How to set the VCORES in hadoop mapreduce/yarn? - hadoop

The following are my configuration :
**mapred-site.xml**
map-mb : 4096 opts:-Xmx3072m
reduce-mb : 8192 opts:-Xmx6144m
**yarn-site.xml**
resource memory-mb : 40GB
min allocation-mb : 1GB
the Vcores in hadoop cluster displayed 8GB but i dont know how the computation or where to configure it.
hope someone could help me.

Short Answer
It most probably doesn't matter, if you are just running hadoop out of the box on your single-node-cluster or even a small personal distributed cluster. You just need to worry about memory.
Long Answer
vCores are used for larger clusters in order to limit CPU for different users or applications. If you are using YARN for yourself there is no real reason to limit your container CPU. That is why vCores are not even taken into consideration by default in Hadoop !
Try setting your available nodemanager vcores to 1. It doesn't matter ! Your number of containers will still be 2 or 4 .. or whatever the value of :
yarn.nodemanager.resource.memory-mb / mapreduce.[map|reduce].memory.mb
If really do want the number of containers to take vCores into consideration and be limited by :
yarn.nodemanager.resource.cpu-vcores / mapreduce.[map|reduce].cpu.vcores
then you need to use a different a different Resource Calculator. Go to your capacity-scheduler.xml config and change DefaultResourceCalculator to DominantResourceCalculator.
In addition to using vCores for container allocation, you want to use vCores to really limit CPU usage of each node ? You need to change even more configurations to use the LinuxContainerExecutor instead of the DefaultContainerExecutor, because it can manage linux cgroups which are used to limit CPU resources. Follow this page if you want more info on this.

yarn.nodemanager.resource.cpu-vcores - Number of CPU cores that can be allocated for containers.
mapreduce.map.cpu.vcores - The number of virtual CPU cores allocated for each map task of a job
mapreduce.reduce.cpu.vcores - The number of virtual CPU cores for each reduce task of a job

I accidentally came across this question and I eventually managed to find the answers that I needed, so I will try to provide a complete answer.
Entities and they relations For each hadoop application/job, you have an Application Master that communicates with the ResourceManager about available resources on the cluster. The ResourceManager receives information about available resources on each node from each NodeManager. The resources are called Containers (memory and CPU). For more information see this.
Resource declaration on the cluster Each NodeManager provides information about its available resources. Relevant settings are yarn.nodemanager.resource.memory-mb and yarn.nodemanager.resource.cpu-vcores in $HADOOP_CONF_DIR/yarn-site.xml. They declare the memory and cpus that can be allocated to Containers.
Ask for resources For your jobs you can configure what resources are needed by each map/reduce. This can be done as follows (this is for the map tasks).
conf.set("mapreduce.map.cpu.vcores", "4");
conf.set("mapreduce.map.memory.mb", "2048");
This will ask for 4 virtual cores and 2048MB of memory for each map task.
You can also configure the resources that are necessary for the Application Master the same way with the properties yarn.app.mapreduce.am.resource.mb and yarn.app.mapreduce.am.resource.cpu-vcores.
Those properties can have default values in $HADOOP_CONF_DIR/mapred-default.xml.
For more options and default values I would recommend you to take a look at this and this

Related

Suggestions required in increasing utilization of yarn containers on our discovery cluster

Current Setup
we have our 10 node discovery cluster.
Each node of this cluster has 24 cores and 264 GB ram Keeping some memory and CPU aside for background processes, we are planning to use 240 GB memory.
now, when it comes to container set up, as each container may need 1 core, so max we can have 24 containers, each with 10GB memory.
Usually clusters have containers with 1-2 GB memory but we are restricted with the available cores we have with us or maybe I am missing something
Problem statement
as our cluster is extensively used by data scientists and analysts, having just 24 containers does not suffice. This leads to heavy resource contention.
Is there any way we can increase number of containers?
Options we are considering
If we ask the team to run many tez queries (not separately) but in a file, then at max we will keep one container.
Requests
Is there any other way possible to manage our discovery cluster.
Is there any possibility of reducing container size.
can a vcore (as it's a logical concept) be shared by multiple containers?
Vcores are just a logical unit and not in anyway related to a CPU core unless you are using YARN with CGroups and have yarn.nodemanager.resource.percentage-physical-cpu-limit enabled. Most tasks are rarely CPU-bound but more typically network I/O bound. So if you were to look at your cluster's overall CPU utilization and memory utilization, you should be able to resize your containers based on the wasted (spare) capacity.
You can measure utilization with a host of tools but sar, ganglia and grafana are the obvious ones but you can also look at Brendan Gregg's Linux Performance tools for more ideas.

Yarn - make hadoop use more resources

As you can see, this node contains 3 containers (which is using 6GB memory and 3 vCores). I would like it to use rest of the vCores ( 5 vCores in vCores Avail column). I've not done any configuration on the yarn-site.xml yet.
Yarn uses only the resources that it needs
What you are currently looking at seems to be the resources currently used by the running jobs.
Yarn knows that it is allowed to use 2GB more memory and 5 more vcores, but it seems that by the nature of the job these can simply not be utilized.
Hence, it is not likely a problem, or somethign that needs to be fixed but just a matter of you running job of this nature.
Example
When I say a job of this nature, I mean a job for which it is not required to use 3 containers of 2 GB each.
The most simple example of such a job would be a count of 3 comparatively small files with a default container size of 2 GB.
If you really would want to run this kind of job more in parrallel, you would need to resort to workarounds (like setting a tiny maximum container size, or splitting all files in half). However, I would not recommend this.

