hellow, I am using dhtmlxgantt tool for project management in My laravel app. but in My time line I can only add till 2014-12-31 but I need increse My year till 2020. how can I do this.
It can be done in a couple of different ways
1) You can define range using start_date/end_date options
gantt.config.start_date = new Date(2016, 0, 1);
gantt.config.end_date = new Date(2021, 0, 1);
gantt.init();//or gantt.render() if gantt is already initialized
2) Alternatively, you can tell gantt to always recalculate the time scale in order to fit all data you have in gantt (by default such calculation happens only once when you load data)
gantt.config.fit_tasks = true;
Note, that you either set date range explicitly (define start/end dates), or tell gantt to calculate it automatically (use fit_tasks config), you can't enable both.
Then you can set the date picker range in the details form:
gantt.config.lightbox.sections=[
{name:"description", height:70, map_to:"text", type:"textarea",focus:true},
{name:"time", year_range: [2016, 2025] map_to:"auto", type:"duration"}
];
http://docs.dhtmlx.com/gantt/desktop__duration.html
Note, that gantt may become slow when you display huge date range. Usually, it can be fixed by enabling static_background mode and smart rendering extension. http://docs.dhtmlx.com/gantt/desktop__performance.html http://docs.dhtmlx.com/gantt/api__gantt_static_background_config.html
Related
The Format module
The Format module is used to model and combine pretty printers with a syntactic extension that allows typed formats and it helps a lot when you are writing something like a code generator or a data structure printer.
The problem
However, there is a limit of 78 columns that is initialized on the margin of the formatter and will pull to the left anything that takes more than this limit.
I'm printing a lighter version of a Yojson.Basic.json program using the Format module, but when the input is too large, the output is collapsed, and that is not really "prettily".
Preview
Here is how it is is formatted when it is short:
Here is how it is formatted when the indentation becomes too large
I've been trying to exceed and configure this limit to 120 columns, but didn't have any success.
What have I tried?
Using Format.pp_set_margin ppf 120 to reconfigure
Using Format.pp_set_max_indent to a larger value
But they doesn't seem to have any effect and there is no documentation easily available about this limit. I've discovered it only by reading the source code.
What am I doing?
let string_of_cst program =
let ppf = Format.str_formatter in
(* I've enabled colors. *)
Format.pp_set_tags ppf colors;
Format.pp_set_formatter_tag_functions ppf with_colors;
(* [print_json] is my printer. *)
print_json ppf program;
(* Get string out of printer. *)
Format.flush_str_formatter ()
How can I configure a larger limit?
The issue is that the values for margin and max_indent are implicitly constrained to the cone 1 < max_indent < margin and the function set_max_indent silently fails and does nothing if this constraint is not respected.
To avoid this issue, in OCaml ≥4.08, it would be possible to use the new set_geometry function that requires to set both value simultaneously and fails with an exception if the required max_indent is greater than the margin.
Otherwise, you should always set both values at the same time, and always in the order
margin first, and max_indent second. If you don't know which value to chose for max_indent, margin - 10 is generally an alright choice.
still learning about Ruby + Sketchup!
Today,I would like to add a measurement (good english word ?) as I can do manually with the 'cotation' (french version) tool when I click to point then drag the measure text.
Can't find that in the docs to do with Ruby and API ...
Thanks for your help
You are probably looking for the Sketchup::Entities::add_dimension_linear method.
http://ruby.sketchup.com/Sketchup/Entities.html#add_dimension_linear-instance_method
Assuming a and b below are edges
voffset = [-20, 0, 0]
Sketchup.active_model.entities.add_dimension_linear(a.start, b.start, voffset)
The value of voffset controls not just how far offset the dimension is, but also the axis along which the measurement is made. You may need to experiment with different values to get a feeling for how that determination is done. As with many things in SketchUp, it often guesses (or 'infers') at what you want.
I am using a Kendo spreadsheet to import data from an Excel file so I can plug it into an SQL Server database using Ajax callbacks. The Ajax callbacks work fine, but I have determined that any Date strings are being converted to an integer offset from a base date of 12/30/1899. I have submitted a support ticket to Telerik, but they do not seem to understand the problem.
The data is displayed in the Kendo spreadsheet appropriately as a date. Kendo converts a date input as "12/1/2015" to "12-1-2015".
I am using the latest version of the ASP.NET MVC 5 wrapper, but the JavaScript code is the 2016-1-226-545 version of the JavaScript. The wrapper version seems to be irrelevant, but later versions of the JavaScript have the gulpfile.js, and this conflicts with the Bundleconfig interface on my ASP.NET MVC 5 project, so I simply work with the last version of the JavaScript that works for my setup.
