Love some guidance on this problem:
G is a directed acyclic graph. You want to move from vertex c to vertex z. Some edges reduce your profit and some increase your profit. How do you get from c to z while maximizing your profit. What is the time complexity?
Thanks!
The problem has an optimal substructure. To find the longest path from vertex c to vertex z, we first need to find the longest path from c to all the predecessors of z. Each problem of these is another smaller subproblem (longest path from c to a specific predecessor).
Lets denote the predecessors of z as u1,u2,...,uk and dist[z] to be the longest path from c to z then dist[z]=max(dist[ui]+w(ui,z))..
Here is an illustration with 3 predecessors omitting the edge set weights:
So to find the longest path to z we first need to find the longest path to its predecessors and take the maximum over (their values plus their edges weights to z).
This requires whenever we visit a vertex u, all of u's predecessors must have been analyzed and computed.
So the question is: for any vertex u, how to make sure that once we set dist[u], dist[u] will never be changed later on? Put it in another way: how to make sure that we have considered all paths from c to u before considering any edge originating at u?
Since the graph is acyclic, we can guarantee this condition by finding a topological sort over the graph. topological sort is like a chain of vertices where all edges point left to right. So if we are at vertex vi then we have considered all paths leading to vi and have the final value of dist[vi].
The time complexity: topological sort takes O(V+E). In the worst case where z is a leaf and all other vertices point to it, we will visit all the graph edges which gives O(V+E).
Let f(u) be the maximum profit you can get going from c to u in your DAG. Then you want to compute f(z). This can be easily computed in linear time using dynamic programming/topological sorting.
Initialize f(u) = -infinity for every u other than c, and f(c) = 0. Then, proceed computing the values of f in some topological order of your DAG. Thus, as the order is topological, for every incoming edge of the node being computed, the other endpoints are calculated, so just pick the maximum possible value for this node, i.e. f(u) = max(f(v) + cost(v, u)) for each incoming edge (v, u).
Its better to use Topological Sorting instead of Bellman Ford since its DAG.
Source:- http://www.utdallas.edu/~sizheng/CS4349.d/l-notes.d/L17.pdf
EDIT:-
G is a DAG with negative edges.
Some edges reduce your profit and some increase your profit
Edges - increase profit - positive value
Edges - decrease profit -
negative value
After TS, for each vertex U in TS order - relax each outgoing edge.
dist[] = {-INF, -INF, ….}
dist[c] = 0 // source
for every vertex u in topological order
if (u == z) break; // dest vertex
for every adjacent vertex v of u
if (dist[v] < (dist[u] + weight(u, v))) // < for longest path = max profit
dist[v] = dist[u] + weight(u, v)
ans = dist[z];
Related
Given a weighed, connected and directed graph G=(V,E) with n vertexes and m edges, and given a pre-calculated shortest path distance's matrix S where S is n*n S(i,j) denotes the weight of shortest path from vertex i to vertex j.
we know just weight of one edge (u, v) is changed (increased or decreased).
for two specific vertex s and t we want to update the shortest path length between these two vertex.
This can be done in O(1).
How is this possible? what is the trick of this answer?
You certainly can for decreases. I assume S will always refer to the old distances. Let l be the new distance between (u, v). Check if
S(s, u) + l + S(v, t) < S(s, t)
if yes then the left hand side is the new optimal distance between s and t.
Increases are impossible. Consider the following graph (edges in red have zero weight):
Suppose m is the minimum weight edge here, except for (u, v) which used to be lower. Now we update (u, v) to some weight l > m. This means we must find m to find the new optimum length.
Suppose we could do this in O(1) time. Then it means we could find the minimum of any array in O(1) time by feeding it into this algorithm after adding (u, v) with weight -BIGNUMBER and then 'updating' it to BIGNUMBER (we can lazily construct the distance matrix because all distances are either 0, inf or just the edge weights). That is clearly not possible, thus we can't solve this problem in O(1) either.
I am studying algorithms, and I have seen an exercise like this
I can overcome this problem with exponential time but. I don't know how to prove this linear time O(E+V)
I will appreciate any help.
Let G be the graph where the minimum spanning tree T is embedded; let A and B be the two trees remaining after (u,v) is removed from T.
Premise P: Select minimum weight edge (x,y) from G - (u,v) that reconnects A and B. Then T' = A + B + (x,y) is a MST of G - (u,v).
Proof of P: It's obvious that T' is a tree. Suppose it were not minimum. Then there would be a MST - call it M - of smaller weight. And either M contains (x,y), or it doesn't.
If M contains (x,y), then it must have the form A' + B' + (x,y) where A' and B' are minimum weight trees that span the same vertices as A and B. These can't have weight smaller than A and B, otherwise T would not have been an MST. So M is not smaller than T' after all, a contradiction; M can't exist.
If M does not contain (x,y), then there is some other path P from x to y in M. One or more edges of P pass from a vertex in A to another in B. Call such an edge c. Now, c has weight at least that of (x,y), else we would have picked it instead of (x,y) to form T'. Note P+(x,y) is a cycle. Consequently, M - c + (x,y) is also a spanning tree. If c were of greater weight than (x,y) then this new tree would have smaller weight than M. This contradicts the assumption that M is a MST. Again M can't exist.
Since in either case, M can't exist, T' must be a MST. QED
Algorithm
Traverse A and color all its vertices Red. Similarly label B's vertices Blue. Now traverse the edge list of G - (u,v) to find a minimum weight edge connecting a Red vertex with a Blue. The new MST is this edge plus A and B.
When you remove one of the edges then the MST breaks into two parts, lets call them a and b, so what you can do is iterate over all vertices from the part a and look for all adjacent edges, if any of the edges forms a link between the part a and part b you have found the new MST.
