipedia page lists several of the available implementations. In addition, Oracle's JDeveloper IDE includes a BPEL Diagrammer as part of its SOA suite; unfortunately it is no longer part of the standard install but it is still available. Find out more.
Try doing it in layers. You have the most detailed layer done, now add additional docs with the details hidden, grouped into higher-level business processes. Users should be able to safely ignore some of those details, but it's good for them to have visibility of how their part fits in to the whole.
You may need more than one higher-level document.
You can use Prezi to present this information to users in a lucid manner.
Split and present the work flow into phases such that the end user is easily able to identify the phase he is currently in.
Display as many number of phases as the number of inputs. The workflow starts with 6 different inputs so display the six different buttons on screen enabling the user to select the input that he wants.
On selecting the button zoom into the workflow depicting the next steps. This would also help the user to verify the actions that he has done so far to reach the current states.
This would also help the user to verify the actions that he has done so far to reach the current states. But this way of presenting could become cumbersome for the users as the number of steps that he has completed goes up. Say the user has almost reached the end of the workflow. To check for the next step he should go through all the steps which might frustrate the user.
To avoid this you can split the complete work flow chronologically into 3-5 phases. The phases should be split logically. The ultimate aim would be not to overwhelm the users with the full work flow. Personally i would try to avoid the task involving this workflow if presented the way you have shown. No offense. I bet you also feel the same.
Could give you a better picture if you could re-post the image after replacing the state names with numbers.
I'd recommend having the whole flow documented somewhere, but in terms of what is distributed to users, how about focusing on task-oriented flows? No one user will be responsible for the entire process I would imagine.
For example, let's say I have 2 roles, A and B, and 6 tasks, 1 through 6, executed in order. Each task may have multiple steps but is self-contained (e.g. download the file, review, run process, review again, upload). A does the even tasks and B does the odd tasks.
A would need to know about those detailed steps that comprise tasks 2, 4, and 6 but not about what goes on in 1, 3, and 5. So hand A a detailed set of flows for the tasks he is responsible for, along with a diagram that treats each task as a black box.
If the flow can't be made modular in this way, you may want to review the process itself to see why it's so complex.
How about showing an example of a workflow scenario, that is, showing the transitions in one possible passing through the workflow? You could cater this to a specific user profile and highlight the pertinent states, dimming the others. This allows them to get a clear idea of the transitions by seeing a real-life example.