The spreadsheet I am working with is pretty basic to start:
#(
Html.Kendo().Spreadsheet()
.Name("SiteSlotDataSS")
.Rows(10)
.Columns(4).ColumnWidth(100)
.Sheets(sheets =>
{
sheets.Add()
.Name("Study Data");
}
)
)
I use the import option to pull in an Excel spreadsheet and use a simple button with a click event routine to copy the data to a string array to send to the Ajax callback. I have confirmed that the data being sent to the server controller is the same as it is on the client side before being sent. The Date conversion to an integer occurs when the values are extracted from the range.
The code in question that selects the values is:
values = sheet.range("A" + headerRows.toString() + ":" + endRange + (headerRows + rows).toString()).values();
This produces the correct translation of every other column except for columns containing dates.
I tried the following to brute-force the issue, without success:
for (var x = 0; x <= rows; x++) {
sheet.range("K" + (headerRows + x).toString()).format(kendo.spreadsheet.formatting.date);
}
I could try a date function to convert the date back into the original value, but everyone pretty much knows how Telerik's documentation is a bit skimpy and overall simply a nightmare to find answers to questions with.
What is the solution?
It appears that Kendo Spreadsheet stores the date values as an integer offset from 12/30/1899 in days. I determined the "0" value by entering a date of 1/1/1901 to see what came back, then 1/1/1900. The result of the latter was "2", making the base date 12/30/1899. Taking the data and converting it at the server seems to be the best option. I don't really expect much of a response from Telerik.
I have addressed the storage issue with Telerik, and they have acknowledged there is a bug in the spreadsheet widget.
For now, the solution is to bring the values array one row at a time back to the server and do the data conversion server-side. The integer that is returned in the values array for dates is the way the Kendo Spreadsheet stores the information client-side. Formatting the column simply will not do anything but change the client-side display. It will not change how Kendo returns the values matrix from the spreadsheet range selected.
Firstly, I think you mean 12/31/1899. It makes no sense to refer anything to 12/30/1899.
Excel dates start with 1/1/1900, just as do your Kendo (Japanese: "the way of the sword") dates. If you're getting an integer, forcibly coerce it to the corresponding date on the receiving by merely FORMATTING THE COLUMN. There is no need for a specific function to "convert" days-since-1900 counts to text dates (MM/DD/YYYY), as they are the SAME, differing only in human-readable representation.
Of course, it wasn't clear from your description whether Excel was on the input side or the output side of the problem.
I am using jfreecharts to vreate a value-time chart.
Data is gathered dynamically from web services and some times there are large numbers in it. The chart is created without any problem but the value axis
labels are of this format: 2E10 etc. I would like to have 20000000000 displayed. I have not find any solution after 2 hours of rsearching. Can anyone suggest something?
This fixed the problem:
NumberAxis rangeAxis = (NumberAxis) plot.getRangeAxis();
DecimalFormat newFormat = new DecimalFormat("0.0000");
rangeAxis.setNumberFormatOverride(newFormat);
It also works when you have a dataset with largest value a float with 0 as integer part and at least the first 3 decimal digits to be 0 in which case labels also appear in negative power of 10 by default.
I building a custom user control in asp.net where the user can enter in a date. I am already using a JQuery function that puts in a date mask in the format of dd/mm/yyyy, but I am unable to find another JQuery function(s) or one that combines all my needs.
What I am also looking for is:
1) To validate whether the date is really a date, i.e. not 31/13/2010 or anything along those lines.
2) Where I can check to see whether a date is in the past or in future based upon a configuration entry in the application.
Can anyone help me, please?
This is just off the top of my head, but you could use JavaScript's Date object http://www.w3schools.com/jsref/jsref_obj_date.asp
1) You could use one of the following
var d = new Date(dateString);
var d = new Date(year, month, day, hours, minutes, seconds, milliseconds);
Then verify that the date components are the same as entered. If you set the month to 50, it will take the year, and go 50 months forward... which seems odd, but... Just have to verify the information is what you entered. The months start at 0 for January, so when checking, be aware of that.
2) There's probably a lot of ways to do this check, but a quick thought on it is
var t = d.getTime() - new Date().getTime();
If t is positive, it's in the future, if it's negative it's in the past.
The new Date() creates a date object with the current time.
You could also use the jQuery UI DatePicker. http://jqueryui.com/demos/datepicker/
I haven't checking into the exact functionality it has that might fit your requirement, but it is another resource to check into.