Pseudocode :
for(all vertices in part a){
u = current vertex;
for(all adjacent edges of u){
v = adjacent vertex of u for the current edge
if(u and v belong to different part of the MST) found new MST;
}
}
Complexity is O(V + E)
Note : You can keep a simple array to check if vertex is in part a of the MST or part b.
Also note that in order to get the O(V + E) complexity, you need to have an adjacency list representation of the graph.
Let's say you have graph G' after removing the edge. G' consists have two connected components.
Let each node in the graph have a componentID. Set the componentID for all the nodes based on which component they belong to. This can be done with a simple BFS for example on G'. This is an O(V) operation as G' only has V nodes and V-2 edges.
Once all the nodes have been flagged, iterate over all unused edges and find the one with the least weight that connects the two components (componentIDs of the two nodes will be different). This is an O(E) operation.
Thus the total runtime is O(V+E).
I have the following problem and I'm not quite sure how to solve it:
Given a graph G = (V;E) in which every edge e has a positive integer cost c_e and a starting vertex s\in V . Design an O(V + E) algorithm that marks all vertices reachable from s using a path (not necessarily a simple path) with the total cost of that path being multiples of 5.
How can I keep track of the total amount of cost of the path that I've already visited? I've been studying about BFS in undirected weighted graphs and made some attempts on using it here, but most of the BFS references focus on finding the shortest path (and not something like keep it multiple of 5).
What do you think about the next algorithm?
Let's consider new directed graph based on the source graph. For every vertex v from the source graph create 5 new vertexes v[0], v[1], ..., v[4] in the new graph corresponding to the modules from the division by 5. Then, if vertexes v and u were connected in the source graph by the edge with the weight w, add edge between v[i] and u[(i + w) % 5], u[j] and v[(j + w) % 5] in the new graph, where i = 0..4, j = 0..4. Then run BFS from the v[0], where v is the starting vertex in the source graph.
Consider vertexes with the index 0 like v[0]. Each of them corresponding to the path of the length multiple of 5 to the vertex v in the source graph. All of such vertexes marked after BFS as reachable from the starting vertex form the answer. Total complexity is linear.
I'm pretty sure this problem is P and not NP, but I'm having difficulty coming up with a polynomially bound algorithm to solve it.
You can :
check that number of edges in the graph is n(n-1)/2.
check that each vertice is connected to exaclty n-1 distinct vertices.
This will run in O(V²), which is polynomial.
Hope it helped.
Here's an O(|E|) algorithm that also has a small constant.
It's trivial to enumerate every edge in a complete graph. So all you need to do is scan your edge list and verify that every such edge exists.
For each edge (i, j), let f(i, j) = i*|V| + j. Assuming vertices are numbered 0 to |V|-1.
Let bitvec be a bit vector of length |V|2, initialized to 0.
For each edge (i, j), set bitvec[f(i, j)] = 1.
G is a complete graph if and only if every element of bitvec == 1.
This algorithm not only touches E once, but it's also completely vectorizable if you have a scatter instruction. That also means it's trivial to parallelize.
Here is an O(E) algorithm:
Use O(E) as it is input time, to scan the graph
Meanwhile, record each vertex p's degree, increase degree only if the neighbor is not p itself (self-connecting edge) and is not a vertex q where p and q has another edge counted already (multiple edge), these checking can be done in O(1)
Check if all vertex's degree is |V|-1, this step is O(V), if Yes then it is a complete graph
Total is O(E)
For a given graph G = (V,E), check for each pair u, v in the V, and see if edge (u,v) is in E.
The total number of u, v pairs are |V|*(|V|-1)/2. As a result, with a time complexity of O(|V|^2), you can check and see if a graph is complete or not.
I'm trying to find out an efficient way of finding the shortest path between 2 nodes in a graph with positive edge costs that goes trough a subset of nodes.
More formally:
Given a graph G = (U, V) where U is the set of all nodes in the graph and V is the set of all edges in the graph, a subset of U called U' and a cost function say:
f : UxU -> R+
f(x, y) = cost to travel from node x to node y if there exists an edge
between node x and node y or 0 otherwise,
I have to find the shortest path between a source node and a target node that goes trough all the nodes in U'.
The order in which I visit the nodes in U' doesn't matter and I am allowed to visit a node more than once.
My original idea was to make use of Roy-Floyd algorithm to generate the cost matrix.
Then, for each permutation of the nodes in U' I would be computing the cost between the source and the target like this: f(source_node, P1) + f(P1, P2) + ... + f(Pk, target) saving the configuration for the lowest cost and then reconstructing the path.
The complexity for this approach is O(n3 + k!) O(n3 + k*k!), where n is the number of nodes in the graph and k the number of nodes in the subset U', which is off limits since I'll have to deal with graphs with maximum n = 2000 nodes out of which maximum n - 2 nodes will be part of the U' subset.
This is a generalization of travelling salesman. If U' == U, you get exactly TSP.
You can use the O(n^2 * 2^n) TSP algorithm, where the exponential factor for full scale TSP (2^n) will reduce to k = |U'|, so you'd get O(n^2 * 2^k).
This has the DP solution to TSP.
http://www.lsi.upc.edu/~mjserna/docencia/algofib/P07/dynprog.pdf
Combine the source node s and target node t into a single node z, and define the node set U'' := U' union {z}, with the distances to and from z defined by f(z,x) := f(s,x) and f(x,z) := f(x,t) for all x in U \ {s, t}. Compute shortest paths between all nodes of U'' and let f'(x,y) be the shortest distances, or infinity when there is no appropriate path. Voila, you now have a travelling salesman problem on the complete directed graph with vertices U'' and edge weights f'.