execute PACKAGE_BATCH.USP_TERMIANTE_SUSPENSION;
BEGIN
DBMS_SCHEDULER.CREATE_JOB (
job_name => '"LTR"."TERMINATE_SUSPENSION_JOB"',
job_type => 'STORED_PROCEDURE',
job_action => 'LTR.PACKAGE_BATCH.USP_TERMINATE_SUSPENSION',
number_of_arguments => 0,
start_date => sysdate,
repeat_interval => 'FREQ=MINUTELY;BYMINUTE=1',
end_date => NULL,
enabled => TRUE,
auto_drop => TRUE,
comments => 'Terminate Suspension When End Date is equal to Current Date');
DBMS_SCHEDULER.set_attribute
( name => '"LTR"."TERMINATE_SUSPENSION_JOB"',
attribute => 'job_action',
value => 'LTR.PACKAGE_BATCH.USP_TERMINATE_SUSPENSION');
DBMS_SCHEDULER.SET_ATTRIBUTE(
name => '"LTR"."TERMINATE_SUSPENSION_JOB"',
attribute => 'logging_level', value => DBMS_SCHEDULER.LOGGING_RUNS);
DBMS_SCHEDULER.enable(
name => '"LTR"."TERMINATE_SUSPENSION_JOB"');
END;

FREQ=MINUTELY;BYMINUTE=1
This will make the job run at every "1"st minute. So 12:01, 1:01, 2:01 etc.
If you need to make it run every minute - FREQ=MINUTELY is sufficient or you can add BYSECOND=0 if you want to ensure it runs at exactly 12:01:00, 12:02:00, 12:03:00 etc.

To keep it simple, see these examples:
Every minute
Repeat interval using calendaring syntax.
'freq=minutely;'
Repeat interval using dates and timestamps.
'sysdate + 1/24/60'
'systimestamp + 1/24/60'
'sysdate + interval ''1'' minute'
'systimestamp + interval ''1'' minute'
Every minute, on the minute
Repeat interval using calendaring syntax.
'freq=minutely; bysecond=0;'
Repeat interval using dates and timestamps.
'trunc(sysdate, ''MI'') + 1/24/60'
'trunc(systimestamp, ''MI'') + 1/24/60'
'trunc(sysdate, ''MI'') + interval ''1'' minute'
'trunc(systimestamp, ''MI'') + interval ''1'' minute'
More example here http://oracle-base.com/articles/10g/scheduler-10g.php#every_minute

Related

Use DBMS_SCHEDULER repeat_interval to run a task once in two days

I am trying to create a task (delete some cache data) that will run once in two days. This will run on Oracle 11g. So far I came up with the following anonymous block:
begin
DBMS_SCHEDULER.CREATE_JOB (
job_name => 'clear_cache',
job_type => 'PLSQL_BLOCK',
job_action => 'begin delete from MY_CACHE;commit; end;',
start_date => to_date('19/09/2016','dd/mm/rrrr')+ 19/24,
repeat_interval => 'to_date(''19/09/2016'',''dd/mm/rrrr'')+ 2 + 19/24',
enabled => TRUE);
end;
However, I am not sure about repeat_interval value..
Assuming that I will run this block today (15/09/2016), I want clear_cache to be executed on:
19/09/2016 at 7 p.m
21/09/2016 at 7 p.m.
23/09/2016 at 7 p.m.
etc
I know that if i use
start_date => sysdate,
repeat_interval => 'trunc(sysdate) + 7 + 7/24'
Then it will start execution today, will repeat every 7 days at 7 p.m., what I want,though, is to begin next Monday and repeat every 2nd day and I am not sure how to achieve that...
So, I would like to know what exactly to put into repeat_interval ...
Thanks.
It's worth using the built-in calendaring syntax rather than trying to roll your own. By stating that you want the job to run daily with an interval of 2 it will run every 2 days.
The syntax is FREQ=DAILY;INTERVAL=2, if you set the start date to 7pm then it'll start at that time in your current timezone.
The start_date parameter is a date, so you can use an actual date or timestamp here.
DBMS_SCHEDULER.CREATE_JOB (
job_name => 'clear_cache',
job_type => 'PLSQL_BLOCK',
job_action => 'begin delete from MY_CACHE; commit; end;',
start_date => timestamp '2016-09-19 19:00:00',
repeat_interval => 'FREQ=DAILY;INTERVAL=2',
enabled => TRUE);

Create oracle scheduler job which runs daily

I want to create oracle scheduler job which runs daily at 20:00 and runs for 30 minute. This job will delete the rows from KPI_LOGS table as this table contains large amount of data and it continues to grow. I have created the below script in oracle sql developer for such job but not sure if this is correct or not as i am new to scheduler job concept.
BEGIN
DBMS_SCHEDULER.CREATE_JOB (
job_name => '"RATOR_MONITORING"."CROP_KPI_LOGS"',
job_type => 'PLSQL_BLOCK',
job_action => 'DELETE FROM KPI_LOGS WHERE CAST(TIMESTAMP AS DATE) < (SYSDATE - 28);',
number_of_arguments => 0,
start_date => NULL,
repeat_interval => 'FREQ=DAILY;INTERVAL=30',
end_date => NULL,
enabled => FALSE,
auto_drop => FALSE,
comments => 'CROP_KPI_LOGS');
DBMS_SCHEDULER.SET_ATTRIBUTE(
name => '"RATOR_MONITORING"."CROP_KPI_LOGS"',
attribute => 'logging_level', value => DBMS_SCHEDULER.LOGGING_OFF);
DBMS_SCHEDULER.enable(
name => '"RATOR_MONITORING"."CROP_KPI_LOGS"');
END;
the repeat_internal is incorrect, what you have there will run every 30 days. to run at 8pm each day go for...
FREQ=DAILY; BYHOUR=20
you can't dictate how long it will run for, it will take as long as your DELETE statement takes

How to limit oracle job interval for a particular day ,(Monday)?