How can I determine the correct number of YARN containers?

My question is about the configuration of YARN.
How can I determine how many containers I need in my cluster?
In other words, what have i to consider to set the correct amount of memory/cpu per container?
There are some best practices for the sizing?
Thanks.
can't comment from a hortonworks, but the sizing should be the same as cloudera
CPU
1 vcore dedicated to the os
1 vcore to the hdfs datanode
1 vcore for the node manager
1 vcore for the vendor agent (this is purely for cloudera, assume there is an ambari equivalent)
All the others I would assign to yarn containers. I would assign a vcore multiplayer to 4
RAM
Reserve some for you OS, it depends on your os but it would be between 4-8GB
take away ram for your hdfs datanode & your nodemanager (min 1gb each)
Take away any additional ram reserved for other services
Assign the rest for yarn.

In YARN, how is the container size determined?

In YARN application, how does ApplicationMaster decide on the size of the container? I understand there are parameters controlling on the minimum memory allocation, vcores ratio etc. But how does application master understand that it needs so much amount of memory and so many CPUs for a particular job - either MapReduce / Spark?
First let me explain in one or two lines how YARN works then we go through the questions.
So let's assume we have 100GB of total YARN cluster memory and 1GB minimum-allocation-mb, then we have 100 max containers. If we set the minimum allocation to 4GB, then we have 25 max containers.
Each application will get the memory it asks for rounded up to the next container size. So if the minimum is 4GB and you ask for 4.5GB you will get 8GB.
If the job/task Memory requirement is bigger than the allocated container size, in which case it will shoot down this container.
Now coming back to your original question, how YARN application master decide how much amount of Memory and CPU is required for a particular job.
YARN Resource Manager (RM) allocates resources to the application through logical queues which include memory, CPU, and disks resources.
By default, the RM will allow up to 8192MB ("yarn.scheduler.maximum-allocation-mb") to an Application Master (AM) container allocation request.
The default minimum allocation is 1024MB ("yarn.scheduler.minimum-allocation-mb").
The AM can only request resources from the RM that are in increments of ("yarn.scheduler.minimum-allocation-mb") and do not exceed ("yarn.scheduler.maximum-allocation-mb").
The AM is responsible for rounding off ("mapreduce.map.memory.mb") and ("mapreduce.reduce.memory.mb") to a value divisible by the ("yarn.scheduler.minimum-allocation-mb").
RM will deny an allocation greater than 8192MB and a value not divisible by 1024MB.
Following YARN and Map-Reduce parameters need to set to change the default Memory requirement:-
For YARN
yarn.scheduler.minimum-allocation-mb
yarn.scheduler.maximum-allocation-mb
yarn.nodemanager.vmem-pmem-ratio
yarn.nodemanager.resource.memory.mb
For MapReduce
mapreduce.map.java.opts
mapreduce.map.memory.mb
mapreduce.reduce.java.opts
mapreduce.reduce.memory.mb
So conclusion is that, application master doesn't use any logic to calculate resources (memory/CPU) requirement for a particular job. It simply use above mentioned parameters value for it.
If any jobs doesn't complete in given container size (including virtual Memory), then node manager simply kill the container.

Why more memory on hadoop map task make mapreduce job slower?

I want to ask. Why if I configured on mapred-site.xml in mapreduce.map/reduce.memory.mb and mapreduce.map/reduce.java.opts to bigger value than default value make my job slower?
But If I configured it too low, then I'll get task failed. And I think on this condition, my memory configuration on hadoop is not necessary...
Can you give me an explanation?
What might be happening in your environment is, when you increase values of the mapreduce.map/reduce.memory.mb and mapreduce.map/reduce.java.opts configurations to upper bound, it actually reduces the number of containers allowed to execute Map/Reduce task in every node thus eventually causes the slowness in the over all job time.
If you have 2 nodes, each with 25 GB of free ram , and say you configured the mapreduce.map/reduce.memory.mb as 4 GB, then you might get atleast 6 containers on every node, totally it is 12. So you would get a chance of running 12 mapper/reducer tasks in parallel.
In case if you configure mapreduce.map/reduce.memory.mb as 10 GB , then you might get only 2 containers on every node , totally it would be 4 containers to execute your mapper/reducer tasks in parallel. So the mapper/reducer tasks would mostly run in sequence due to lack of free containers, thus causes a delay in the over all job completion time.
You should justify the approprite value for the configuration with considering the resources available and the amount of resources required for the Map/Reduce containers according to your environment. Hope this makes sense.
you can allocate memory for map/reduce containers based on two factors
available memory per each Datanode
total number of cores(vcores) you have.
try to create number of containers equivalent to number of cores you have in each detained. ( including hyper threading)
for example if you have 10 physical core ( 20 cores including hyper threading)
so total number containers you can plan is 19 ( leaving 1 core for other processes)
assume that you have 'X' GB Ram in each data node, then
leave some memory(assume Y GB) for other processes (heap) like, Datanode, Node Manager,Region server ,etc
Now memory available for YARN is X -Y = Z
Memory for Map container = Y/number of containers per node
Memory for Reduce container = Y/(2 * number of containers per node)