Hi i have to show one report and the report data should refresh on every monday.
automatically
I have checked oracle scheduler . i cant see any option for limiting the interval to monday
.
I am thinking to give start date as monday and repeat 7 days interval .
is it good way
Hi I got the answer.
YOU want to right like the code below.
There are 3 way for scheduling a job on every week day it can be every monday or another day
Here i have tried for running the job automatically on every monday 6 am
We have to set the frequency
either of the below code we can use
FREQ=DAILY; BYDAY=MON; BYHOUR=6; BYMINUTE=0; BYSECOND=0;
FREQ=WEEKLY; BYDAY=MON; BYHOUR=6; BYMINUTE=0; BYSECOND=0;
FREQ=YEARLY; BYDAY=MON; BYHOUR=6; BYMINUTE=0; BYSECOND=0;
begin
dbms_scheduler.create_job(
job_name => 'JOB_TEST',
job_type => 'PLSQL_BLOCK',
job_action => 'begin PROCEDURE_NAME; end;',
start_date => systimestamp,
end_date => null,
comments => 'job is created for running automatically on every monday',
enabled => true,
repeat_interval => 'FREQ=WEEKLY; BYDAY=MON; BYHOUR=0; BYMINUTE=0; BYSECOND=0;');
end;
In oracle We can write jobs using DBMS Scheduler or DBMS JOBS
DBMS Scheduler is the above example and its the advanced one,
IF you want to Do the same Problem Using DMBS JOBS
begin
sys.dbms_job.submit(job => :job,
what => 'procedure name;',
next_date => NEXT_DAY(TRUNC(SYSDATE),'MONDAY'),
interval => 'NEXT_DAY(TRUNC(SYSDATE),''MONDAY'')');
commit;
end;
/

Creating schedule at 2 specific hours in a day

I need a schedule to run at 08:35 and 09:46 every day.
I now how to make a shedule that runs at some hours, it goes like this:
dbms_scheduler.create_job(job_name => 'YOUR_JOB',
job_type => 'PLSQL_BLOCK',
job_action => 'integration_export;',
start_date => systimestamp,
repeat_interval => 'freq=hourly; byhour=8,10,12,14,16,18; byminute=0; bysecond=0;',
enabled => true,
auto_drop => false,
comments => 'some comment about the job');
But if I add the clause minutely then it runs on all these hours at those minutes.
How can I accomplish this?
Put start_date as date itself with exact time, 08:45. Use the date functions and format for that. Make two jobs, one for 8:45 other for 09:46.
start_date = to_date(to_char(trunc(sysdate) <add your time part with proper format>
Sorry, don't have database access to verify that. But, the logic is, start_date with only date part dynamically changing and keeping the time part constant should work.

DBMS_SCHEDULER JOBS Running at morning until night everyday

I want make JOBS use DBMS_SCHEDULER in oracle 10g, where jobs refresh minutely with interval 2 minute running everyday start at 08.00 AM and end at 08.00 PM. I have tried this code,
BEGIN
SYS.DBMS_SCHEDULER.CREATE_JOB
(
job_name => 'UPDATE_REKAP_BALI'
,start_date => trunc(sysdate) + 8/24
,repeat_interval => 'freq=MINUTELY;interval=2'
,end_date => trunc(sysdate) + 20/24
,job_class => 'DEFAULT_JOB_CLASS'
,job_type => 'STORED_PROCEDURE'
,job_action => 'UPDATEREKAPBALI'
,comments => NULL
);
END
but, when i check on the next day, the jobs is not running, i guess that the jobs is never running up again on 08.00 AM at the next day.
Make sure you commit after submitting the job.
Edit This is incorrect: DBMS_SCHEDULER performs an implicit commit, unlike the previous DBMS_JOB which required an explicit commit.
You have to make auto_drop to false , because auto drop will make the job to be dropped once after it is running , so make it as false
BEGIN
DBMS_SCHEDULER.CREATE_JOB (
job_name => 'TEST_J',
job_type => 'CHAIN',
job_action => 'TEST_C',
auto_drop => FALSE,
repeat_interval => 'FREQ=DAILY;BYHOUR=08,09,10,11,12,13,14,15,16,17,18,19;BYMINUTE=02,04,06,08,10,12,14,16,18,20,22,24,26,28,30,32,34,36,38,40,42,44,46,48,50,52,54,56,58,00;BYSECOND=00;',
enabled => TRUE);
END;
/
Auto Drop is enabled by default
http://docs.oracle.com/cd/B28359_01/appdev.111/b28419/d_sched.htm#i1000363
The answer is two links far
http://docs.oracle.com/cd/B19306_01/appdev.102/b14258/d_sched.htm#CIHGCDBJ - Table 93-54 Window Attribute Values
'repeat_interval' line in the table point to "Calendaring Syntax" link http://docs.oracle.com/cd/B19306_01/appdev.102/b14258/d_sched.htm#BABFBCEF where you can find out how to set a schedule in terms of Oracle

Resources